procure the subject matter of procurement by the method of two stage
bidding, if-
(a) it is not feasible for the procuring entity to formulate d etailed
specifications or identify specifi c characteristics for the sub ject matter of
procurement, without receiving i nputs regarding its technical a spects
from bidders; or
(b) the character of the subject matter of procurement is subj ect to
such rapid technological advances and market fluctuations to ma ke open
competitive bidding unfeasible; or
(c) the procuring entity seeks to enter into a contract for th e
purpose of research, experiment, study or development, except w here the
contract includes the production of items in quantities suffici ent to
establish their commercial viab ility or to recover research and
development costs; or
(d) the bidder is expected to carry out a detailed survey or
investigation and undertake a co mprehensive assessment of risks , costs
and obligations associated with the particular procurement.
(2) Subject to the rules as may be made in this behalf, the
procedure for two stage bidding shall include the following, namely:-
(a) in the first stage of the bidding process, the procuring e ntity
shall invite bids containing the technical aspects and contract ual terms
and conditions of the proposed procurement without a bid price;
( b ) a l l f i r s t s t a g e b i d s , w h i c h a r e o t h e r w i s e e l i g i b l e , s h a l l be
evaluated in accordance with the procedure laid down in the rules through
an appropriate committee constituted by the procuring entity;
(c) the committee may hold disc ussions with the bidders and if any
such discussion is held, equal opportunity shall be given to al l bidders to
participate in the discussions;
(d) in revising the relevant terms and conditions of the
procurement, the procuring entity shall not modify the fundamen tal
25
nature of the procurement itself, but may add, amend or delete any
specifications of the subject matter of procurement or criterio n for
evaluation;
(e) notwithstanding anything contained in sections 29 and 30, in
the second stage of the bidding process, the procuring entity s hall invite
bids from all those bidders whose bids at the first stage were not rejected,
to present final bid with bid prices in response to a revised s et of terms
and conditions of the procurement;
(f) any bidder, invited to bid but not in a position to supply t h e
subject matter of procurement due to changes in the specificati ons, may
withdraw from the bidding proceedings without forfeiting any bi d
security that he may have been r equired to provide or being penalised in
any way, by declaring his intention to withdraw from the procur ement
proceedings with adequate justification.
Section 32 • The rajasthan transparency in public procurement act, 2012
Section 32. Two stage bidding.- (1) A procuring entity may choose to
rajasthan-transparency-in-public-procurement-act-2012-sec-32.json
•
Section 32
{
"act_title": "The rajasthan transparency in public procurement act, 2012",
"act_slug": "rajasthan-transparency-in-public-procurement-act-2012",
"section_label": "Section",
"section": {
"number": "32",
"title": "Section 32. Two stage bidding.- (1) A procuring entity may choose to",
"chapter": null,
"content": "procure the subject matter of procurement by the method of two stage \nbidding, if- \n (a) it is not feasible for the procuring entity to formulate d etailed \nspecifications or identify specifi c characteristics for the sub ject matter of \nprocurement, without receiving i nputs regarding its technical a spects \nfrom bidders; or \n (b) the character of the subject matter of procurement is subj ect to \nsuch rapid technological advances and market fluctuations to ma ke open \ncompetitive bidding unfeasible; or \n (c) the procuring entity seeks to enter into a contract for th e \npurpose of research, experiment, study or development, except w here the \ncontract includes the production of items in quantities suffici ent to \nestablish their commercial viab ility or to recover research and \ndevelopment costs; or \n (d) the bidder is expected to carry out a detailed survey or \ninvestigation and undertake a co mprehensive assessment of risks , costs \nand obligations associated with the particular procurement. \n (2) Subject to the rules as may be made in this behalf, the \nprocedure for two stage bidding shall include the following, namely:- \n (a) in the first stage of the bidding process, the procuring e ntity \nshall invite bids containing the technical aspects and contract ual terms \nand conditions of the proposed procurement without a bid price; \n ( b ) a l l f i r s t s t a g e b i d s , w h i c h a r e o t h e r w i s e e l i g i b l e , s h a l l be \nevaluated in accordance with the procedure laid down in the rules through \nan appropriate committee constituted by the procuring entity; \n (c) the committee may hold disc ussions with the bidders and if any \nsuch discussion is held, equal opportunity shall be given to al l bidders to \nparticipate in the discussions; \n (d) in revising the relevant terms and conditions of the \nprocurement, the procuring entity shall not modify the fundamen tal \n25 \n \n\nnature of the procurement itself, but may add, amend or delete any \nspecifications of the subject matter of procurement or criterio n for \nevaluation; \n (e) notwithstanding anything contained in sections 29 and 30, in \nthe second stage of the bidding process, the procuring entity s hall invite \nbids from all those bidders whose bids at the first stage were not rejected, \nto present final bid with bid prices in response to a revised s et of terms \nand conditions of the procurement; \n (f) any bidder, invited to bid but not in a position to supply t h e \nsubject matter of procurement due to changes in the specificati ons, may \nwithdraw from the bidding proceedings without forfeiting any bi d \nsecurity that he may have been r equired to provide or being penalised in \nany way, by declaring his intention to withdraw from the procur ement \nproceedings with adequate justification.",
"footnote": "",
"is_definition": false,
"sort_order": 31
},
"prev_section": "31",
"next_section": "33"
}