40. Bid security.

(a) when the bidder withdraws or modifies his bid after opening of bids;
(b) when the bidder does not execute the agreement, if any, after placement of supply/work order within the validity period of bid;
(c) when the bidder fails to commence the supply of the goods or service or execute work as per supply/work order within the time specified;
(d) when the bidder does not deposit the performance security deposit after the supply/work order is placed;
(e) to adjust any dues against the bidder from any other contract with the procuring entity;
(f) if the bidder breaches any provision of code of integrity prescribed for bidders in chapter-VI.
(a) the expiry of the bid security;
(b) the entry into force of a procurement contract and the provision of a security for the performance of the contract, if such a security is required by the bidding documents;
(c) the cancellation of the procurement;
(d) the withdrawal of a submission prior to the deadline for presenting bids, unless the bidding documents stipulate that no such withdrawal is permitted.