16. Effect of non-completion of project.

(i) formation and registration of a legal entity of sixty per cent of the flat purchasers in the manner as may be prescribed who have come before the Housing Regulatory Authority;
(ii) appointment of the legal entity as an escrow agent for taking over possession of the building and area appurtenant thereto, in the manner as may be prescribed;
(iii) directing the Competent Authority to transfer the Retained Flats in the name of the escrow agent within such period and in the manner as may be prescribed;
(iv) authorizing escrow agent to appoint contractors, consultants and other agencies required to complete the construction and obtain occupation certificate on such terms and conditions as may be decided by the escrow agent in the manner as may be prescribed:
(b) If the promoter, for reasons beyond his control, is unable to give possession of the flat by the date specified, or the further agreed date and a period of three months thereafter, or a further period of three months if those reasons still exist, then, the promoter shall be liable on demand, without prejudice to any other actions to which he may be liable, to refund the amount already received by him in respect of the flat with interest at a rate as my be prescribed including penalty as may be determined by the Housing Regulatory Authority.