3. Resource Plans.

3.2 Standard.
3.2.3 Each resource plan prepared by a Licensee shall be.
(ii) Appropriate, that is, it shall use a method of forecasting energy and/or capacity requirements that is technically suitable for the Licensee preparing it;
(iii) Robust, that is, firstly it shall identify key uncertainties, the plan's exposure to those uncertainties, and the manner in which those risks are to be managed; and secondly it shall identify sources of finance such that the plan may be judged realistic in those terms.
(iv) Uniform, that it it shall present the information and data in the plan in a standard format which contains clear definitions of the terms used.
3.3. Power Procurement Plans.
3.3.6. Each Power Procurement Plan shall consist of.
(ii) Energy utilisation, peak load and power factor data and annual load factors for the previous 5 years period.
(iii) Data for each existing generating station indicating energy and peaking capacity during plan period (as collected from Generating Companies) with due regard to hydrology and peak period discharge capacities of Hydro Electrical Plants.
(iv) Annual capacity and energy balance statements for the plan period, showing available net capacity from existing resources, station by station. Additional net generation capacity to be added indicating year of commission, and total capacity against planning criteria indices as achieved after each addition.
(v) Recommended plan for additional power procurement indicating unit sizes, type, gross capacity, year of commissioning, long run marginal cost along with annual details of incremental cost of generation and incremental net energy generated. It is recognised that insofar as HVPN will use competitive procurement to purchase new capacity from IPPs, the plan for additional power procurement need not identity specific generating units, specific sites or exact MW sizes, but shall identity plants and general location that are reasonably expected to be available from IPPs. Nevertheless HVPN shall include in the plan the results of its evaluation of alternative resources and justify, in terms of economic advantage, its preferred options for meeting new capacity requirements.
(vi) HVPN shall submit a two year implementation plan, consistent with and specifying the detail of the first two years of the Power Procurement Plan. The Licensee shall make explicit the steps it intends to take in the first two years that will enable the acquisition of the supply and demand side resources as anticipated in the remaining years of the Power Procurement Plan.
3.4 Transmission Planning.
3.5. Distribution Planning.
3.6. Commission's Review.