(a) A resolution of the Local Authority.
(b) An undertaking by the Local Authority to the effect that it shall abide by all the conditions attached to the grant and also comply with such instructions as the Government may issue in respect of the works for which the grant is required.
[(c) Plans and estimates of the proposed work together with all details necessary to assess the utility and soundness of the scheme. These plans and estimates for works shall be accompanied by a certificate of Regd. Architect or any officer not below the rank of Assistant Engineer, to the effect that the plan is technically sound and estimates are reasonable having regard to current market rales applicable for identical work if taken up by the Government.]
(d) A report as to how the Local Authority proposes to maintain the proposed work at a level of efficiency considered essential for the particular work in question.
(e) A statement showing the financial position of the local authority during the current financial year and the last two preceding financial years.
(f) A proposal as to how the local authority is going to meet the rest of the expenditure on account of the works proposed.
(g) Any other information required by the Government.
(b) All cases in which the grant-in-aid does not exceed Rs. 25,000/- in a particular year to a particular municipality, shall be examined by the Director of Local Bodies and grant-in-aid permissible under these rules shall be sanctioned by him. All other cases shall be forwarded to the State Government for consideration and grant-in-aid sanctioned by Government shall be released by the Director of Local Bodies.]
[8A. Mode of payment of grant-in-aid.
Section 8 • Specific Purpose Grant-in-Aid Rules, 1961
8. Application for grant.
specific-purpose-grant-in-aid-rules-1961-sec-8.json
•
Section 8
{
"act_title": "Specific Purpose Grant-in-Aid Rules, 1961",
"act_slug": "specific-purpose-grant-in-aid-rules-1961",
"section_label": "Section",
"section": {
"number": "8",
"title": "8. Application for grant.",
"chapter": null,
"content": "(a) A resolution of the Local Authority.\n(b) An undertaking by the Local Authority to the effect that it shall abide by all the conditions attached to the grant and also comply with such instructions as the Government may issue in respect of the works for which the grant is required.\n[(c) Plans and estimates of the proposed work together with all details necessary to assess the utility and soundness of the scheme. These plans and estimates for works shall be accompanied by a certificate of Regd. Architect or any officer not below the rank of Assistant Engineer, to the effect that the plan is technically sound and estimates are reasonable having regard to current market rales applicable for identical work if taken up by the Government.]\n(d) A report as to how the Local Authority proposes to maintain the proposed work at a level of efficiency considered essential for the particular work in question.\n(e) A statement showing the financial position of the local authority during the current financial year and the last two preceding financial years.\n(f) A proposal as to how the local authority is going to meet the rest of the expenditure on account of the works proposed.\n(g) Any other information required by the Government.\n(b) All cases in which the grant-in-aid does not exceed Rs. 25,000/- in a particular year to a particular municipality, shall be examined by the Director of Local Bodies and grant-in-aid permissible under these rules shall be sanctioned by him. All other cases shall be forwarded to the State Government for consideration and grant-in-aid sanctioned by Government shall be released by the Director of Local Bodies.]\n[8A. Mode of payment of grant-in-aid.",
"footnote": "",
"is_definition": false,
"sort_order": 15
},
"prev_section": "7",
"next_section": "9"
}