(i) the status of compliance with the main provisions of the Electricity Act, 2003 and the rules and regulations made thereunder as also important regulatory decisions and policies:
(ii) the dates of filing of Aggregate Revenue Requirement (APR);
(iii) timely filing of true-up petitions, Aggregate Revenue Requirement and tariff petitions, and petitions for adjustments on account of fuel and cost of power purchased;
(iv) steps taken to liquidate regulatory assets;
(v) achievements against Key Performance Indicators (KPIs) and performance milestones mentioned in Memorandum of Understanding (M0U); and
(vi) the strategy and plan for achieving the performance milestones and the actual performance against these performance milestones as prescribed by the State Government.
Form
Form
[ See Rule (3)]
I. Preamble
(Please provide here an overview of the
performance of the Distribution companies during the year and the
strategy for next year)
II. State Electricity Distribution Performance Statement
A. Assessment of compliance for the previous year
(i) Key Performance Indicators (KPI) compliance against target
S.No.
S.No.
Key Performance Indicators
Key Performance Indicators
Unit
Unit
JVVNL
JVVNL
AVVNL
AVVNL
JdVVNL
JdVVNL
Target
Target
Achievement
Achievement
Target
Target
Achievement
Achievement
Target
Target
Achievement
Achievement
1
1
2
2
3
3
4
4
5
5
6
6
7
7
8
8
9
9
1
AT&C loss reduction
%
2a
Energy accounting and auditing of 33 KV feeders
Nos.
2b
Energy accounting and auditing of 11 KV feeders
Nos.
2c
Energy accounting and auditing of DTs
Nos.
3a
Feeder metering
%
3b
Consumer indexing
%
3c
DT Metering
%
3d
Consumer Metering
%
Domestic
%
Non- Domestic
%
Industrial
%
Agriculture
%
4
Consumers billed on actual meter reading
5
Collection Efficiency
6
Reduction in Past Receivables
7a
Date of approval of Annual Account by the Board
of the Company
Date
7b
Date of approval of audited Annual Account of
the Company by the General Body
Date
8a
Functional Directors
Nos.
8b
Independent Directors
Nos.
9a
Filing of True up petition
Date
9b
Filing of ARR petition
Date
9c
Filing of Fuel Cost Power Purchase Adjustment
Date
(ii) Details of measures taken
(Please provide here an assessment of compliance
by Distribution Licensees and State Government in the areas of
long-term planning, consumer protection, regulatory compliance,
corporate governance, financial restructuring and Key performance
indicators in the previous year)
Note. - For the first year, after the commencement of the Act, target may not be mentioned in Key Performance Indicators.
Note.
(iii) Assessment of compliance for the current year (Actual upto December and Projection from January to March of each year)
(i) Key Performance Indicators (KPI) compliance against target
S.No.
S.No.
Key Performance Indicators
Key Performance Indicators
Unit
Unit
JVVNL
JVVNL
AVVNL
AVVNL
JdVVNL
JdVVNL
Target
Target
Achievement
Achievement
Target
Target
Achievement
Achievement
Target
Target
Achievment
Achievment
1
1
2
2
3
3
4
4
5
5
6
6
7
7
8
8
9
9
1
AT&C loss reduction
%
2a
Energy accounting and auditing of 33 KV feeders
Nos.
2b
Energy accounting and auditing of 11 KV feeders
Nos.
2c
Energy accounting and auditing of DTs
Nos.
3a
Feeder metering
%
3b
Consumer indexing
%
3c
DT Metering
%
3d
Consumer Metering
%
Domestic
%
Non- Domestic
%
Industrial
%
Agriculture
%
4
Consumers billed on actual meter reading
5
Collection Efficiency
6
Reduction in Past Receivables
7a
Date of approval of Annual Account by the Board
of the Company
Date
7b
Date of approval of audited Annual Account of
the Company by the General Body
Date
8a
Functional Directors
Nos.
8b
Independent Directors
Nos.
9a
Filing of True up petition
Date
9b
Filing of ARR petition
Date
9c
Filing of Fuel Cost Power Purchase Adjustment
Date
(ii) Details of measures taken
(Please provide here an assessment of compliance by
Distribution Licensees and State Government in the areas of long-term
planning, consumer protection, regulatory compliance, corporate
governance, financial restructuring and Key
performance indicators
in the current year)
III. State Electricity Distribution Strategy Statement
(i) Targets for Key Performance Indicators (KPI) for following year
S.No.
S.No.
Key Performance Indicators
Key Performance Indicators
Unit
Unit
JVVNL
JVVNL
AVVNL
AVVNL
JdVVNL
JdVVNL
Target
Target
Achievement
Achievement
Target
Target
Achievement
Achievement
Target
Target
Achievment
Achievment
1
1
2
2
3
3
4
4
5
5
6
6
7
7
8
8
9
9
1
AT&C loss reduction
%
2a
Energy accounting and auditing of 33 KV feeders
Nos.
2b
Energy accounting and auditing of 11 KV feeders
Nos.
2c
Energy accounting and auditing of DTs
Nos.
3a
Feeder metering
%
3b
Consumer indexing
%
3c
DT Metering
%
3d
Consumer Metering
%
Domestic
%
Non- Domestic
%
Industrial
%
Agriculture
%
4
Consumers billed on actual meter reading
5
Collection Efficiency
6
Reduction in Past Receivables
7a
Date of approval of Annual Account by the Board
of the Company
Date
7b
Date of approval of audited Annual Account of
the Company by the General Body
Date
8a
Functional Directors
Nos.
8b
Independent Directors
Nos.
9a
Filing of True up petition
Date
9b
Filing of ARR petition
Date
9c
Filing of Fuel Cost Power Purchase Adjustment
Date
(ii) Details of Policies and Strategy for achieving the KPI targets
(Please provide here the policies and strategies for
achieving the targets)
IV. Time Bound Action Plan
(Please mention here time bound action plan,
long term, medium term and short term basis including, activates
and monitoring mechanism to ensure achievement of targets for key
Performance Indicators, feedback loop for in/midcourse
correction and such actions as may be required to meet the
obligations cast on the State Government)
JVVNL
JVVNL
AWNL
AWNL
JdWNL
JdWNL
Long Term Plan
Medium Term Plan
Short Term Plan
Section 4 • Rajasthan State Electricity Distribution Management Responsibility Rules, 2016
4. Periodic Reports by State Distribution Licensees.
rajasthan-state-electricity-distribution-management-responsibility-rules-2016-sec-4.json
•
Section 4
{
"act_title": "Rajasthan State Electricity Distribution Management Responsibility Rules, 2016",
"act_slug": "rajasthan-state-electricity-distribution-management-responsibility-rules-2016",
"section_label": "Section",
"section": {
"number": "4",
"title": "4. Periodic Reports by State Distribution Licensees.",
"chapter": null,
"content": "(i) the status of compliance with the main provisions of the Electricity Act, 2003 and the rules and regulations made thereunder as also important regulatory decisions and policies:\n(ii) the dates of filing of Aggregate Revenue Requirement (APR);\n(iii) timely filing of true-up petitions, Aggregate Revenue Requirement and tariff petitions, and petitions for adjustments on account of fuel and cost of power purchased;\n(iv) steps taken to liquidate regulatory assets;\n(v) achievements against Key Performance Indicators (KPIs) and performance milestones mentioned in Memorandum of Understanding (M0U); and\n(vi) the strategy and plan for achieving the performance milestones and the actual performance against these performance milestones as prescribed by the State Government.\nForm\nForm\n[ See Rule (3)]\nI. Preamble\n(Please provide here an overview of the\n performance of the Distribution companies during the year and the\n strategy for next year)\nII. State Electricity Distribution Performance Statement\nA. Assessment of compliance for the previous year\n(i) Key Performance Indicators (KPI) compliance against target\nS.No.\nS.No.\nKey Performance Indicators\nKey Performance Indicators\nUnit\nUnit\nJVVNL\nJVVNL\nAVVNL\nAVVNL\nJdVVNL\nJdVVNL\nTarget\nTarget\nAchievement\nAchievement\nTarget\nTarget\nAchievement\nAchievement\nTarget\nTarget\nAchievement\nAchievement\n1\n1\n2\n2\n3\n3\n4\n4\n5\n5\n6\n6\n7\n7\n8\n8\n9\n9\n1\nAT&C loss reduction\n%\n2a\nEnergy accounting and auditing of 33 KV feeders\nNos.\n2b\nEnergy accounting and auditing of 11 KV feeders\nNos.\n2c\nEnergy accounting and auditing of DTs\nNos.\n3a\nFeeder metering\n%\n3b\nConsumer indexing\n%\n3c\nDT Metering\n%\n3d\nConsumer Metering\n%\nDomestic\n%\nNon- Domestic\n%\nIndustrial\n%\nAgriculture\n%\n4\nConsumers billed on actual meter reading\n5\nCollection Efficiency\n6\nReduction in Past Receivables\n7a\nDate of approval of Annual Account by the Board\n of the Company\nDate\n7b\nDate of approval of audited Annual Account of\n the Company by the General Body\nDate\n8a\nFunctional Directors\nNos.\n8b\nIndependent Directors\nNos.\n9a\nFiling of True up petition\nDate\n9b\nFiling of ARR petition\nDate\n9c\nFiling of Fuel Cost Power Purchase Adjustment\nDate\n(ii) Details of measures taken\n(Please provide here an assessment of compliance\n by Distribution Licensees and State Government in the areas of\n long-term planning, consumer protection, regulatory compliance,\n corporate governance, financial restructuring and Key performance\n indicators in the previous year)\nNote. - For the first year, after the commencement of the Act, target may not be mentioned in Key Performance Indicators.\nNote.\n(iii) Assessment of compliance for the current year (Actual upto December and Projection from January to March of each year)\n(i) Key Performance Indicators (KPI) compliance against target\nS.No.\nS.No.\nKey Performance Indicators\nKey Performance Indicators\nUnit\nUnit\nJVVNL\nJVVNL\nAVVNL\nAVVNL\nJdVVNL\nJdVVNL\nTarget\nTarget\nAchievement\nAchievement\nTarget\nTarget\nAchievement\nAchievement\nTarget\nTarget\nAchievment\nAchievment\n1\n1\n2\n2\n3\n3\n4\n4\n5\n5\n6\n6\n7\n7\n8\n8\n9\n9\n1\nAT&C loss reduction\n%\n2a\nEnergy accounting and auditing of 33 KV feeders\nNos.\n2b\nEnergy accounting and auditing of 11 KV feeders\nNos.\n2c\nEnergy accounting and auditing of DTs\nNos.\n3a\nFeeder metering\n%\n3b\nConsumer indexing\n%\n3c\nDT Metering\n%\n3d\nConsumer Metering\n%\nDomestic\n%\nNon- Domestic\n%\nIndustrial\n%\nAgriculture\n%\n4\nConsumers billed on actual meter reading\n5\nCollection Efficiency\n6\nReduction in Past Receivables\n7a\nDate of approval of Annual Account by the Board\n of the Company\nDate\n7b\nDate of approval of audited Annual Account of\n the Company by the General Body\nDate\n8a\nFunctional Directors\nNos.\n8b\nIndependent Directors\nNos.\n9a\nFiling of True up petition\nDate\n9b\nFiling of ARR petition\nDate\n9c\nFiling of Fuel Cost Power Purchase Adjustment\nDate\n(ii) Details of measures taken\n(Please provide here an assessment of compliance by\n Distribution Licensees and State Government in the areas of long-term\n planning, consumer protection, regulatory compliance, corporate\n governance, financial restructuring and Key\nperformance indicators\n in the current year)\nIII. State Electricity Distribution Strategy Statement\n(i) Targets for Key Performance Indicators (KPI) for following year\nS.No.\nS.No.\nKey Performance Indicators\nKey Performance Indicators\nUnit\nUnit\nJVVNL\nJVVNL\nAVVNL\nAVVNL\nJdVVNL\nJdVVNL\nTarget\nTarget\nAchievement\nAchievement\nTarget\nTarget\nAchievement\nAchievement\nTarget\nTarget\nAchievment\nAchievment\n1\n1\n2\n2\n3\n3\n4\n4\n5\n5\n6\n6\n7\n7\n8\n8\n9\n9\n1\nAT&C loss reduction\n%\n2a\nEnergy accounting and auditing of 33 KV feeders\nNos.\n2b\nEnergy accounting and auditing of 11 KV feeders\nNos.\n2c\nEnergy accounting and auditing of DTs\nNos.\n3a\nFeeder metering\n%\n3b\nConsumer indexing\n%\n3c\nDT Metering\n%\n3d\nConsumer Metering\n%\nDomestic\n%\nNon- Domestic\n%\nIndustrial\n%\nAgriculture\n%\n4\nConsumers billed on actual meter reading\n5\nCollection Efficiency\n6\nReduction in Past Receivables\n7a\nDate of approval of Annual Account by the Board\n of the Company\nDate\n7b\nDate of approval of audited Annual Account of\n the Company by the General Body\nDate\n8a\nFunctional Directors\nNos.\n8b\nIndependent Directors\nNos.\n9a\nFiling of True up petition\nDate\n9b\nFiling of ARR petition\nDate\n9c\nFiling of Fuel Cost Power Purchase Adjustment\nDate\n(ii) Details of Policies and Strategy for achieving the KPI targets\n(Please provide here the policies and strategies for\n achieving the targets)\nIV. Time Bound Action Plan\n(Please mention here time bound action plan,\n long term, medium term and short term basis including, activates\n and monitoring mechanism to ensure achievement of targets for key\n Performance Indicators, feedback loop for in/midcourse\n correction and such actions as may be required to meet the\n obligations cast on the State Government)\nJVVNL\nJVVNL\nAWNL\nAWNL\nJdWNL\nJdWNL\nLong Term Plan\nMedium Term Plan\nShort Term Plan",
"footnote": "",
"is_definition": false,
"sort_order": 3
},
"prev_section": "3",
"next_section": null
}