Degree in Chemical or Electrical or Metallurgical or
Mechanical Engineering or its equivalent.
(i) A minimum experience of 10
years in - (a) design or erection or maintenance, or (b)
testing, examination and inspection of pressure plants.
(ii) He shall be - (a) conversant with the relevant codes
of practices and test procedures relating to pressure
vessels; (b) conversant with statutory requirements concerning
the safety of unfired pressure vessels and equipments operating
under pressure: (c) conversant with nondestructive testing
techniques as are applicable to pressure vessels; (d) able to
identify defects and arrive at a reliable conclusion with regard
to the safety of the pressure plant.
Facilities for carrying out hydraulic test, nondestructive
test, gauges equipment/gadgets for measurement and any other
equipment of gauges to determine the safety in the use of
pressure vessels.
6.
(i) Section 35-Precautions against dangerous fumes.
Master's degree in chemistry or a degree in chemical
Engineering.
(i) A minimum of 7 years in
collection & analysis of environmental samples and
calibration of monitoring equipments.:
(ii) He shall (a) be conversant with the hazardous
properties of chemical and their permissible limit values; (b)
be conversant with the current techniques of sampling and
analysis of the environmental contaminants; and (c) be able
to arrive at a reliable conclusion as regards the safety in
respect of entering and carrying out hot work.
Meters, instruments and devices duly calibrated and certified
for carrying out the tests and certification of safety in working
in confined spaces.
7.
Ventilation system as required under various schedules framed
under section 87, such as schedules on- (i) Grinding or
glazing of metals and process incidental there to
(ii) Cleaning or smoothing, roughening etc. of articles, by
gadgets sand, metal shot or grit of other abrasive propelled by a
– Blast of compressed air of steam;
(iii) Handling and processing of Asbestos;
(iv) Manufacture of Rayon by viscose process;
(v) Foundry operations.]
Degree in Mechanical or Electrical Engineering or equivalent.
(i) A minimum of 7 years in the design, fabrication,
installation, testing of ventilation system used for extraction
and collection of dusts, fumes and vapours and other ancillary
equipments;
(ii) He shall be conversant with relevant codes of practices
and test procedures that are current in respect of ventilation
and a traction system for fumes, and shall be able to arrive at a
reliable conclusion with regard to effectiveness of the system.
Facilities for testing the ventilation system, instruments and
gauges for testing the effectiveness of the extraction system for
dusts, vapours and fumes and any other equipment needed for
determining the efficiency and adequacy of these systems.
He shall have the assistance of a suitable qualified technical
person who can come to a reasonable conclusion as to the adequacy
of the system.
Rules 3 to 11 prescribed under Sub-section (1) of section 6
[3. Submission of plans.
(a) the site of the factory and immediate surrounding including adjacent building and other structures, roads, drains etc. drawn to a scale not less than [1 cm = 10 metres] ;
(b) the plan elevation and necessary cross sections of the factory buildings indicating all relevant details relating to natural lighting, ventilation and means of escape in case of fire. and the position of the plant and machinery, aisles and passage ways; and shall be drawn to a scale not less than [1 cm = 2 metres] ; and
(c) such other particulars as the Chief Inspector may require.]
[3A. Approval of plans.]
(a) A flow chart. of the manufacturing process supplemented by a brief description of the process in its various stages.
(b) Plans in duplicate drawn to scale showing:
(i) the site of the factory and immediate surroundings including adjacent buildings and other structures. roads. drains etc. drawn to a scale not less than [1 cm = 10 metres] , and
(ii) the plans. elevation and necessary cross-sections of the various buildings, indicating all relevant details relating to natural lighting, ventilation and means of escape in case of fire. The plans shall also clearly indicate the position of the plant and machinery, aisles and passage ways, and shall be drawn to a scale not less than [1 cm = 2 metres].
(c) Such other particulars as the Chief Inspector may require.
[3B. Prohibition of use of premises as factory without licence.
[3C. Certificate of Stability.
Form of Certificate of Stability
Form of Certificate of Stability
Section 31 • Rajasthan Factories Rules, 1951
Section 31 – 'Pressure Plant”
rajasthan-factories-rules-1951-sec-31.json
•
Section 31
{
"act_title": "Rajasthan Factories Rules, 1951",
"act_slug": "rajasthan-factories-rules-1951",
"section_label": "Section",
"section": {
"number": "31",
"title": "Section 31 – 'Pressure Plant”",
"chapter": null,
"content": "Degree in Chemical or Electrical or Metallurgical or\n\t\t\t\tMechanical Engineering or its equivalent.\n(i) A minimum experience of 10\n\t\t\t\tyears in - (a) design or erection or maintenance, or (b)\n\t\t\t\ttesting, examination and inspection of pressure plants.\n(ii) He shall be - (a) conversant with the relevant codes\n\t\t\t\tof practices and test procedures relating to pressure\n\t\t\t\tvessels; (b) conversant with statutory requirements concerning\n\t\t\t\tthe safety of unfired pressure vessels and equipments operating\n\t\t\t\tunder pressure: (c) conversant with nondestructive testing\n\t\t\t\ttechniques as are applicable to pressure vessels; (d) able to\n\t\t\t\tidentify defects and arrive at a reliable conclusion with regard\n\t\t\t\tto the safety of the pressure plant.\nFacilities for carrying out hydraulic test, nondestructive\n\t\t\t\ttest, gauges equipment/gadgets for measurement and any other\n\t\t\t\tequipment of gauges to determine the safety in the use of\n\t\t\t\tpressure vessels.\n6.\n(i) Section 35-Precautions against dangerous fumes.\nMaster's degree in chemistry or a degree in chemical\n\t\t\t\tEngineering.\n(i) A minimum of 7 years in\n\t\t\t\tcollection & analysis of environmental samples and\n\t\t\t\tcalibration of monitoring equipments.:\n(ii) He shall (a) be conversant with the hazardous\n\t\t\t\tproperties of chemical and their permissible limit values; (b)\n\t\t\t\tbe conversant with the current techniques of sampling and\n\t\t\t\tanalysis of the environmental contaminants; and (c) be able\n\t\t\t\tto arrive at a reliable conclusion as regards the safety in\n\t\t\t\trespect of entering and carrying out hot work.\nMeters, instruments and devices duly calibrated and certified\n\t\t\t\tfor carrying out the tests and certification of safety in working\n\t\t\t\tin confined spaces.\n7.\nVentilation system as required under various schedules framed\n\t\t\t\tunder section 87, such as schedules on- (i) Grinding or\n\t\t\t\tglazing of metals and process incidental there to\n(ii) Cleaning or smoothing, roughening etc. of articles, by\n\t\t\t\tgadgets sand, metal shot or grit of other abrasive propelled by a\n\t\t\t\t– Blast of compressed air of steam;\n(iii) Handling and processing of Asbestos;\n(iv) Manufacture of Rayon by viscose process;\n(v) Foundry operations.]\nDegree in Mechanical or Electrical Engineering or equivalent.\n(i) A minimum of 7 years in the design, fabrication,\n\t\t\t\tinstallation, testing of ventilation system used for extraction\n\t\t\t\tand collection of dusts, fumes and vapours and other ancillary\n\t\t\t\tequipments;\n(ii) He shall be conversant with relevant codes of practices\n\t\t\t\tand test procedures that are current in respect of ventilation\n\t\t\t\tand a traction system for fumes, and shall be able to arrive at a\n\t\t\t\treliable conclusion with regard to effectiveness of the system.\nFacilities for testing the ventilation system, instruments and\n\t\t\t\tgauges for testing the effectiveness of the extraction system for\n\t\t\t\tdusts, vapours and fumes and any other equipment needed for\n\t\t\t\tdetermining the efficiency and adequacy of these systems.\nHe shall have the assistance of a suitable qualified technical\n\t\t\t\tperson who can come to a reasonable conclusion as to the adequacy\n\t\t\t\tof the system.\nRules 3 to 11 prescribed under Sub-section (1) of section 6\n[3. Submission of plans.\n(a) the site of the factory and immediate surrounding including adjacent building and other structures, roads, drains etc. drawn to a scale not less than [1 cm = 10 metres] ;\n(b) the plan elevation and necessary cross sections of the factory buildings indicating all relevant details relating to natural lighting, ventilation and means of escape in case of fire. and the position of the plant and machinery, aisles and passage ways; and shall be drawn to a scale not less than [1 cm = 2 metres] ; and\n(c) such other particulars as the Chief Inspector may require.]\n[3A. Approval of plans.]\n(a) A flow chart. of the manufacturing process supplemented by a brief description of the process in its various stages.\n(b) Plans in duplicate drawn to scale showing:\n(i) the site of the factory and immediate surroundings including adjacent buildings and other structures. roads. drains etc. drawn to a scale not less than [1 cm = 10 metres] , and\n(ii) the plans. elevation and necessary cross-sections of the various buildings, indicating all relevant details relating to natural lighting, ventilation and means of escape in case of fire. The plans shall also clearly indicate the position of the plant and machinery, aisles and passage ways, and shall be drawn to a scale not less than [1 cm = 2 metres].\n(c) Such other particulars as the Chief Inspector may require.\n[3B. Prohibition of use of premises as factory without licence.\n[3C. Certificate of Stability.\nForm of Certificate of Stability\nForm of Certificate of Stability",
"footnote": "",
"is_definition": false,
"sort_order": 4
},
"prev_section": "29",
"next_section": "1"
}