Section 5. Determination of need for procurement.- (1) In every case of

a procurement made under this Act the procuring entity shall fi rst
determine the need for the subject matter of procurement.
(2) While assessing the need unde r sub-section (1), the procur ing
entity shall take into account the estimated cost of the procur ement and
also decide on the following matters, namely:-
(a) the scope or quantity of procurement, if determined;
(b) the method of procurement to be followed with justificatio n
thereof;
(c) need for pre-qualification, if any;
(d) limitation on participation of bidders in terms of section 6 , i f
any applicable, and justification thereof; and
(e) any other matter as may be prescribed.
(3) The procuring entity shall ma intain documents relating to the
determination of the need for pro curement under sub-section (1) and the
assessment made under sub-section (2).