(i) Development on a User's system already connected to the State Transmission System.
(ii) The introduction of a new Connection point between the User's system and the State Transmission System.
(iii) Evacuation system for Generating Stations within or outside the State.
(iv) Reactive Power Compensation.
(v) A general increase in system capacity (due to addition of generation or system load) to remove operating constraints and maintain standards of security.
(vi) Transient or steady state stability considerations.
(vii) Cumulative effect of any of the above.
• Defines the procedure for the exchange of information between STU and a User in respect of any proposed development on the User's system, which may have an impact on the performance of the User.
• Details the information which STU shall make available to Users in order to facilitate the identification and evaluation of opportunities for use of or connection to State Transmission System;
• Details the information required by STU from Users to enable STU to plan the development of its Transmission System to facilitate proposed User developments;
• Specifies planning and design standards, which will be applied by STU in planning and development of the power system.
(i) Forecast the demand for power within the Area of Supply, based on the forecasts provided by distribution licensees, and provide to the Commission details of the demand forecasts, data, methodology and assumptions on which the forecasts are based. For demand forecasting, the methodology and procedure followed by the Electric Power Survey Committee constituted by CEA may be followed. These forecasts would be annually reviewed and updated. The primary responsibility of load forecasting within distribution licensee's Area of Supply rests with respective distribution licensees. The distribution licensees shall determine peak load and energy forecasts of their areas for each category of loads for each of the succeeding 5 years and submit the same annually by 31st March to STU along with details of the demand forecasts, data, methodology and assumptions on which the forecasts are based along with their proposals for transmission system augmentation. The demand forecasts shall be updated annually or whenever major changes are made in the existing forecasts or planning. While indicating requirements of single consumers with large demands (1 MW or higher) the distribution licensee shall satisfy himself as to the degree of certainty of the demand materializing.
(ii) The STU shall work out on the basis of projected loads and losses of the system, the net energy requirement and peak load requirement at generation end. The installed capacity, peak availability, surplus and deficit both in demand and energy shall also be worked out by the STU.
(iii) Workout the additional generating capacity required after taking into account, the existing capacity, assistance from captive power plants, projects under construction, proposed projects under IPPs (Independent Power Producers) in the State sector and share of the State from Central sector Power Projects both within and outside Tamil Nadu.
(iv) Prepare a proposal for the requirement of generation for the State to meet the load demand as per the forecast, after examining the economic; technical and environmental aspects of all available alternatives taking into account the existing contracted generation resources and effects of demand side management.
(v) The plan shall indicate the areas opened up for private investors / generation expansion so as to facilitate decision on private investment.
(vi) Prepare a transmission plan for the State Transmission System compatible with the above load forecast and generation plan. This will include provision for VAR compensation needed in the State Transmission System. The reactive power planning exercise is to be carried out by STU in consultation with RLDC/SREB and distribution licensees.
(vii) STU's planning department shall use load flow, short circuit, transient stability study, relay coordination study and other techniques for transmission system planning.
(viii) STU's planning department shall simulate the contingency and system constraint conditions for the system in transmission system planning.
(ix) STU would maintain a historical database based on operational data supplied by SLDC using the state-of-the-art tools such as Energy Management System (EMS) for demand forecasting.
(x) STU shall be responsible to prepare and submit a long-term (10 years) plan to the Commission for the requirement of generation expansion and transmission system expansion to meet the future demand growth. The proposal for setting up of generating plant would be prepared after examining the economic, technical & environmental aspects.
(xi) All the Users shall supply to STU, the desired planning data by 31st March every year to enable STU to formulate and finalize the plan by 30th September each year for the next 5 years.
(xii) The plan reports shall contain a Chapter on additional transmission requirement, which may include not only intra-State transmission lines but also additional equipment such as transformer, capacitors, reactors etc.
(xiii) The plan report shall also indicate the action taken to fulfill the additional requirement and actual progress made on new schemes. The planning report and power map will be available to any interested party for making investment decision/connection decisions to the STS.
(xiv) To provide long-term open access as per the terms and conditions formulated by TNERC.
(xv) Based on Plans prepared by the STU, other Transmission / distribution licensees shall have to plan, their systems to further evacuate power from the STS. In case of Long Term Open Access Applications requiring any strengthening in the intra-State transmission system to absorb/evacuate power beyond STS, the applicant shall co-ordinate with CTU.
(xvi) The Inter-State Transmission System and associated intra-State trans-mission system are complementary and inter-dependent and planning of one affects the other's planning and performance.
• Capacity addition by the distribution licensee, IPPs, Co-Generators and Captive Generators.
• Flows from central sector power stations.
• Expected power flow through Trading of Power.
• Adoption and effectiveness of Demand Side Management and Energy Conservation Measures.
• Optimization of existing capacity through renovation and modernization.
• Utilizing the off peak surplus from base load station for the pumped storage plants during pump mode operation.
• Environmental and financial constraints.
• Fuel prices and availability.
(b) The important key issues with respect to the generation planning are.
• Predicting the establishment of new generation capacity, including where, when and how much.
• Predicting generation despatch.
• Provision towards generation reserve for reliability of supply.
• Predicting decommissioning of old generation capacity.
• Environmental regulation leading to an increasing amount of renewable energy sources generation with prioritized Grid access.
• The impact of wind energy generators, Co-Generators and Captive generation units on the dynamic performance of the power system considering its special nature.
• Impact of large generating plant on the Grid.
• Increasing amount of non-despatchable generation.
• Marginal costs for generators.
• Price elasticity of consumers.
• Market player's estimates of future power prices.
• Rules for access to the capacity on the interconnection.
(c) The STU shall analyze the planning problem by making use of software models, simulation programs etc., of power system engineering. Possible applications are:
• Predicting the generation capacity and despatch by including system reliability, marginal generation costs, future electricity price and future environmental policy, through dedicated models.
• Simulation of different scenarios in capacity development and generation despatch for the development of a flexible transmission grid structure.
• Integrated resource or least cost planning methods to evaluate the potential capacity addition resources and uncertainties and to determine the best mix of sources.
• Probability methods for generation planning by representing generating unit failure and repair processes, load variability due to weather and other uncertainties.
Note: Many hydro stations in Tamil Nadu are tied up with irrigation schedules and these stations have to be closed down during certain period of the year. Also in case of monsoon failure, many hydro stations cannot be operated at full capacity. For estimating peak availability and energy availability for generation planning, these peculiarities shall be taken into account.
(i) As a general rule, the STS shall be capable of withstanding and be secured against the following contingency outages without necessitating load shedding or rescheduling of generation during Steady State Operation:
- Outage of a 110 kV D/C line or,
- Outage of a 230 kV D/Cline or,
- Outage of a 400 kV S/C line or,
- Outage of single Interconnecting Transformer.
(ii) The above contingencies shall be considered assuming a pre contingency system depletion (Planned outage) of another 230 k V D/C line or 400 kV S/C line in another corridor and rot emanating from the same substation. All the Generating Units may operate within their reactive capability curves and the network voltage profile shall also be maintained within voltage limits specified.
(b) The STS shall be capable of withstanding the loss of most severe single system infeed without loss of stability.
(c) Any one of these events defined above shall not cause:
(i) Loss of supply.
(ii) Prolonged operation of the system frequency below and above specified limits.
(iii) Unacceptable high or low voltage.
(iv) System instability.
(v) Unacceptable overloading of STS elements.
(i) Security of supply, extendibility, maintainability and operational flexibility.
(ii) Statutory Safety Requirements.
(iii) Protection from direct lightning stroke.
(iv) Switching Scheme:-
(a) 400 kV sub-station: One and a half breaker scheme or double main and transfer bus bar scheme.
(b) 230 kV sub-station: Double Main and Transfer Scheme or Double-Main with breaker by-pass scheme.
(c) 110 kV sub-station: Main and Transfer Scheme.
(d) Below 110 kV: as decided by the licensee with the consent of STU.
(v) All new EHT Circuit Breakers shall be of SF6 type.
(vi) Isolators shall be pneumatic or motor operated.
(vii) Surge diverters shall be of metal oxide type as per IEC 60099.
(viii) Inter-Connecting Transformers shall be provided with On Load Tap Changers (OLTC).
(ix) The Control Room shall be extensible. Operation of Circuit breakers, OLTCs, Isolators (230KV and above), shall be possible from the Local Panels as well as Panels in the Control Room. Necessary interlocks shall be provided to meet these requirements.
(x) All sub-station structures shall be of lattice steel, protected against corrosion by hot dip galvanization. Lightning masts shall be designed for diagonal wind condition. The structures shall conform to IEC - 865, IS - 875, IS - 806, IS-802 and IS-800.
(xi) Electrical, mechanical and civil designs shall be standardized to the extent possible. Where standards developed by CTU/STU are available, the same may be adopted at the option of the transmission licensee.
(xii) Power Supply to Sub-Station Auxiliaries:
(a) AC supply: Two HT supplies shall be arranged from independent sources. One of the two HT supplies shall be standby to the other. In addition, a Diesel Generating set of suitable capacity shall also be provided.
(b) DC Supply: (Applicable to new sub-stations) There shall be two sets of 220V batteries, each equipped with its own charger for substations of 230 kV and above. Each battery shall be of adequate capacity to meet the sub-station requirements. The batteries shall operate in parallel and one being standby to the other. Facility for changing the duly of the batteries from main to standby and vice versa shall be made. There shall be two sets of 50V batteries (one being standby to the other) for PLCC System. For sub-stations of 110 KV and below, one set of battery each may be provided.
(xiii) For high current, XLPE cables shall be employed., However for LV / MV systems PVC Cables corresponding to IS -1554 could be employed at the discretion of the Licensees. The cables shall normally be laid in trenches. For buried cables, suitable protection shall be provided.
(xiv) Reliable (PL.CC or higher quality) communication link shall be provided on ail EHT lines for voice, fax, protection, telemetry and SCADA. High accuracy standard coupling shall be provided for this purpose.
(xv) Sub-Station Grounding shall be done in accordance with IEEE-80.
(xvi) The size and number of Interconnecting transformers shall be selected such that outage of one ICT would not overload the remaining ICTs or the underlying system.
(xvii) The stuck breaker condition in the sub-station shall cause disruption of not more than four feeders in 110 kV or 230kV system, more than two feeders in 400kV.
(xviii) In the sub-stations of 230 kV and higher voltage, the Control Room, PLCC Room, Relay Testing Room and Electronic Laboratory shall be air-conditioned.
(a) Shall be of XLPE (Cross linked Poly Ethylene) type corresponding to IS -7098
(Any alternative type of cable developed in due course with same or better performance may be employed after taking clearance from the STU / Commission).
(b) The cable conductor shall be of adequate size considering continuous current, short circuit current voltage drop etc and shall correspond to IS s 130
(c) Cables shall be provided suitable sheathing, armouring and screening such that these have the requisite mechanical strength and flexibility to withstand the stresses during handling and laying into ducts/ trenches.
(d) Prior permission shall be obtained from the appropriate authority for digging trenches and precautions shall be taken to prevent accidents and to preclude accidental cutting of communication cables, other power cables, water, gas and sewage lines in accordance with the provisions of "Part-VIII of the Act".
(e) The route maps shall be kept at the substation and markers shall be fixed to trace the cables.
(f) Road crossing shall be carried out by providing culverts, huge pipes or Gl pipes.
(g) Jointing anti termination shall be carried out in accordance with the relevant standards.
(ii) Clearance from Power Telecom Coordination Committee shall be obtained.
(b) The operative power factor of the generators in the network shall be between 0.85 lagging and 0.95 leading for good reactive power supply capability for local loads and should not generally be used for remote despatching of reactive power.
(c) The quantum of compensation required to be provided in the Grid shall be suitably distributed in the transmission system, sub stations and distribution system of network. The norms for percentages and quantum of MVAr to be provided by the Licensees / Generators for different period must be specified by STU through well-documented guidelines for use by all concerned.
(i) Standard planning data Standard planning data consists of details, which are expected to be normally sufficient for the STU to investigate the impact on the STS due to User development. For generation planning the required standard data shall be furnished as per Annexure A-l. For transmission planning the required standard data shall be furnished as per Annexure A-2.
(i) Standard planning data
(ii) Detailed planning data Detailed planning data consist of additional, more detailed data not normally expected to be required by STU to assess the impact of User development on the STS. This data shall be furnished by the Users of STS as and when requested by STU.
(ii) Detailed planning data
Chapter 6
Grid Connectivity Conditions
Section 5 • Tamil Nadu Electricity Grid Code, 2005
5. System Planning.
tamil-nadu-electricity-grid-code-2005-sec-5.json
•
Section 5
{
"act_title": "Tamil Nadu Electricity Grid Code, 2005",
"act_slug": "tamil-nadu-electricity-grid-code-2005",
"section_label": "Section",
"section": {
"number": "5",
"title": "5. System Planning.",
"chapter": null,
"content": "(i) Development on a User's system already connected to the State Transmission System.\n(ii) The introduction of a new Connection point between the User's system and the State Transmission System.\n(iii) Evacuation system for Generating Stations within or outside the State.\n(iv) Reactive Power Compensation.\n(v) A general increase in system capacity (due to addition of generation or system load) to remove operating constraints and maintain standards of security.\n(vi) Transient or steady state stability considerations.\n(vii) Cumulative effect of any of the above.\n• Defines the procedure for the exchange of information between STU and a User in respect of any proposed development on the User's system, which may have an impact on the performance of the User.\n• Details the information which STU shall make available to Users in order to facilitate the identification and evaluation of opportunities for use of or connection to State Transmission System;\n• Details the information required by STU from Users to enable STU to plan the development of its Transmission System to facilitate proposed User developments;\n• Specifies planning and design standards, which will be applied by STU in planning and development of the power system.\n(i) Forecast the demand for power within the Area of Supply, based on the forecasts provided by distribution licensees, and provide to the Commission details of the demand forecasts, data, methodology and assumptions on which the forecasts are based. For demand forecasting, the methodology and procedure followed by the Electric Power Survey Committee constituted by CEA may be followed. These forecasts would be annually reviewed and updated. The primary responsibility of load forecasting within distribution licensee's Area of Supply rests with respective distribution licensees. The distribution licensees shall determine peak load and energy forecasts of their areas for each category of loads for each of the succeeding 5 years and submit the same annually by 31st March to STU along with details of the demand forecasts, data, methodology and assumptions on which the forecasts are based along with their proposals for transmission system augmentation. The demand forecasts shall be updated annually or whenever major changes are made in the existing forecasts or planning. While indicating requirements of single consumers with large demands (1 MW or higher) the distribution licensee shall satisfy himself as to the degree of certainty of the demand materializing.\n(ii) The STU shall work out on the basis of projected loads and losses of the system, the net energy requirement and peak load requirement at generation end. The installed capacity, peak availability, surplus and deficit both in demand and energy shall also be worked out by the STU.\n(iii) Workout the additional generating capacity required after taking into account, the existing capacity, assistance from captive power plants, projects under construction, proposed projects under IPPs (Independent Power Producers) in the State sector and share of the State from Central sector Power Projects both within and outside Tamil Nadu.\n(iv) Prepare a proposal for the requirement of generation for the State to meet the load demand as per the forecast, after examining the economic; technical and environmental aspects of all available alternatives taking into account the existing contracted generation resources and effects of demand side management.\n(v) The plan shall indicate the areas opened up for private investors / generation expansion so as to facilitate decision on private investment.\n(vi) Prepare a transmission plan for the State Transmission System compatible with the above load forecast and generation plan. This will include provision for VAR compensation needed in the State Transmission System. The reactive power planning exercise is to be carried out by STU in consultation with RLDC/SREB and distribution licensees.\n(vii) STU's planning department shall use load flow, short circuit, transient stability study, relay coordination study and other techniques for transmission system planning.\n(viii) STU's planning department shall simulate the contingency and system constraint conditions for the system in transmission system planning.\n(ix) STU would maintain a historical database based on operational data supplied by SLDC using the state-of-the-art tools such as Energy Management System (EMS) for demand forecasting.\n(x) STU shall be responsible to prepare and submit a long-term (10 years) plan to the Commission for the requirement of generation expansion and transmission system expansion to meet the future demand growth. The proposal for setting up of generating plant would be prepared after examining the economic, technical & environmental aspects.\n(xi) All the Users shall supply to STU, the desired planning data by 31st March every year to enable STU to formulate and finalize the plan by 30th September each year for the next 5 years.\n(xii) The plan reports shall contain a Chapter on additional transmission requirement, which may include not only intra-State transmission lines but also additional equipment such as transformer, capacitors, reactors etc.\n(xiii) The plan report shall also indicate the action taken to fulfill the additional requirement and actual progress made on new schemes. The planning report and power map will be available to any interested party for making investment decision/connection decisions to the STS.\n(xiv) To provide long-term open access as per the terms and conditions formulated by TNERC.\n(xv) Based on Plans prepared by the STU, other Transmission / distribution licensees shall have to plan, their systems to further evacuate power from the STS. In case of Long Term Open Access Applications requiring any strengthening in the intra-State transmission system to absorb/evacuate power beyond STS, the applicant shall co-ordinate with CTU.\n(xvi) The Inter-State Transmission System and associated intra-State trans-mission system are complementary and inter-dependent and planning of one affects the other's planning and performance.\n• Capacity addition by the distribution licensee, IPPs, Co-Generators and Captive Generators.\n• Flows from central sector power stations.\n• Expected power flow through Trading of Power.\n• Adoption and effectiveness of Demand Side Management and Energy Conservation Measures.\n• Optimization of existing capacity through renovation and modernization.\n• Utilizing the off peak surplus from base load station for the pumped storage plants during pump mode operation.\n• Environmental and financial constraints.\n• Fuel prices and availability.\n(b) The important key issues with respect to the generation planning are.\n• Predicting the establishment of new generation capacity, including where, when and how much.\n• Predicting generation despatch.\n• Provision towards generation reserve for reliability of supply.\n• Predicting decommissioning of old generation capacity.\n• Environmental regulation leading to an increasing amount of renewable energy sources generation with prioritized Grid access.\n• The impact of wind energy generators, Co-Generators and Captive generation units on the dynamic performance of the power system considering its special nature.\n• Impact of large generating plant on the Grid.\n• Increasing amount of non-despatchable generation.\n• Marginal costs for generators.\n• Price elasticity of consumers.\n• Market player's estimates of future power prices.\n• Rules for access to the capacity on the interconnection.\n(c) The STU shall analyze the planning problem by making use of software models, simulation programs etc., of power system engineering. Possible applications are:\n• Predicting the generation capacity and despatch by including system reliability, marginal generation costs, future electricity price and future environmental policy, through dedicated models.\n• Simulation of different scenarios in capacity development and generation despatch for the development of a flexible transmission grid structure.\n• Integrated resource or least cost planning methods to evaluate the potential capacity addition resources and uncertainties and to determine the best mix of sources.\n• Probability methods for generation planning by representing generating unit failure and repair processes, load variability due to weather and other uncertainties.\nNote: Many hydro stations in Tamil Nadu are tied up with irrigation schedules and these stations have to be closed down during certain period of the year. Also in case of monsoon failure, many hydro stations cannot be operated at full capacity. For estimating peak availability and energy availability for generation planning, these peculiarities shall be taken into account.\n(i) As a general rule, the STS shall be capable of withstanding and be secured against the following contingency outages without necessitating load shedding or rescheduling of generation during Steady State Operation:\n- Outage of a 110 kV D/C line or,\n- Outage of a 230 kV D/Cline or,\n- Outage of a 400 kV S/C line or,\n- Outage of single Interconnecting Transformer.\n(ii) The above contingencies shall be considered assuming a pre contingency system depletion (Planned outage) of another 230 k V D/C line or 400 kV S/C line in another corridor and rot emanating from the same substation. All the Generating Units may operate within their reactive capability curves and the network voltage profile shall also be maintained within voltage limits specified.\n(b) The STS shall be capable of withstanding the loss of most severe single system infeed without loss of stability.\n(c) Any one of these events defined above shall not cause:\n(i) Loss of supply.\n(ii) Prolonged operation of the system frequency below and above specified limits.\n(iii) Unacceptable high or low voltage.\n(iv) System instability.\n(v) Unacceptable overloading of STS elements.\n(i) Security of supply, extendibility, maintainability and operational flexibility.\n(ii) Statutory Safety Requirements.\n(iii) Protection from direct lightning stroke.\n(iv) Switching Scheme:-\n(a) 400 kV sub-station: One and a half breaker scheme or double main and transfer bus bar scheme.\n(b) 230 kV sub-station: Double Main and Transfer Scheme or Double-Main with breaker by-pass scheme.\n(c) 110 kV sub-station: Main and Transfer Scheme.\n(d) Below 110 kV: as decided by the licensee with the consent of STU.\n(v) All new EHT Circuit Breakers shall be of SF6 type.\n(vi) Isolators shall be pneumatic or motor operated.\n(vii) Surge diverters shall be of metal oxide type as per IEC 60099.\n(viii) Inter-Connecting Transformers shall be provided with On Load Tap Changers (OLTC).\n(ix) The Control Room shall be extensible. Operation of Circuit breakers, OLTCs, Isolators (230KV and above), shall be possible from the Local Panels as well as Panels in the Control Room. Necessary interlocks shall be provided to meet these requirements.\n(x) All sub-station structures shall be of lattice steel, protected against corrosion by hot dip galvanization. Lightning masts shall be designed for diagonal wind condition. The structures shall conform to IEC - 865, IS - 875, IS - 806, IS-802 and IS-800.\n(xi) Electrical, mechanical and civil designs shall be standardized to the extent possible. Where standards developed by CTU/STU are available, the same may be adopted at the option of the transmission licensee.\n(xii) Power Supply to Sub-Station Auxiliaries:\n(a) AC supply: Two HT supplies shall be arranged from independent sources. One of the two HT supplies shall be standby to the other. In addition, a Diesel Generating set of suitable capacity shall also be provided.\n(b) DC Supply: (Applicable to new sub-stations) There shall be two sets of 220V batteries, each equipped with its own charger for substations of 230 kV and above. Each battery shall be of adequate capacity to meet the sub-station requirements. The batteries shall operate in parallel and one being standby to the other. Facility for changing the duly of the batteries from main to standby and vice versa shall be made. There shall be two sets of 50V batteries (one being standby to the other) for PLCC System. For sub-stations of 110 KV and below, one set of battery each may be provided.\n(xiii) For high current, XLPE cables shall be employed., However for LV / MV systems PVC Cables corresponding to IS -1554 could be employed at the discretion of the Licensees. The cables shall normally be laid in trenches. For buried cables, suitable protection shall be provided.\n(xiv) Reliable (PL.CC or higher quality) communication link shall be provided on ail EHT lines for voice, fax, protection, telemetry and SCADA. High accuracy standard coupling shall be provided for this purpose.\n(xv) Sub-Station Grounding shall be done in accordance with IEEE-80.\n(xvi) The size and number of Interconnecting transformers shall be selected such that outage of one ICT would not overload the remaining ICTs or the underlying system.\n(xvii) The stuck breaker condition in the sub-station shall cause disruption of not more than four feeders in 110 kV or 230kV system, more than two feeders in 400kV.\n(xviii) In the sub-stations of 230 kV and higher voltage, the Control Room, PLCC Room, Relay Testing Room and Electronic Laboratory shall be air-conditioned.\n(a) Shall be of XLPE (Cross linked Poly Ethylene) type corresponding to IS -7098\n(Any alternative type of cable developed in due course with same or better performance may be employed after taking clearance from the STU / Commission).\n(b) The cable conductor shall be of adequate size considering continuous current, short circuit current voltage drop etc and shall correspond to IS s 130\n(c) Cables shall be provided suitable sheathing, armouring and screening such that these have the requisite mechanical strength and flexibility to withstand the stresses during handling and laying into ducts/ trenches.\n(d) Prior permission shall be obtained from the appropriate authority for digging trenches and precautions shall be taken to prevent accidents and to preclude accidental cutting of communication cables, other power cables, water, gas and sewage lines in accordance with the provisions of \"Part-VIII of the Act\".\n(e) The route maps shall be kept at the substation and markers shall be fixed to trace the cables.\n(f) Road crossing shall be carried out by providing culverts, huge pipes or Gl pipes.\n(g) Jointing anti termination shall be carried out in accordance with the relevant standards.\n(ii) Clearance from Power Telecom Coordination Committee shall be obtained.\n(b) The operative power factor of the generators in the network shall be between 0.85 lagging and 0.95 leading for good reactive power supply capability for local loads and should not generally be used for remote despatching of reactive power.\n(c) The quantum of compensation required to be provided in the Grid shall be suitably distributed in the transmission system, sub stations and distribution system of network. The norms for percentages and quantum of MVAr to be provided by the Licensees / Generators for different period must be specified by STU through well-documented guidelines for use by all concerned.\n(i) Standard planning data Standard planning data consists of details, which are expected to be normally sufficient for the STU to investigate the impact on the STS due to User development. For generation planning the required standard data shall be furnished as per Annexure A-l. For transmission planning the required standard data shall be furnished as per Annexure A-2.\n(i) Standard planning data\n(ii) Detailed planning data Detailed planning data consist of additional, more detailed data not normally expected to be required by STU to assess the impact of User development on the STS. This data shall be furnished by the Users of STS as and when requested by STU.\n(ii) Detailed planning data\nChapter 6\nGrid Connectivity Conditions",
"footnote": "",
"is_definition": false,
"sort_order": 4
},
"prev_section": "4",
"next_section": "6"
}