(a) on six monthly basis, in cases where the aggregate installed capacity of the generating stations or the stand by plant or captive generating plant is 100 MW or more, and
(b) on annual basis in other cases, considering the fuel consumed by the generating company for the generation of energy, the age of the generating plant, the rated capacity of the generating plant, the station heat rate and calorific value of the fuel used within 6 or 12 completed calendar months of the financial year. Such assessment shall be made before the completion of the subsequent three financial year.
Section 9 • Gujarat Green Cess Rules, 2011
9. Manner of Assessment of Cess .
gujarat-green-cess-rules-2011-sec-9.json
•
Section 9
{
"act_title": "Gujarat Green Cess Rules, 2011",
"act_slug": "gujarat-green-cess-rules-2011",
"section_label": "Section",
"section": {
"number": "9",
"title": "9. Manner of Assessment of Cess .",
"chapter": null,
"content": "(a) on six monthly basis, in cases where the aggregate installed capacity of the generating stations or the stand by plant or captive generating plant is 100 MW or more, and\n(b) on annual basis in other cases, considering the fuel consumed by the generating company for the generation of energy, the age of the generating plant, the rated capacity of the generating plant, the station heat rate and calorific value of the fuel used within 6 or 12 completed calendar months of the financial year. Such assessment shall be made before the completion of the subsequent three financial year.",
"footnote": "",
"is_definition": false,
"sort_order": 8
},
"prev_section": "8",
"next_section": "10"
}