79M. Time frame for the total process.

S. No.
S. No.
Activity
Activity
Time Required
Time Required
1.
Examination of preliminary report and permission
to the proponent to proceed for preparation of detailed proposal
OR rejection of the proposal, as the case may be, by the
Administrative Department.
One Month from the date of receipt of the
proposal.
2.
Detailed proposal submission by the proponent.
Within three Months or period extended under
sub-rule (6) of Rule 79-D.
3.
Examination of detailed proposal, preparation of
bid documents and approval from competent authority
Forty Five days
4.
Bid invitation and submission of bids
(i) Thirty days from the date of first
publication of Notice Inviting Bids;
(ii) Where clarifications/addendum are issued,
at least Fifteen days from date of issue of clarifications/
addendum; or
(iii) In case of International Competitive
Bidding, the period of submission of bids shall be forty five
days from the date of first publication of Notice Inviting Bids
and at least twenty days from the date of issue of
clarifications/ addendum.
5.
Bids evaluation
Fifteen Days
6.
Time for project proponent to match the most
advantageous bid, if any.
Fifteen Days
7.
Letter of Award
Within 7 days of approval of award by the
competent authority.
8.
Execution of Contract Agreement
Within fifteen days of issue of letter of award
or a period as specified in the bidding documents.