1255. Selection of sites.

(b) The Executive Engineer will advise the committee on the points noted in the Works and Buildings Department Code, paragraph 146 and Appendix V. He will prepare a plan of the site selected embodying such information as may be necessary in each case, e.g., if the site is on land liable to be flooded, the highest flood level should be shown with reference to the general level of the site. He will forward this plan with the proceedings of the committee, after both have been countersigned by the members, to the Superintending Engineer of the Circle.
(c) The Superintending Engineer will, if he approves of the site and arrangements of the buildings, countersign the plan and forward it with the proceedings to the Deputy Inspector-General for countersignature and return to the Executive Engineer if he does not approve of the site or arrangement of the buildings, the Superintending Engineer will discuss the matter with the President of the site committee, and, if unable to agree, will forward the plan to the Deputy Inspector-General with his opinion.
(d) If the officers composing the committee are unable to agree as to the site proposed, the case should be referred to the Deputy Inspector-General for decision. A note of any objection made should be attached to the proceedings of the committee. After deciding the case so referred, the Deputy Inspector-General will communicate his decision and send the plan of the site approved by him to the Superintending Engineer and at the same time he will communicate his decision to the President of the site committee. In cases where the views of the Deputy Inspector-General differ from those of the Superintending Engineer the matter should be referred to Government through the Inspector-General for decision.
(e) In the case of important buildings the Deputy Inspector-General will, before countersigning the plan, send it through the Inspector-General to the Director of Health Services for opinion.
(f) No alteration in the relative positions of buildings on the site selected is permissible except with the authority of a fresh and properly constituted site committee.
(g) For further particulars see paragraph 146 and Appendix V of the Works and Buildings Department Code.