42. Permission for non-agricultural use.

(a) the area mentioned in clause (2) of the Explanation to section 47A, as a peripheral area of the Municipal Corporation or the Municipal Council;
(b) the areas falling within the control line of the National Highways, State Highways, District Roads or Village Roads;
(c) the areas notified as the Eco-sensitive Zone by the Government of India.]
[42A. No permission required for change of use of land situate in area covered by Development plan.
(a) no prior permission of the Collector shall be necessary for conversion of use of any land held as an Occupants—Class I for any purpose as defined in the sanctioned Development Plan or draft Development Plan prepared and published as per the provisions of the Maharashtra Regional and Town Planning Act, 1966 ; however, the Planning Authority shall ascertain from the concerned revenue authority the Class of land, its occupancy and encumbrances, if any, thereupon, and after ascertaining the same, it shall grant the development permission as per the provisions of the Maharashtra Regional and Town Planning Act, 1966 ;
(b) for conversion of use of any land held as an Occupants—Class II or land leased by the Government, for any purpose as defined in the sanctioned Development Plan or draft Development Plan prepared and published as per the provisions of the Maharashtra Regional and Town Planning Act, 1966, the occupant shall apply to the Planning Authority for permission to change the use of land, and the Planning Authority shall direct the said occupant to obtain no objection certificate of the Collector for such change; the Collector shall examine the documents by which the land is granted and the relevant laws by which the concerned land is governed and, if permissible to grant no objection certificate, require the applicant to pay the Nazarana and the Government dues for that purpose; and on payment of the same, the Collector shall issue no objection certificate for change of use of such land ; on receipt of such certificate, the concerned Planning Authority shall issue development permission as per the provisions of the Maharashtra Regional and Town Planning Act, 1966.
(b) While granting no objection certificate for the use of land under clause (b) of sub-section (1) or permission under the Code, the Collector shall grant the no objection certificate or permission relying upon the Data Bank prepared and certified by the concerned authorities at the District level.
(c) It shall be the responsibility of the District Head of the concerned Department to update the Data Bank, from time to time.]
[42B. Provision for conversion of land use for lands included in final Development plan area.
(a) in respect of land held as Occupant Class-I, within 30 days from the date of application ;
(b) in respect of land held as Occupant Class-II, -
(i) within 30 days from the date of application, where the Collector is competent to grant permission for change of use of such land at his level ;
(ii) within 30 days from the date on which the permission of the authority, competent to allow such conversion or change of use, is received by the Collector :