Table : Bid cycle of outer time frame for various procurement methods (applicable for goods and works) - By One Stage Bidding
Procurement Method
Procurement Method
Open Competitive Bidding
Open Competitive Bidding
Limited Bidding
Limited Bidding
Publication of NIB and launch of Bidding
documents
Day 0
Issue of Bidding documents-Day 0
Submission of Bids
- 30 days from issue
of Bidding documents
- where the pre-bid conference is held 15 days
from date of issue of clarification/addendum
07days from issue of Bidding documents/date of
issue of clarification/addendum
Technical Bid Opening
Within 1 day of last day of submission
Within 1 day of last day of submission of bids
Issue of Letter of Award
Within 3 days of approval of award
Within 3 days of approval of award
Contract Signing
Within 15 days of Issue of Letter of Award
Within 15 days of Issue of Letter of Award
Declaration of the Bid results on State Public
Procurement Portal and Departmental website
Within 3 days of issue of letter of acceptance.
Within 3 days of issue of letter of acceptance.
Table : Time schedule for acceptance of bids by respective authority
1
For bids to be accepted by an Executing Engineer
or an Head of Office
20 Days
2
For bids to be accepted by a Superintending
Engineer or a Regional Officer
30 Days
3
For bids to be accepted by an Additional Chief
Engineer
40 Days
4
For bids to be accepted by a Chief Engineer or
Head of the Department
50 days
5
For bids to be accepted by an Administrative
Department
60 Days
6
For bids to be accepted by a Finance
Committee/Board/ Empowered Committee/ Empowered Board, etc.
70 Days
[Note: Communication of acceptance of tender shall also take place within the above limits of time period.]
Section 38 • Rajasthan Public Procurement Rules, 2012
38. Time frame for procurement process.
rajasthan-public-procurement-rules-2012-sec-38.json
•
Section 38
{
"act_title": "Rajasthan Public Procurement Rules, 2012",
"act_slug": "rajasthan-public-procurement-rules-2012",
"section_label": "Section",
"section": {
"number": "38",
"title": "38. Time frame for procurement process.",
"chapter": null,
"content": "Table : Bid cycle of outer time frame for various procurement methods (applicable for goods and works) - By One Stage Bidding\nProcurement Method\nProcurement Method\nOpen Competitive Bidding\nOpen Competitive Bidding\nLimited Bidding\nLimited Bidding\nPublication of NIB and launch of Bidding\n\t\t\t\tdocuments\nDay 0\nIssue of Bidding documents-Day 0\nSubmission of Bids\n- 30 days from issue\n\t\t\t\tof Bidding documents\n- where the pre-bid conference is held 15 days\n\t\t\t\tfrom date of issue of clarification/addendum\n07days from issue of Bidding documents/date of\n\t\t\t\tissue of clarification/addendum\nTechnical Bid Opening\nWithin 1 day of last day of submission\nWithin 1 day of last day of submission of bids\nIssue of Letter of Award\nWithin 3 days of approval of award\nWithin 3 days of approval of award\nContract Signing\nWithin 15 days of Issue of Letter of Award\nWithin 15 days of Issue of Letter of Award\nDeclaration of the Bid results on State Public\n\t\t\t\tProcurement Portal and Departmental website\nWithin 3 days of issue of letter of acceptance.\nWithin 3 days of issue of letter of acceptance.\nTable : Time schedule for acceptance of bids by respective authority\n1\nFor bids to be accepted by an Executing Engineer\n\t\t\t\tor an Head of Office\n20 Days\n2\nFor bids to be accepted by a Superintending\n\t\t\t\tEngineer or a Regional Officer\n30 Days\n3\nFor bids to be accepted by an Additional Chief\n\t\t\t\tEngineer\n40 Days\n4\nFor bids to be accepted by a Chief Engineer or\n\t\t\t\tHead of the Department\n50 days\n5\nFor bids to be accepted by an Administrative\n\t\t\t\tDepartment\n60 Days\n6\nFor bids to be accepted by a Finance\n\t\t\t\tCommittee/Board/ Empowered Committee/ Empowered Board, etc.\n70 Days\n[Note: Communication of acceptance of tender shall also take place within the above limits of time period.]",
"footnote": "",
"is_definition": false,
"sort_order": 36
},
"prev_section": "37",
"next_section": "39"
}