Sections
1. Short Title, Extent and Commencement.
Section 12. Scope.
Section 23. Definitions.
Section 34. Connectivity.
Section 45. Application procedure for Connectivity to intra-State transmission system.
Section 56. Processing of Application and Grant of connectivity by STU.
Section 67. Application procedure for Connectivity to distribution system by a generating station.
Section 78. Processing of Application and Grant of connectivity to distribution system by a generating station.
Section 89. Eligibility for Open Access and conditions to be satisfied.
Section 910. Criteria for granting long-term access or medium-term open access or short term open access.
Section 1011. Categories of Open Access Customers.
Section 1112. Application procedure for Open Access.
Section 1213. Procedure for Long-Term Access.
Section 1314. Procedure for medium-term open access.
Section 1415. Procedure for short-term Open Access.
Section 1516. Consent by STU, SLDC or Distribution Licensee.
Section 1617. Consideration of applications from defaulters.
Section 1718. Application by eligible entities other than consumers and generating stations connected to distribution system.
Section 1819. Allotment Priority.
Section 1921. Transmission Charges.
Section 2122. Scheduling and system operation charges.
Section 2223. Wheeling Charges.
Section 2324. Cross subsidy surcharge.
Section 2425. Additional Surcharge.
Section 2526. Standby charges for drawal of power by open access customer from distribution licensee.
Section 2627. Other charges.
Section 2728. Scheduling.
Section 2829. Metering.
Section 2930. Revision.
Section 3031. Losses.
Section 3132. Imbalance Charge.
Section 3233. Reactive Energy Charge.
Section 3334. Billing, collection and disbursement.
Section 3435. Late payment surcharge.
Section 3536. Default in payment.
Section 3637. Payment Security Mechanism.
Section 3738. Information system.
Section 3842. Under-Utilisation or Non-Utilisation of open access capacity in intra-State transmission system.
Section 4243. Computation of capacity availability for open access.
Section 4344. Curtailment Priority.
Section 4445. Powers to Remove Difficulties.
Section 4546. Repeal and Savings.
Section 4610. The approved transaction shall be incorporated in day-ahead scheduling in accordance with the provisions of intra-state ABT. < only in case of approval>
Section 1011. Please submit following to SLDC with detials in the manner as specified in procedure: < only in case of approval>
Section 1112. The approval is subject to provisions of SERC (Terms and conditions for Intra State Open Access) Regulations, 2010 and any other relevant regulation/order/code as amended and applicable from time to time. < only in case of rejection >
Section 1213. No approvel is being granted on account of < only in case of rejection >
Section 13
gujarat-electricity-regulatory-commission-terms-and-conditions-of-intra-state-open-access-regulations-2011.json
•
46 Sections
•
Gujarat
{
"id": 16585,
"slug": "gujarat-electricity-regulatory-commission-terms-and-conditions-of-intra-state-open-access-regulations-2011",
"title": "Gujarat Electricity Regulatory Commission (Terms and Conditions of Intra-State Open Access) Regulations, 2011",
"short_title": "Gujarat Electricity Regulatory Commission (Terms and Conditions of Intra-State Open Access) Regulations, 2011",
"act_number": "(Regulation of No. 3 of 2011)",
"act_year": 2011,
"act_type": "STATE",
"location": "Gujarat",
"law_status": "unknown",
"enactment_date": null,
"description": "Gujarat Electricity Regulatory Commission (Terms and Conditions of Intra-State Open Access) Regulations, 2011",
"preamble": "",
"section_label": "Section",
"sections": [
{
"number": "1",
"title": "1. Short Title, Extent and Commencement.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 0
},
{
"number": "2",
"title": "2. Scope.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 1
},
{
"number": "3",
"title": "3. Definitions.",
"chapter": null,
"content": "(a) \"Act\" means the Electricity Act, 2003 (36 of 2003);\n(b) \"Allotted Capacity\" means the power transfer in MW between the specified point(s) of injection and point(s) of drawal allowed to a long-term/medium-term customer on the intra-State transmission system and the expression \"allotment of capacity\" shall be construed accordingly;\n(c) \"Applicant\" means a consumer, trader, distribution licensee or a Generating company who has applied seeking connectivity or open access as the case may be\n(d) \"Central Commission\" means the Central Electricity Regulatory Commission referred to in Section 76 of the Act;\n(e) \"Commission\" means the Gujarat Electricity Regulatory Commission referred to in Section 82 of the Act;\n(f) \"Consumer\" shall carry the same meaning as in the Act, but shall be restricted to such consumers within the State of Gujarat to whom these regulations will apply.\n(g) \"Contracted load\" means the load in kW/HP/kVA (kilo Watt/Horse Power/kilo Volt Ampere) which the distribution licensee has agreed to supply from time to time subject to the governing terms and conditions and is different from the connected load;\n(h) \"Day\" means a day starting at 00.00 hours and ending at 24.00 hours;\n(i) \"Distribution licensee\" means any person licensed under Part IV of the Act for distribution and retail supply of electricity in the State of Gujarat;\n(j) \"IEGC\" means the Indian Electricity Grid Code Specified by Central Electricity Regulatory Commission under clause (h) of sub-section (1) of section 79 of the Act, and as amended from time to time;\n(k) \"Imbalance\" in a time block for a generating station means its total actual generation minus its total scheduled generation and for a consumer or buyer means its total drawal minus its total scheduled drawal.\n(l) \"Long-term access\" means the right to use the intra-State transmission system or distribution system for a period exceeding 12 years but not exceeding 25 years.\n(m) \"Medium-term open access\" means the right to use the intra-State transmission system or distribution system for a period exceeding three months but not exceeding three years\n(n) \"Month\" means a calendar month as per the Gregorian calendar;\n(o) \"Nodal agency\" means the nodal agency defined in Regulation 12 of these regulations;\n(p) \"Open access\" means the non-discriminatory provision for the use of transmission lines or distribution system or associated facilities with such lines or system by any licensee or consumer or a person engaged in generation in accordance with these regulations and includes long-term access, medium-term open access and short-term open access.\n(q) \"Open access customer\" means a consumer, trader, distribution licensee or a generating company who has been granted open access under these regulations.\n(r) \"Reserved Capacity\" means the power transfer in MW between the specified point(s) of injection and point(s) of drawal allowed to a short-term customer on the transmission/distribution system depending on availability of transmission/distribution capacity and the expression \"reservation of capacity\" shall be construed accordingly;\n(s) \"Short-term open access\" means open access for a period upto one month at a time, but not exceeding a period of six months in a calendar year.\n(t) \"SLDC\" means the State Load Dispatch Centre established under subsection (1) of section 31 of the Act;\n(u) \"State Grid Code\" means the State Grid Code specified by the Commission under clause (h) of sub-section (1) of section 86 of the Act, applicable on the date of commencement of these regulations and as amended from time to time;\n(v) \"State Transmission Utility (STU)\" means the Government Company notified by the State Government under sub-section (1) of section 39 of the Act;\n(w) \"Transmission licensee\" means any person licensed under Part IV of the Act for transmission of electricity.\n(x) \"Transmission System Segment\" means a part or whole of the transmission system from the point of injection to the point of drawal.\nChapter 2\nConnectivity",
"footnote": "",
"is_definition": true,
"sort_order": 2
},
{
"number": "4",
"title": "4. Connectivity.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 3
},
{
"number": "5",
"title": "5. Application procedure for Connectivity to intra-State transmission system.",
"chapter": null,
"content": "Sr. No.\nSr. No.\nQuantum of power to be injected/off take\n\t\t\t\tinto/from Intra-state Transmission and/or distribution system\nQuantum of power to be injected/off take\n\t\t\t\tinto/from Intra-state Transmission and/or distribution system\nApplication fee(Rs. in lakh) For Connectivity\nApplication fee(Rs. in lakh) For Connectivity\n1\nUp to 100 MW\n2\n2\nMore than 100 MW and upto to 500 MW\n3\n3\nMore than 500 MW and up to 1000 MW\n6\n4\nMore than 1000 MW\n9",
"footnote": "",
"is_definition": false,
"sort_order": 4
},
{
"number": "6",
"title": "6. Processing of Application and Grant of connectivity by STU.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 5
},
{
"number": "7",
"title": "7. Application procedure for Connectivity to distribution system by a generating station.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 6
},
{
"number": "8",
"title": "8. Processing of Application and Grant of connectivity to distribution system by a generating station.",
"chapter": null,
"content": "Chapter 3\nGeneral Provisions for open Access",
"footnote": "",
"is_definition": false,
"sort_order": 7
},
{
"number": "9",
"title": "9. Eligibility for Open Access and conditions to be satisfied.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 8
},
{
"number": "10",
"title": "10. Criteria for granting long-term access or medium-term open access or short term open access.",
"chapter": null,
"content": "Chapter 4\nApplication Procedure and Approval",
"footnote": "",
"is_definition": false,
"sort_order": 9
},
{
"number": "11",
"title": "11. Categories of Open Access Customers.",
"chapter": null,
"content": "(1) System to which connected\n(a) Intra-State transmission system\n(b) Distribution system\n(2) Inter-se location of drawal and injection points\n(a) Both within the same distribution system\n(b) within the State of Gujarat but in different distribution systems\n(c) In different States\n(3) Duration of Open Access\n(a) Long-term access\n(b) Medium-term open access\n(c) Short-term open access",
"footnote": "",
"is_definition": false,
"sort_order": 10
},
{
"number": "12",
"title": "12. Application procedure for Open Access.",
"chapter": null,
"content": "Table 1\nTable 1\nOpen Access Customer connected to Distribution\n\t\t\t\tSystem\nOpen Access Customer connected to Distribution\n\t\t\t\tSystem\nS. No.\nS. No.\nPeriod\nPeriod\nInter-se location of drawal and injection\n\t\t\t\tpoint\nInter-se location of drawal and injection\n\t\t\t\tpoint\nNodal agency\nNodal agency\nApplication fee (Rs.)\nApplication fee (Rs.)\nDocuments to accompany the application\nDocuments to accompany the application\nTime frame for disposal of application (days\n\t\t\t\tfrom the receipt of application)\nTime frame for disposal of application (days\n\t\t\t\tfrom the receipt of application)\nApplicable Charges\nApplicable Charges\nApplicable Losses\nApplicable Losses\nCharges\nCharges\nCommercial Settlement\nCommercial Settlement\n1\nShort -Term Open Access (STOA)\nShort -Term Open Access (STOA)\nBoth within the same Distribution licensee\nBoth within the same Distribution licensee\nSLDC\n2000\n• Proof of payment of\n\t\t\t\tApplication fee.\n• PPA or Sale-purchase agreement of power\n• As provided in Regulation 15\n• Wheeling Charge • Cross\n\t\t\t\tSubsidy surcharge, and Additional surcharge, if any\n• Stand-by charges, if\n\t\t\t\tany\n• Imbalance and Reactive Energy Charges, as\n\t\t\t\tapplicable.\n}\nPrepared and Collected by Distribution licensee\n• Distribution loss in kind at relevant voltage\n\t\t\t\tlevel.\n2\nBoth within Gujarat but in areas of different\n\t\t\t\tDistribution Licensees\nBoth within Gujarat but in areas of different\n\t\t\t\tDistribution Licensees\nSLDC\n5000\n• Proof of payment of\n\t\t\t\tApplication fee,\n• Consent from the\n\t\t\t\tDistribution licensees concerned.\n• PPA or Sale-purchase agreement of power\n• As provided in Regulation 15\n• Wheeling Charge\n• Cross Subsidy\n\t\t\t\tsurcharge, Additional surcharge, if any\n• Stand-by charges, if\n\t\t\t\tany\n• Imbalance and\n\t\t\t\tReactive Energy Charges, as applicable.\n• Scheduling and system\n\t\t\t\tOperating Charges as applicable.\n• Transmission charge(Intra-State)\n}\n}\nPrepared and\n\t\t\t\tCollected by Distribution licensee\nPrepared and collected by SLDC\n• Distribution loss in\n\t\t\t\tkind at relevant voltage level in respect of both Distribution\n\t\t\t\tLicensees\n• Transmission loss in kind. (Intra-State)\n3\nInjection point in the intra-State\n\t\t\t\ttransmission system within Gujarat\nInjection point in the intra-State\n\t\t\t\ttransmission system within Gujarat\nSLDC\n5000\n• Proof of payment of\n\t\t\t\tApplication fee,\n• Consent from the\n\t\t\t\tDistribution licensees concerned.\n• PPA or Sale-purchase agreement of power\n• As provided in Regulation 15\n• Wheeling Charge\n• Cross Subsidy\n\t\t\t\tsurcharge, Additional surcharge, if any\n• Stand-by charges, if\n\t\t\t\tany\n• Imbalance and\n\t\t\t\tReactive Energy Charges, as applicable.\n• Scheduling and system\n\t\t\t\tOperating Charges, as applicable.\n• Transmission charge (Intra-State)\n}\n}\nPrepared and\n\t\t\t\tCollected by Distribution licensee and disburse.\nPrepared and collected by SLDC\n• Distribution loss in\n\t\t\t\tkind at relevant voltage level.\n• Transmission Loss in kind. (Intra-State)\n4\nIn different States\nIn different States\nRLDC of the region where consumer is located\nAs per CERC Regulation\n• Proof of payment of\n\t\t\t\tApplication fee,\n• Consent from the\n\t\t\t\tSLDCs and Distribution licensees concerned as applicable,\n• PPA or Sale-purchase agreement of power\nAs per Central Commission's Regulation\n• Wheeling Charges\n• Cross Subsidy\n\t\t\t\tsurcharge, Additional surcharge, if any\n• Stand-by charges, if\n\t\t\t\tany\n• Imbalance and\n\t\t\t\tReactive Energy Charges, as applicable.\n• Scheduling and system\n\t\t\t\tOperating Charges, as applicable\n• Transmission Charge (Intra-State and Inter\n\t\t\t\tState).\n}\n}\n}\n}\nPrepared and\n\t\t\t\tCollected by Distribution licensee and disburse.\nPrepared and\n\t\t\t\tcollected by SLDC\nPrepared and\n\t\t\t\tcollected by RLDC\nPrepared and collected by RLDC\n• Distribution loss in\n\t\t\t\tkind at relevant voltage level.\n• Transmission Loss in kind. (Intra-State and\n\t\t\t\tInter State).\n5\nMedium-Term Open\n\t\t\t\tAccess (MTOA)\nMedium-Term Open\n\t\t\t\tAccess (MTOA)\nBoth within the same Distribution licensee\nBoth within the same Distribution licensee\nSLDC\n25000\n• Proof of payment of\n\t\t\t\tApplication fee,\n• PPA or Sale-purchase\n\t\t\t\tagreement of power,\n• In case of generating station not already\n\t\t\t\tconnected to grid, documentary evidence for completion of the\n\t\t\t\tconnectivity showing that the same shall be completed before\n\t\t\t\tintended date of MTOA.\n30\n• Wheeling Charge\n• Cross Subsidy\n\t\t\t\tsurcharge, Additional surcharge, if any\n• Stand-by charges, if\n\t\t\t\tany\n• Imbalance and Reactive Energy Charges, as\n\t\t\t\tapplicable.\n}\nPrepared and Collected by Distribution licensee\n\t\t\t\tand disburse.\n• Distribution loss in kind at relevant voltage\n\t\t\t\tlevel.\n6\nBoth within Gujarat but different Distribution\n\t\t\t\tLicensees\nBoth within Gujarat but different Distribution\n\t\t\t\tLicensees\nSTU\n50000\n• Proof of payment of\n\t\t\t\tApplication fee,\n• PPA or Sale-purchase\n\t\t\t\tagreement of power,\n• In case of\n\t\t\t\tgenerating station not already connected to grid, documentary\n\t\t\t\tevidence showing that the connectivity shall be completed before\n\t\t\t\tintended date of MTOA,\n• Consent from the distribution licensees\n\t\t\t\tconcerned.\n40\n• Wheeling Charge\n• Cross Subsidy\n\t\t\t\tsurcharge, Additional surcharge, if any\n• Stand-by charges, if\n\t\t\t\tany\n• Imbalance and\n\t\t\t\tReactive Energy Charges, as applicable.\n• SLDC fees and charges\n• Transmission charge(Intra-State)\n}\n}\n}\nPrepared and\n\t\t\t\tCollected by Distribution licensee and disburse.\nPrepared and\n\t\t\t\tcollected by SLDC\nPrepared and collected by STU\n• Distribution loss in\n\t\t\t\tkind at relevant voltage level in respect of both Distribution\n\t\t\t\tLicensees\n• Transmission loss in kind. (Intra-State)\n7\nInjection point in the intra-State\n\t\t\t\ttransmission system within the State\nInjection point in the intra-State\n\t\t\t\ttransmission system within the State\nSTU\n50000\n• Proof of payment of\n\t\t\t\tApplication fee,\n• PPA or Sale-purchase\n\t\t\t\tagreement of power,\n• In case of\n\t\t\t\tgenerating station not already connected to grid, documentary\n\t\t\t\tevidence showing that the connectivity shall be completed before\n\t\t\t\tintended date of MTOA,\n• Consent from the Distribution licensees\n\t\t\t\tconcerned.\n40\n• Wheeling Charge\n• Cross Subsidy\n\t\t\t\tsurcharge, Additional surcharge, if any\n• Stand-by charges, if\n\t\t\t\tany\n• Imbalance and\n\t\t\t\tReactive Energy Charges, as applicable.\n• SLDC fees and\n\t\t\t\tcharges.\n• Transmission charge (Intra-State)\n}\n}\n}\nPrepared and\n\t\t\t\tCollected by Distribution licensee\nPrepared and\n\t\t\t\tcollected by SLDC\nPrepared and collected by STU\n• Distribution loss in\n\t\t\t\tkind at relevant voltage level.\n• Transmission Loss in kind. (Intra-State)\n8\nIn different States i.e Gujarat and other\n\t\t\t\tstates.\nIn different States i.e Gujarat and other\n\t\t\t\tstates.\nCTU\nAs per CERC Regulation\n• Proof of payment of\n\t\t\t\tApplication fee,\n• PPA or Sale-purchase\n\t\t\t\tagreement of power,\n• In case of\n\t\t\t\tgenerating station not already connected to grid, documentary\n\t\t\t\tevidence showing that the connectivity shall be completed before\n\t\t\t\tintended date of MTOA,\n• Consent from the SLDCs and Distribution\n\t\t\t\tlicensees concerned as applicable.\nAs per Central Commission's Regulation\n• Wheeling Charges\n• Cross Subsidy\n\t\t\t\tsurcharge, Additional surcharge, if any\n• Stand-by charges, if\n\t\t\t\tany\n• Imbalance and\n\t\t\t\tReactive Energy Charges, as applicable.\n• SLDC fees and\n\t\t\t\tcharges.\n• Transmission Charge (Intra-State and Inter\n\t\t\t\tState).\n}\n}\n}\nPrepared and\n\t\t\t\tCollected by Distribution licensee\nPrepared and\n\t\t\t\tcollected by SLDC\nPrepared and collected by STU\n• Distribution loss in kind at relevant voltage\n\t\t\t\tlevel. • Transmission Loss in kind. (Intra-State and Inter State).\n9\nLong -Term Access (LTA)\nLong -Term Access (LTA)\nBoth within the same Distribution licensee\nBoth within the same Distribution licensee\nSLDC\n25000\n• Proof of payment of\n\t\t\t\tApplication fee,\n• PPA or Sale-purchase\n\t\t\t\tagreement of power,\n• In case of generating station not already\n\t\t\t\tconnected to grid, documentary evidence showing that the\n\t\t\t\tconnectivity shall be completed before intended date of LTA\n30\n• Wheeling Charge\n• Cross Subsidy\n\t\t\t\tsurcharge, Additional surcharge, if any\n• Stand-by charges, if\n\t\t\t\tany\n• Imbalance and Reactive Energy Charges, as\n\t\t\t\tapplicable.\n}\nPrepared and Collected by Distribution licensee\n• Distribution loss in kind at relevant voltage\n\t\t\t\tlevel.\n10\nBoth within Gujarat but different Distribution\n\t\t\t\tLicensees\nBoth within Gujarat but different Distribution\n\t\t\t\tLicensees\nSTU\n50000\n• Proof of payment of\n\t\t\t\tApplication fee,\n• PPA or Sale-purchase\n\t\t\t\tagreement of power,\n• In case of\n\t\t\t\tgenerating station not already connected to grid, documentary\n\t\t\t\tevidence showing that the connectivity shall be completed before\n\t\t\t\tintended date of LTA,\n• Consent from the distribution licensees\n\t\t\t\tconcerned.\n• 120 days where\n\t\t\t\taugmentation of transmission system is not required\n• 150 days, where augmentation of transmission\n\t\t\t\tsystem is required.\n• Wheeling Charge \n\t\t\t\tCross Subsidy surcharge, Additional surcharge, if any\n• Stand-by charges, if\n\t\t\t\tany\n• Imbalance and\n\t\t\t\tReactive Energy Charges, as applicable.\n• SLDC fees and\n\t\t\t\tcharges.\n• Transmission charge(Intra-State)\n}\n}\n}\nPrepared and\n\t\t\t\tCollected by Distribution licensee\nPrepared and\n\t\t\t\tcollected by SLDC\nPrepared and collected by STU\n• Distribution loss in\n\t\t\t\tkind at relevant voltage level in respect of both Distribution\n\t\t\t\tLicensees\n• Transmission loss in kind. (Intra-State)\n11\nInjection point in the intra-State\n\t\t\t\ttransmission system within the State\nInjection point in the intra-State\n\t\t\t\ttransmission system within the State\nSTU\n50000\n• Proof of payment of\n\t\t\t\tApplication fee,\n• PPA or Sale-purchase\n\t\t\t\tagreement of power,\n• In case of\n\t\t\t\tgenerating station not already connected to grid, documentary\n\t\t\t\tevidence showing that the connectivity shall be completed before\n\t\t\t\tintended date of LTA,\n• Consent from the Distribution licensee\n\t\t\t\tconcerned.\n• 120 days where\n\t\t\t\taugmentation of transmission system is not required.\n• 150 days, where augmentation of transmission\n\t\t\t\tsystem is required.\n• Wheeling Charge\n• Cross Subsidy\n\t\t\t\tsurcharge, Additional surcharge, if any\n• Stand-by charges, if\n\t\t\t\tany\n• Imbalance and\n\t\t\t\tReactive Energy Charges, as applicable.\n• SLDC fees and charges\n• Transmission charge (Intra-State)\n}\n}\n}\nPrepared and Collected\n\t\t\t\tby Distribution licensee\nPrepared and collected\n\t\t\t\tby SLDC\nPrepared and collected by STU\n• Distribution loss in\n\t\t\t\tkind at relevant voltage level.\n• Transmission Loss in kind. (Intra-State)\n12\nIn different States i.e Gujarat and other\n\t\t\t\tstates.\nIn different States i.e Gujarat and other\n\t\t\t\tstates.\nCTU\nAs per CERC Regulation\n• Proof of payment of\n\t\t\t\tApplication fee,\n• PPA or Sale-purchase\n\t\t\t\tagreement of power,\n• In case of\n\t\t\t\tgenerating station not already connected to grid, documentary\n\t\t\t\tevidence showing that the connectivity shall be completed before\n\t\t\t\tintended date of LTA,\n• Consent from the SLDCs and Distribution\n\t\t\t\tlicensees concerned as applicable.\nAs per Central Commission's Regulation\n• Wheeling Charges\n• Cross Subsidy\n\t\t\t\tsurcharge, Additional surcharge, if any\n• Stand-by charges, if\n\t\t\t\tany\n• Imbalance and\n\t\t\t\tReactive Energy Charges, as applicable.\n• SLDC fees and charges\nTransmission Charge\n• (Intra-State and Inter State).\n}\n}\n}\nPrepared and Collected\n\t\t\t\tby Distribution licensee\nPrepared and collected\n\t\t\t\tby SLDC\nPrepared and collected by STU\n• Distribution loss in\n\t\t\t\tkind at relevant voltage level.\n• Transmission Loss in kind. (Intra-State and\n\t\t\t\tInter State).\nTable 2\nTable 2\nOpen Access Customer connected to Intra-State\n\t\t\t\tTransmission System\nOpen Access Customer connected to Intra-State\n\t\t\t\tTransmission System\nS. No.\nS. No.\nPeriod\nPeriod\nInter-se location of drawal and injection\n\t\t\t\tpoint\nInter-se location of drawal and injection\n\t\t\t\tpoint\nNodal agency\nNodal agency\nApplication fee (Rs.)\nApplication fee (Rs.)\nDocuments to accompany the application\nDocuments to accompany the application\nTime frame for disposal of application\nTime frame for disposal of application\nApplicable Charges\nApplicable Charges\nApplicable Losses\nApplicable Losses\nFor Capacity upto 100 MW\nFor Capacity upto 100 MW\nFor Capacity more than 100 MW\nFor Capacity more than 100 MW\nCharges\nCharges\nCommercial Settlement\nCommercial Settlement\n1\nShort -Term Open Access (STOA)\nShort -Term Open Access (STOA)\nBoth within the Gujarat (in the intra-State\n\t\t\t\ttransmission system)\nBoth within the Gujarat (in the intra-State\n\t\t\t\ttransmission system)\nSLDC\n5000\n5000\n• Proof of\n\t\t\t\tpayment of Application fee.\n• PPA or Sale-purchase agreement of power\n• As provided in Regulation 15\n• Imbalance and\n\t\t\t\tReactive Energy Charges as applicable. • Scheduling and\n\t\t\t\tsystem Operating Charges, as applicable\n• Transmission\n\t\t\t\tCharge (intra-State)\n• Wheeling Charge, if\n\t\t\t\tapplicable (ie. If fixed charge being paid by consumer could be\n\t\t\t\tattributed to wheeling/ distribution network related cost)\n• Cross-subsidy surcharge and additional surcharge\n\t\t\t\tif any\n}\n}\nPrepared and Collected by SLDC\nPrepared and collected by Distribution Licensee\n• Transmission Loss in kind. (intra-State).\n2\nInjection point in the distribution system\n\t\t\t\twithin Gujarat\nInjection point in the distribution system\n\t\t\t\twithin Gujarat\nSLDC\n5000\n5000\n• Proof of\n\t\t\t\tpayment of Application fee,\n• Consent from\n\t\t\t\tthe Distribution licensees concerned.\n• PPA or Sale-purchase agreement of power\n• As provided in Regulation 15\n• Imbalance and\n\t\t\t\tReactive Energy Charges, as applicable.\n• Scheduling and\n\t\t\t\tsystem, as applicable\n• Transmission\n\t\t\t\tCharge (Intra-State),\n• Cross-subsidy surcharge and additional\n\t\t\t\tsurcharge if any\n}\n}\nPrepared and\n\t\t\t\tCollected by SLDC\nPrepared and collected by Distribution Licensee\n• Distribution\n\t\t\t\tloss in kind at relevant.\n• Transmission loss in kind. (Intra-State)\n3\nIn different States and other states.\nIn different States and other states.\nRLDC of region where consumer is located\nAs per CERC Regulation\nAs per Regulation\n• Proof of\n\t\t\t\tpayment of Application fee,\n• Consent from\n\t\t\t\tthe SLDCs and Distribution licensee concerned as applicable.\n• PPA or Sale-purchase agreement of power\nAs per Central Commission's Regulation\n• Imbalance and\n\t\t\t\tReactive Energy Charges, as applicable.\n• Scheduling and\n\t\t\t\tsystem Operating Charges, as applicable\n• Transmission\n\t\t\t\tCharge (Intra-State),\n• Cross-subsidy\n\t\t\t\tsurcharge and additional surcharge if any\n}\n}\n}\nPrepared and\n\t\t\t\tCollected by SLDC\nPrepared and collected by RLDC\nPrepared and collected by Distribution Licensee\n• Distribution\n\t\t\t\tloss in kind at relevant voltage level, if applicable\n• Transmission Loss in kind. (Intra-State\n\t\t\t\tand Inter State).\n4\nMedium-Term Open\n\t\t\t\tAccess (MTOA)\nMedium-Term Open\n\t\t\t\tAccess (MTOA)\nBoth within the Gujarat (in the intra-state\n\t\t\t\ttransmission system)\nBoth within the Gujarat (in the intra-state\n\t\t\t\ttransmission system)\nSTU\n25000\n50000\n• Proof of\n\t\t\t\tpayment of Application fee,\n• PPA or\n\t\t\t\tSale-purchase agreement of power\n• In case of generating station or consumer not\n\t\t\t\talready connected to grid, documentary evidence showing that the\n\t\t\t\tconnectivity shall be completed before intended date of MTOA.\n30\n• Imbalance\n\t\t\t\tReactive Energy Charges, as applicable.\n• SLDC fees and\n\t\t\t\tCharges\n• Transmission\n\t\t\t\tCharge (Intra-state),\n• Cross-subsidy\n\t\t\t\tsurcharge and additional surcharge if any\n}\n}\n}\nPrepared and\n\t\t\t\tCollected by SLDC\nPrepared and\n\t\t\t\tcollected by STU\nPrepared and collected by Distribution Licensee\n• Transmission Loss in kind. (Intra-State).\n5\nInjection point in the distribution system\n\t\t\t\twithin Gujarat\nInjection point in the distribution system\n\t\t\t\twithin Gujarat\nSTU\n25000\n50000\n• Proof of\n\t\t\t\tpayment of Application fee,\n• PPA or\n\t\t\t\tSale-purchase agreement of power,\n• In case of generating station or consumer\n\t\t\t\tnot already connected to grid, documentary evidence showing that\n\t\t\t\tthe connectivity shall be completed before intended date of MTOA.\n• Consent from the Distribution licensee\n\t\t\t\tconcerned.\n30\n• Imbalance and\n\t\t\t\tReactive Energy Charges, as applicable.\n• SLDC fees and\n\t\t\t\tcharges\n• Transmission\n\t\t\t\tCharge (Intra-State),\n• Cross-subsidy and additional surcharge if\n\t\t\t\tany\n}\n}\n}\nPrepared and Collected by SLDC\nPrepared and collected by STU\nPrepared and collected by Distribution Liecensee\n• Distribution loss in kind at relevant\n\t\t\t\tvoltage level.\n• Transmission Loss in kind. (Intra-State).\n6\nIn diffirent State i.e Gujarat and other\n\t\t\t\tstates.\nIn diffirent State i.e Gujarat and other\n\t\t\t\tstates.\nCTU\nAs per CERC Regulation\nAs per CERC Regulation\n• Proof of\n\t\t\t\tpayment of Application fee,\n• PPA or\n\t\t\t\tSale-purchase agreement of power,\n• In case of\n\t\t\t\tgenerating station or consumer not already connected to grid,\n\t\t\t\tdocumentary evidence showing that the connectivity shall be\n\t\t\t\tcompleted before intended date of MTOA,\n• Consent from the distribution licensee\n\t\t\t\tconcerned, as applicable\nAs per Central Commission's Regulation\n• imbalance and\n\t\t\t\tReactive Energy Charges, as applicable.\n• SLDC fees and \n\t\t\t\tCharges.\n• Transmission\n\t\t\t\tCharge (Intra-State),\n• Cross-subsidy\n\t\t\t\tsurcharge and additional surcharge if any\n}\n}\n}\nPrepared and\n\t\t\t\tCollected by SLDC\nPrepared and\n\t\t\t\tcollected by STU\nPrepared and collected by Distribution Licensee\n• Distribution\n\t\t\t\tloss in kind at relevant voltage level, if applicable\n• Transmission loss in kind. (Intra-State)\n7\nLong -Term Access (LTA)\nLong -Term Access (LTA)\nBoth within Gujarat (in the intra-state\n\t\t\t\ttransmission system)\nBoth within Gujarat (in the intra-state\n\t\t\t\ttransmission system)\nSTU\n50000\n100000\n• Proof of\n\t\t\t\tpayment of Application fee,\n• Bank\n\t\t\t\tGuarantee,\nPPA or Sale-purchase\n\t\t\t\tagreement of power,\n• In case of generating station or consumer\n\t\t\t\tnot already connected to grid, documentary evidence showing that\n\t\t\t\tthe connectivity shall be completed before intended date of LTA,\n• 120 days where augmentation of transmission\n\t\t\t\tsystem is not required.\n• 150 days where augmentation of transmission\n\t\t\t\tsystem is required.\n• Imbalance and\n\t\t\t\tReactive Energy Charges, as applicable\n• SLDC fees and \n\t\t\t\tcharges\n• Transmission\n\t\t\t\tCharge (Intra-State),\n• Cross-subsidy\n\t\t\t\tsurcharge and additional surcharge if any\n}\n}\n}\nPrepared and\n\t\t\t\tCollected by SLDC\nPrepared and\n\t\t\t\tcollected by STU\nPrepared and collected by Distribution Licensee\n• Transmission Loss in kind. (Intra-State)\n8\nInjectino point in the distribution system\n\t\t\t\twithin Gujarat\nInjectino point in the distribution system\n\t\t\t\twithin Gujarat\nCTU\n50000\n100000\n• Proof of\n\t\t\t\tpayment of Application fee,\n• Bank Guarantee,\n• PPA or\n\t\t\t\tSale-purchase agreement of power,\n• In case of\n\t\t\t\tgenerating station or consumer not already connected to grid,\n\t\t\t\tdocumentary evidence showing that the connectivity shall be\n\t\t\t\tcompleted before intended date of LTA,\n• Consent from the Distribution licensee\n\t\t\t\tconcerned.\n• 120 days where augmentation of transmission\n\t\t\t\tsystem is not required.\n• 150 days, where augmentation of transmission\n\t\t\t\tsystem is required.\n• Imbalance and\n\t\t\t\tReactive Energy Charges, as applicable.\n• SLDC fees and\n\t\t\t\tcharges.\n• Transmission\n\t\t\t\tCharge (Intra-State),\n• Wheeling\n\t\t\t\tCharge, if applicable (i.e If fixed charge being paid by consumer\n\t\t\t\tcould be atributed to wheeling/distribution network related cost)\n• Cross-subsidy\n\t\t\t\tsurcharge and additional surcharge if any\n}\n}\n}\n}\nPrepared and\n\t\t\t\tCollected by SLDC\nPrepared and\n\t\t\t\tcollected by STU\nPrepared and collected by Distribution Licensee\n• Distribution loss in kind at relevant\n\t\t\t\tvoltage level. • Transmission Loss in kind.\n\t\t\t\t(Intra-State).\n9\nIn different States i.e Gujarat and other\n\t\t\t\tstates.\nIn different States i.e Gujarat and other\n\t\t\t\tstates.\nCTU\nAs per CERC Regulation\nAs per CERC Regulation\n• Proof of\n\t\t\t\tpayment of Application fee,\n• Bank Guarantee,\n• PPA or\n\t\t\t\tSale-purchase agreement of power,\n• In case of generating station or consumer\n\t\t\t\tnot already connected to grid, documentary evidence showing that\n\t\t\t\tthe connectivity shall be completed before intended date of LTA\n• Consent from the STU and Distribution licensee\n\t\t\t\tconcerned, as applicable.\nAs per Central Commission's Regulation\n• Imbalance and\n\t\t\t\tReactive Energy Charges, as applicable.\n• SLDC fees and charges\n• Transmission\n\t\t\t\tCharge (Intra-State),\n• Cross-subsidy surcharge and additional\n\t\t\t\tsurcharge if any\n}\n}\n}\nPrepared and Collected by SLDC\nPrepared and collected by STU\nPrepared and collected by Distribution Licensee\n• Distribution loss in kind at relevant\n\t\t\t\tvoltage level, If applicable\n• Transmission Loss in kind. (Intra-state and \n\t\t\t\tInter State).",
"footnote": "",
"is_definition": false,
"sort_order": 11
},
{
"number": "13",
"title": "13. Procedure for Long-Term Access.",
"chapter": null,
"content": "(1) Involving inter-State transmission system:\n(2) Involving only intra-State transmission system:\n(a) The application for grant of long-term access shall contain details such as name of the entity or entities from whom electricity is proposed to be procured or to whom to be supplied along with the quantum of power and such other details as may be laid down by the State Transmission Utility in the detailed procedure:\n(b) The applicant shall submit any other information sought by the nodal agency including the basis for assessment of power to be interchanged using the intra-State transmission system and power to be transmitted to or from various entities or regions to enable the nodal agency to plan the intra-State transmission system in a holistic manner.\n(c) The application shall be accompanied by a bank guarantee of Rs 10,000/- (ten thousand) per MW of the total power to be transmitted. The bank guarantee shall be in favour of the nodal agency, in the manner laid down under the detailed procedure.\n(d) The bank guarantee of Rs. 10,000 /- (ten thousand) per MW shall be kept valid and subsisting till the execution of the long-term access agreement, in the case when augmentation of transmission system is required, and till operationalization of long-term access when augmentation of transmission system is not required.\n(e) The bank guarantee may be encashed by the nodal agency, if the application is withdrawn by the applicant or the long-term access rights are relinquished prior to the operationalisation of such rights when augmentation of transmission system is not required.\n(f) The aforesaid bank guarantee will stand discharged with the submission of bank guarantee required to be given by the applicant to the State Transmission Utility during construction phase when augmentation of transmission system is required, in accordance with the provisions in the detailed procedure.\n(g) On receipt of the application, the nodal agency shall, in consultation and through coordination with other agencies involved in intra-State transmission system to be used, process the application and carry out the necessary system studies as expeditiously as possible so as to ensure that the decision to grant long-term access is arrived at within the timeframe specified in clause 3 of Regulation 12 herein above:\n(h) Based on the system studies, the nodal agency shall specify the intra- State transmission system that would be required to give long-term access. In case augmentation to the existing intra-State transmission system is required, the same will be intimated to the applicant.\n(i) While granting long-term access, the nodal agency shall communicate to the applicant, the date from which long-term access shall be granted and an estimate of the transmission charges likely to be payable based on the prevailing costs, prices and methodology of sharing of transmission charges specified by the Commission.\n(j) The applicant shall sign an agreement for long-term access with the State Transmission Utility in case long-term access is granted by the State Transmission Utility, in accordance with the provision as may be made in the detailed procedure. While seeking long-term access to an intra-State transmission licensee, other than the State Transmission Utility, the applicant shall sign a tripartite long-term access agreement with the State Transmission Utility and the intra-State transmission licensee. The long-term access agreement shall contain the date of commencement of long-term access, the point of injection of power into the grid and point of drawal from the grid and the details of dedicated transmission lines, if any, required. In case augmentation of transmission system is required, the long-term access agreement shall contain the time line for construction of the facilities of the applicant and the transmission licensee, the bank guarantee required to be given by the applicant and other details in accordance with the detailed procedure.\n(k) Immediately after grant of long-term access, the nodal agency shall inform the State Load Despatch Centre so that it can consider the same while processing requests for grant of short-term open access, received under these regulations.\n(l) On the expiry of the period of long-term access, the same shall stand extended on a written request by the consumer, to the Sate Transmission Utility, submitted at least six months prior to such expiry, mentioning the period for which extension is required:\n(3) Within the same distribution system:",
"footnote": "",
"is_definition": false,
"sort_order": 12
},
{
"number": "14",
"title": "14. Procedure for medium-term open access.",
"chapter": null,
"content": "(1) Involving inter-State transmission system:\n(2) Involving only intra-State transmission system:\n(a) The application for grant of medium-term open access shall contain such details as may be laid down under the detailed procedure and shall, in particular, include the point of injection into the grid, point of drawal from the grid and the quantum of power for which medium-term open access has been applied for.\n(b) The start date of the medium-term open access shall not be earlier than 5 months and not later than 1 year from the last day of the month in which application has been made.\n(c) On receipt of the application, the nodal agency shall, in consultation and through coordination with other agencies involved in intra-State transmission, process the application and carry out the necessary system studies as expeditiously as possible so as to ensure that the decision to grant or refuse medium-term open access is made within the timeframe specified in clause (3) of Regulation 12 herein above:\n(d) On being satisfied that the requirements specified under clause (2) of Regulation 10 are met, the nodal agency shall grant medium-term open access for the period stated in the application:\n(e) Immediately after grant of medium-term open access, the nodal agency shall inform the State Load Despatch Centre so that it can consider the same while processing requests for short-term open access received under these regulations.\n(f) On expiry of the period of the medium-term open access, the medium-term consumer shall not be entitled to any overriding preference for renewal of the term.\n(3) Within the same distribution system:",
"footnote": "",
"is_definition": false,
"sort_order": 13
},
{
"number": "15",
"title": "15. Procedure for short-term Open Access.",
"chapter": null,
"content": "(1) Involving inter-State transmission system:\n(2) Involving only intra-State transmission system:\n(a) Open Access in advance\n(a) Open Access in advance\n(i) Application may be submitted to the Nodal Agency seeking short-term open access upto the fourth month, considering the month in which an application is made being the first month.\n(ii) Separate application shall be made for each month and for each transaction in a month.\n(iii) The application to the Nodal agency shall be on the prescribed form given in FORMAT-ST1 containing such details as capacity needed, generation planned or power purchase contracted, point of injection, point of drawal, duration of availing open access, peak load, average load and such other additional information as may be required by the Nodal agency. The application shall be accompanied by a non-refundable application fee in cash or by demand draft in favour of the officer so notified by Nodal agency.\nFORMAT-ST1\n(iv) An application for grant of open access commencing in any month may be submitted in a cover marked \"Application for Short-Term Open Access - in advance\" upto 15th day of the preceding month.\n(v) Nodal agency shall acknowledge receipt of the application by indicating time and date on \"ACKNOWLEDGEMENT\" to the applicant.\n(vi) A consumer of distribution licensee intending to avail open access shall also furnish a copy of his application to the distribution licensee of his area of supply.\n(vii) Based on the type of transactions Nodal agency shall take a decision on the applications for short-term open access in the manner provided herein below.\n(viii) All applications received under sub-sub-clause (iv) above shall be taken up for consideration together and processed as per allotment priority criteria specified under Regulation 19 of these regulations.\n(ix) Nodal agency shall check transaction for congestion of any element (line and transformer) of transmission and distribution system involved in transaction.\n(x) Nodal agency shall convey grant of open access or otherwise in FORMAT-ST2 along with schedule of payments to the consumer latest by 21st day of such preceding month.\nFORMAT-ST2\n(xi) Nodal agency shall assign specific reasons if open access is denied under sub-sub clause (x).\n(b) Day-Ahead Open Access\n(b) Day-Ahead Open Access\n(i) An application for grant of day-ahead open access may be received by Nodal agency within three days prior to the date of scheduling but not later than 1300 Hours of the day immediately preceding the day of scheduling for day-ahead transaction.\n(ii) Nodal agency shall check for congestion and convey grant of approval or otherwise in FORMAT-ST2 . All other provisions of application for short-term open access shall apply.\nFORMAT-ST2\n(c) Procedure for scheduling transaction in a contingency.\n(c) Procedure for scheduling transaction in a contingency.\n(d) Bidding Procedure\n(d) Bidding Procedure\n(i) If the capacity sought by the consumers for Open Access in Advance for the following month is more than the available capacity or SLDC perceives congestion of any element of transmission and distribution system involved in the transaction, the allocation shall be made through electronic bidding procedure.\n(ii) The decision of SLDC in respect of an expected congestion shall be final and binding.\n(iii) SLDC shall convey information of congestion and decision for invitation of bidding indicating floor price in FORMAT-ST3 to the applicants .\nFORMAT-ST3\n(iv) SLDC shall also display the bidding information on its website.\n(v) The floor price of transmission and wheeling charges determined on the basis of relevant order of the Commission shall be indicated in FORMAT-ST3 .\nFORMAT-ST3\n(vi) The Bids shall be accepted in FORMAT-ST4 upto the \"bid closing time\" as indicated in bidding invitation FORMAT-ST3 . Modification / amendment to a bid, once submitted shall not be entertained.\nFORMAT-ST4\nFORMAT-ST3\n(vii) If any consumer does not participate in bidding process, his application shall be deemed to have been withdrawn and shall not be processed.\n(viii) SLDC shall not entertain any request for extension of time/date for submission of bids.\n(ix) The bidders shall quote price (rounded-off to whole number) in denomination in which floor price has been determined.\n(x) The quoted price shall be arranged in descending order and allocation of available capacities shall be accorded in such descending order until the available capacity is exhausted.\n(xi) In case of equal price quoted by two or more consumers, the allocation from the residual available capacity at any stage under sub-sub-clause (x) above shall be made in proportion to capacity being sought by such consumers.\n(xii) All consumers, in favour of whom full capacities have been allotted, shall pay the highest price obtained from bids.\n(xiii) The consumers, who are allotted less capacity, shall pay the price as quoted by them .\n(xiv) SLDC shall reject bids which are incomplete, vague in any manner or not found in conformity with the bidding procedure.\n(xv) The successful bidder, in favour of whom the capacities have been allocated, shall pay transmission charges, wheeling charges, as the case may be, determined by bidding under sub-sub clause (xii) or (xiii) of this clause.\n(e) The reserved capacity by a short-term open access customer is not transferable to others.\n(f) The capacity available as a result of surrender or reduction or cancellation of the reserved capacity by the State Load Dispatch Centre, may be reserved for any other short-term open access customer in accordance with these regulations.\n(g) On expiry of the period of the short-term open access, the short-term consumer shall not be entitled to any overriding preference for renewal of the term.\n(2) Within the same distribution system:",
"footnote": "",
"is_definition": false,
"sort_order": 14
},
{
"number": "16",
"title": "16. Consent by STU, SLDC or Distribution Licensee.",
"chapter": null,
"content": "(1) Inter-State open access :\n(2) Intra-State Open Access :\n(a) In respect of a consumer connected to a distribution system seeking Open access, such consumer shall be required to submit the consent of the distribution licensee concerned. The distribution licensee shall convey its consent to the applicant by e-mail or fax or by any other usually recognised mode of communication, within three (3) working days of receipt of the application.\n(b) While processing the application from a generating station seeking consent for open access, the distribution licensee shall verify the following, namely-\n(i) Existence of infrastructure necessary for time-block-wise energy metering and accounting in accordance with the provisions of the State Grid Code in force,\n(ii) Availability of capacity in the distribution network, and.\n(iii) Availability of RTU and communication facility to transmit real- time data to SLDC.\n(c) Where existence of necessary infrastructure and availability of capacity in the distribution network has been established, the distribution licensee shall convey its consent to the applicant by e-mail or fax or by any other usually recognised mode of communication, within three (3) working days of receipt of the application.\n(d) In case the nodal agency finds that the application for consent is incomplete or defective in any respect, it shall communicate the deficiency or defect to the applicant by e-mail or fax or by any other usually recognised mode of communication, within two (2) working days of receipt of the application:\n(e) In case the application has been found to be in order but the distribution licensee refuses to give consent on the grounds of non-existence of necessary infrastructure or unavailability of surplus capacity in the distribution network, such refusal shall be communicated to the applicant by e-mail or fax or by any other usually recognized mode of communication, within the period of three (3) working days from the date of receipt of the application, along with reasons for such refusal:\n(f) Where the distribution licensee has not communicated any deficiency or defect in the application within two (2) days from the date of receipt of application, or refusal or consent within the specified period of three (3) working days from the date of receipt of the application consent shall be deemed to have been granted.",
"footnote": "",
"is_definition": false,
"sort_order": 15
},
{
"number": "17",
"title": "17. Consideration of applications from defaulters.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 16
},
{
"number": "18",
"title": "18. Application by eligible entities other than consumers and generating stations connected to distribution system.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 17
},
{
"number": "19",
"title": "19. Allotment Priority.",
"chapter": null,
"content": "(a) A distribution Licensee shall have the highest priority in allotment of open access capacity irrespective of whether the open access request is for long-term, medium-term or short-term.\n(b) The long-term access applicants shall have the priority next to the distribution licensee.\n(c) The medium-term open access applicants shall have the priority next to the long- term access applicants.\n(d) The short-term open access applicants shall have the priority next to the medium- term open access applicants.\n(e) Allotment priority for short-term open access applicants shall be decided subject to capacity availability.\n(f) An existing open access customer shall have the priority higher than new open access applicants under respective category provided the former applies for its renewal thirty days prior to the expiry of existing term of open access.\n(g) When the requirement projected by an applicant is more than the available capacity and the said applicant is not able to limit his requirement to the available capacity, the request of applicant having next lower priority shall be taken up for consideration.\nChapter 5\nSubmission Of Detailed Procedure\n20.\n(a) The proformae for application of connectivity and the connection agreement, referred to regulation 6 and 8 above.\n(b) The proformae for application of long-term access and medium-term open access and LTA/MTOA agreements.\n(c) Any other issues, including Bank Guarantee for construction, payment mechanisms for application fee etc., necessary for implementation of these regulations.\nChapter 6\nOpen Access Charges",
"footnote": "",
"is_definition": false,
"sort_order": 18
},
{
"number": "21",
"title": "21. Transmission Charges.",
"chapter": null,
"content": "(1) For use of inter-State transmission system :\nAs specified by the Central Commission from time to time.\n(2) For use of intra-State transmission system :\n(i) By Long-Term and Medium-Term Open Access Customers:\n[(ii) By Short-Term Open Access Customers:\n= 24 × TTC /(ACs× 8760) (In Rs./MW/day)\nTTC = Total Transmission Cost determined by the Commission for the transmission system for the relevant year (in Rs.) and\nACs = Sum of capacities allocated to all long-term and medium-term open access customers in MW.",
"footnote": "",
"is_definition": false,
"sort_order": 19
},
{
"number": "22",
"title": "22. Scheduling and system operation charges.",
"chapter": null,
"content": "(1) In respect of inter-State open access\n(a) Long-term access and Medium-term open access\n(i) Regional Load Despatch Centre fees and charges including charges for the Unified Load Despatch and Communication Scheme as specified by the Central Commission under section 28(4) of the Act.\n(ii) State Load Despatch Centre fees and charges as specified by the Commission under sub-section (3) of section 32 of the Act.\n(b) Short-term open access\n(i) Regional Load Despatch Centre and State load dispatch centre fees and charges as specified by the Central Commission.\n(2) In respect of intra-State open access\n(2) In respect of intra-State open access\n(a) Long-term access and medium-term open access Long-term access and medium-term open access customers shall be liable to pay SLDC fees and charges determined by the Commission under sub-section (3) of section 32 of the Act.\n(b) Short-term open access",
"footnote": "",
"is_definition": false,
"sort_order": 20
},
{
"number": "23",
"title": "23. Wheeling Charges.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 21
},
{
"number": "24",
"title": "24. Cross subsidy surcharge.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 22
},
{
"number": "25",
"title": "25. Additional Surcharge.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 23
},
{
"number": "26",
"title": "26. Standby charges for drawal of power by open access customer from distribution licensee.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 24
},
{
"number": "27",
"title": "27. Other charges.",
"chapter": null,
"content": "Chapter 7\nScheduling, Metering, Revision and Losses",
"footnote": "",
"is_definition": false,
"sort_order": 25
},
{
"number": "28",
"title": "28. Scheduling.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 26
},
{
"number": "29",
"title": "29. Metering.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 27
},
{
"number": "30",
"title": "30. Revision.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 28
},
{
"number": "31",
"title": "31. Losses.",
"chapter": null,
"content": "(1) Transmission losses:\n(a) Inter-State transmission:\n(i) Long-term access and medium-term open access: The buyers shall bear apportioned energy losses in the transmission system in accordance with the provisions specified by the Central Commission.\n(ii) Short-term Open Access: The buyers and sellers shall absorb apportioned energy losses in the transmission system in accordance with the provisions specified by the Central Commission.\n(b) Intra-State transmission:\n(2) Distribution loss.\nChapter 8\nImbalance and Reactive Energy Charges",
"footnote": "",
"is_definition": false,
"sort_order": 29
},
{
"number": "32",
"title": "32. Imbalance Charge.",
"chapter": null,
"content": "• The energy consumption of such customer shall be recorded in 15 minutes time block.\n• In case of actual energy drawl is more than the scheduled energy drawl but within the contracted demand, customer shall be liable to pay for such over drawl at the applicable tariff rates as determined by the Commission time to time.\n• In case of actual energy drawl is more than the scheduled energy drawl and also more than the contracted demand, payment for the capacity above the contract demand shall have to be made at the penal rate as specified by the Commission for such categories of customers in the tariff schedule.\n• Provided that in case of under drawl as a result of non-availability of the distribution system or unscheduled load shedding, the open access customers shall be compensated by the distribution licensee at the rate of compensation notified by the Commission under standard of performance regulations for relevant category of consumers.",
"footnote": "",
"is_definition": false,
"sort_order": 30
},
{
"number": "33",
"title": "33. Reactive Energy Charge.",
"chapter": null,
"content": "Chapter 9\nCommercial Matters",
"footnote": "",
"is_definition": false,
"sort_order": 31
},
{
"number": "34",
"title": "34. Billing, collection and disbursement.",
"chapter": null,
"content": "(1) Inter-State transactions:\n(a) Short-term Open Access\n(a) Short-term Open Access\n(i) Collection and disbursement of transmission charges for use of CTU and STU systems and operating charges payable to RLDCs and SLDCs towards short-term open access shall be made by the nodal RLDC in accordance with the procedure specified by the Central Commission.\n(ii) The short-term open access customer connected to distribution system of a distribution licensee shall pay to such distribution licensee the charges payable to the distribution licensee within 3 days from the grant of the short-term open access by the nodal agency.\n(b) Long-term access and medium- term open access\n(b) Long-term access and medium- term open access\n(i) Billing, collection and disbursement of charges payable to RLDC including Unified Load Despatch and Communication Scheme shall be in accordance with the procedure specified by the Central Commission.\n(ii) Bills towards the charges payable to SLDC shall be raised by the STU/SLDC directly to the open access customer connected to STU and to the distribution licensee in respect of the customers connected to the distribution system, before the 3rd working day of the succeeding calendar month.\n(iii) Distribution licensee shall raise the bill with the open access customer connected to it within 3 days of receipt of bill from SLDC.\n(iv) Open access customer connected to the distribution licensee shall pay the charges within five days of receipt of bill from distribution licensee. The distribution licensee shall disburse the amount payable to STU/SLDC on a monthly basis.\n(v) Open access customer connected to the STU shall pay the bills within five working days of receipt of the bill.\n(2) Intra-State transactions:\n(a) Short-term Open Access\n(a) Short-term Open Access\n(i) The short-term open access customer shall deposit with SLDC the transmission charges and operating charges within 3 working days of grant of the short-term open access by SLDC.\n(ii) In addition to the above, the short-term open access customer connected to distribution system of a distribution licensee shall also pay to SLDC, the charges payable to the distribution licensee within 3 days from the grant of the short-term open access by the nodal agency. Such charges would be disbursed to the distribution licensee on a weekly basis.\n(b) Long-term and Medium-Term open access. - SLDC, transmission licensees and distribution licensee, where applicable, shall communicate to STU the details of the bills due to them by the 3rd day of the succeeding calendar month. STU shall separately indicate the above charges and raise the bill with the open access customer, together with the charges receivable by it, if any, before the 5th day of the above month. The open access customer shall pay the charges within 7 days from the date of receipt of the bill. STU shall disburse the charges payable to SLDC, transmission licensee and distribution licensee on a monthly basis.\n(b) Long-term and Medium-Term open access.",
"footnote": "",
"is_definition": false,
"sort_order": 32
},
{
"number": "35",
"title": "35. Late payment surcharge.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 33
},
{
"number": "36",
"title": "36. Default in payment.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 34
},
{
"number": "37",
"title": "37. Payment Security Mechanism.",
"chapter": null,
"content": "Chapter 10\nInformation System",
"footnote": "",
"is_definition": false,
"sort_order": 35
},
{
"number": "38",
"title": "38. Information system.",
"chapter": null,
"content": "(1) A status report on long-term access or medium-term open access customers indicating:\n(a) Name of customer;\n(b) Period of open access granted (date of commencement and date of termination);\n(c) Point of injection;\n(d) Point of drawal;\n(e) Transmission system/distribution system used, and\n(f) Open access capacity used.\nThe above mentioned details shall be provided by STU to State Load Dispatch Centre.\n(2) A status report on the current short-term open access customers indicating:\n(a) Name of customer;\n(b) Period of open access granted (date of commencement and date of termination);\n(c) Point of injection;\n(d) Point of drawal;\n(e) Transmission system/distribution system used, and;\n(f) Open access capacity used.\n(3) Peak load flows and capacity available including the reserve capacity on all EHV lines and HV lines emanating from EHV sub-stations.\n(4) The information regarding average loss in transmission and distribution system as determined by respective licensees.\nChapter 11\nOpen Access to Generating Station Connected to Distribution System\n39.\n40.\n41.\n(1) While processing the application from a generating station seeking open access, the distribution licensee shall verify the following, namely-\n(a) Existence of infrastructure necessary for time-block-wise energy metering and accounting in accordance with the provisions of the State Grid Code in force,\n(b) Availability of capacity in the distribution network, and\n(c) Availability of RTU and communication facility to transmit real time data to SLDC.\n(2) Where existence of necessary infrastructure and availability of capacity in the distribution network has been established, the distribution licensee shall convey its approval within the timelines indicated in clause (3) of Regulation 12 herein above as applicable to a consumer.\n(3) In case the distribution licensee finds that the application is incomplete or defective in any respect, it shall communicate the deficiency or defect to the applicant by e-mail or fax or by any other usually recognised mode of communication, within two (2) working days of receipt of the application.\n(4) In case the application has been found to be in order but the distribution licensee refuses to give approval for open access on the grounds of non-existence of necessary infrastructure or unavailability of surplus capacity in the distribution network, such refusal shall be communicated to the applicant by e-mail or fax or by any other usually recognized mode of communication, within the period of three (3) working days from the date of receipt of the application, along with reasons for such refusal\n(5) The Generating station shall pay the wheeling charge to the distribution licensee as determined by the Commission.\n(6) In case the generating station is not able to inject the scheduled power due to non-availability of distribution system, the distribution licensee shall compensate the generating station to the extent of the difference between the UI charge payable by the generating station and the charges receivable by the generating station from the Open Access Customer in case the later is lower.\nChapter 12\nMiscellaneous",
"footnote": "",
"is_definition": false,
"sort_order": 36
},
{
"number": "42",
"title": "42. Under-Utilisation or Non-Utilisation of open access capacity in intra-State transmission system.",
"chapter": null,
"content": "(a) Long-term customer who has availed access rights for at least 12 years\n(a) Long-term customer who has availed access rights for at least 12 years\n(i) Notice of one (1) year - If such a customer submits an application to the State Transmission Utility at least 1 (one) year prior to the date from which such customer desires to relinquish the access rights, there shall be no charges.\n(ii) Notice of less than one (1) year - If such a customer submits an application to the State Transmission Utility at any time less than a period of 1 (one) year prior to the date from which such customer desires to relinquish the access rights, such customer shall pay an amount equal to 66% of the transmission charges for the stranded transmission capacity for the period falling short of a notice period of one (1) year.\n(b) Long-term customer who has not availed access rights for at least 12 (twelve) years - such customer shall pay an amount equal to 66% of the estimated transmission charges (net present value) for the stranded transmission capacity for the period falling short of 12 (twelve) years of access rights:\n(b) Long-term customer who has not availed access rights for at least 12 (twelve) years\n(c) The discount rate that shall be applicable for computing the net present value as referred to in sub-clause (a) and (b) of clause (1) above shall be the discount rate to be used for bid evaluation in the Central Commission's Notification issued from time to time in accordance with the Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by distribution Licensees issued by the Ministry of Power.\n(d) The compensation paid by the long-term customer for the stranded transmission capacity shall be used for reducing transmission charges payable by other long-term customers and medium-term customers in the year in which such compensation payment is due in the ratio of transmission charges payable for that year by such long- term customers and medium-term customers.\n(2) Medium-term Open Access customers\n(3) Short-term open access customer\n(a) The short-term open access schedules accepted by the nodal agency in advance or on first-come-first-served basis may be cancelled or revised downwards on an application to that effect made to the nodal agency by the short-term open access customer:\n(b) The person seeking cancellation or downward revision of short-term open access schedule shall pay the transmission charges for the first two (2) days of the period for which the cancellation or downward revision of schedule, as the case may be, has been sought, in accordance with the schedule originally approved by the nodal agency, and thereafter in accordance with the revised schedule prepared by the nodal agency during the period of such cancellation or downward revision.\n(c) In case of cancellation, operating charges specified in Regulations 21 of these regulations shall be payable for two (2) days or the period of cancellation in days, whichever is less.",
"footnote": "",
"is_definition": false,
"sort_order": 37
},
{
"number": "43",
"title": "43. Computation of capacity availability for open access.",
"chapter": null,
"content": "(a) Available open access capacity of a transmission system segment: = (DC-SD-AC) + NC - ND where, DC=Designed capacity of the transmission segment in MW, SD = Sustained demand (peak load experienced) in MW recorded in the segment, AC = Already allotted capacity, but not availed in MW, NC = New capacity in MW expected to be added and ND = New Demand expected to be added.\n(b) Available open access capacity of a sub-station: = (TC-SP-AC)+NC - ND where, TC= Transformer capacity of the sub-station in MVA, SP= Sub-station peak in MVA, AC= Already allotted capacity but not availed in MVA , New transformer capacity in MVA expected to be added and ND = New Demand expected to be added.\n(c) The STU shall update these values on a quarterly basis on the first calendar day of the first month of the quarter and publish it on their website.",
"footnote": "",
"is_definition": false,
"sort_order": 38
},
{
"number": "44",
"title": "44. Curtailment Priority.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 39
},
{
"number": "45",
"title": "45. Powers to Remove Difficulties.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 40
},
{
"number": "46",
"title": "46. Repeal and Savings.",
"chapter": null,
"content": "Formats for Short-Term\nFormat- St 1\nFormat- St 1\nApplication for Grant of Short-term open Access\nApplication for Grant of Short-term open Access\n(to be submitted by the customer to Nodal Agency)\n1\nCustomer Application No\n< Self generted by customer>\nDate\n2\nPeriod of Transaction\n<1 month and less than 1 month/day\n\t\t\t\tahead/same day>\n3\nNature of Customer*\n< Seller/buyer/captive user/trader(on behalf\n\t\t\t\tof seller/buyer/captive user)>\n<* In Term of power transfer >\n4\nCustomer Name\n5\nRegistration Code\nValid up to\n< Regulations code shall be an provided by SLDC>\n6\nDetails of Transaction Party's to Grid\nInjecting Entry\nDrawee Entity\nName of Entry\nStatus of Entry**\nUtility in which is Embedded\n<**In terms of ownership state utility/CPP/IPP/ISGS/Discos/Consumer/specify, if any other>\n7\nDetails of injecting/Drawee Connectively with\n\t\t\t\tintra-State System\nInjecting Entry\nDrawee Entity\nName of Sub-station\nTransmission\nDistribution\nVoltage Level\nTransmission\nDistribution\nName of Licensee (Owner of S/S)\nIntervening intra-State Licensee\nIntervening intra-State Licensee\n8\nOpen Access Sought for (Period from date\n\t\t\t\t__________________ to date_________________)\nDate\nHours\nCapacity\nFrom\nTo\nFrom\nTo\nMW***\n9\nDetails of PPA/PSA/MOU\nName/& Address of Parties\nDate of PPA/PSA/MOU\nValidity Period\nCapacity\nSeller\nBuyer\nCommencement\nExpiry\nMW****\n10\nDetails of Non-Refundable Application Fee Mode\nBank Details\nInstrument Details\nAmount (Rs.)\nType(Draft/Cash)\nInstrument No.\nDate\n11\nI hereby authorize Nodal Agency to process said\n\t\t\t\tapplication in case open access capacity allotted, for day ahead\n\t\t\t\tscheduling in accordance with the provisions of intra-State ABT\n12\nDeclaration\nAll Entries/Utilities to transaction shall abide\n\t\t\t\tby provisions of the Electricity Act, 2003 (the Act)\n\t\t\t\tSERC (Terms and Conditions for Intra-State Open Access)\n\t\t\t\tRegulation and any other relevant regulation/order/code as\n\t\t\t\tamended from time to time.\nPlace Date\nSignature (with Stamp) Name & Designation\nEnclosures\n(1) Non-refundable application fee by Demand draft or cash receipt (if payment by cash).\n(2) Self-certified copy of PPA/PSA/MoU entered between the parties (buyer and seller) of transaction stating contracted power, period of transaction, drawal pattern, point(s) of injection and drawal etc.\n(3) Self-certified copies of concurrence of STU and/or transmission licensee and/or distribution licensee. (If period of transaction is of three months and more)\n(4) If any other\nCopy to along with relevant enclosures [except (1) & (2)]:\n(1) Managing Director of transmission licensee involved in transaction.\n(2) Managing Director of distribution licensee involved in transaction\n(3) Officer in charge of transmission substation involved in transaction.\n(4) Officer in charge of distribution substation involved in transaction.\n(5) Any other concerned.\nFor use of SLDC (with Reference to Enrolment of\n\t\t\t\tApplication)\nSLDC Reference ID No.\nNodel SLDC Approval No.\n< if approved>\nOr Reasons of Refusal***** (if Refused)\n< ***** SLDC may also enclose supporting documents for the reasons of refusal duly signed on each page>\nFormats for Short-Term\nAcknowledgement\nAcknowledgement\n(for office use only)\nApplication for Grant of Short-Term open Access\nApplication for Grant of Short-Term open Access\n(A) < to be filled by the Customer>\n1\nCustomer Application No\n< Self generted by customer>\nDate\n2\nPeriod of Transaction\n<1 months and more/less than 1 months/day\n\t\t\t\tahead>\n3\nNature of Customer*\n< Seller/buyer/captive user/trader(on behalf\n\t\t\t\tof seller/buyer/captive user)>\n<* In Term of power transfer>\n4\nCustomer Name\n5\nRegistration Code\nValid up to\n< Regulations code shall be an provided by SLDC>\n(B) < to be filled by SLDC>\nDetails and Time of Receipt of Application\nPlace Date\nPlace Date\nSignature (With Stamp) Name & Designation\nSignature (With Stamp) Name & Designation\n...................................................................................\nAcknowledgement\nAcknowledgement\n(to be issued by SLDC to the customer immediately on receipt of application duty filled in)\nApplication for Grant of Short-Term Open Access\nApplication for Grant of Short-Term Open Access\n(A) < to be filled by the Customer>\n1\nCustomer Application No\n< Self generted by customer>\nDate\n2\nPeriod of Transaction\n<1 months and more/less than 1 months/day\n\t\t\t\tahead>\n3\nNature of Customer**\n< Seller/buyer/captive user/tradition behalf\n\t\t\t\tof seller/buyer/captive user)>\n<** In Term of power transfer>\n4\nCustomer Name\n5\nRegistration Code\nValid up to\n< Regulations code shall be an provided by SLDC>\n(B) < to be filled by SLDC>\nDate and Time of Receipt of Application\nPlace Date\nPlace Date\nSignature (With Stamp) Name & Designation\nSignature (With Stamp) Name & Designation\nN.B.\nFormat for short-term\nFormat-ST2\nFormat-ST2\nApproval for short-term open Access\nApproval for short-term open Access\n(to be issued by SLDC)\nNodel SLDC Approval No.\n/(R-0)\nDate\n< 'R-O' status original approval with revision no. - zero >\n1\nCustomer Application No\n< as provided by customer on Format-ST1>\nDate\n2\nPeriod of Transaction\n<1 month and less than 1 month/day\n\t\t\t\tahead/same day>\n3\nNature of Customer*\n< Seller/buyer/captive user/trader behalf\n\t\t\t\tof seller/buyer/captive user)>\n<* In Term of power transfer>\n4\nCustomer Name\n5\nRegistration Code\nvalid up to\n6\nDetails of Transaction Party's to Grid\nInjecting Entry\nDecree Entry\nName of Entity\nStatus of Entity**\nUtility in which is Embedded\n<** In terms of ownership state utility/CPP/IPP/ISGS/Discos/Consumer/specify, if any other>\n7\nDetails of injecting/Drawee Connectively with\n\t\t\t\tintra-State System\nInjecting Entry\nDecree Entry\nName of Sub-station\nTransmission\nDistribution\nVoltage Level\nTransmission\nDistribution\nName of Licensee (Owner of S/S)\nIntervening intra-State Licensee\nIntervening intra-State Licensee\n8\nOpen Access Approved for (Period from date\n\t\t\t\t__________________ to date_________________)\nRevision No\n0\nMonth\nDate\nHours\nCapacity MW\nMWH\nFrom\nTo\nFrom\nTo\nApplied\nAllotted\nTotal MWH\n9\nDetails of Bidding < only in case of Bidding>\nDetails of Intra-State System\nDate\nHours\nApplicable Rate (Rs./KWH)\nFrom\nTo\nFrom\nTo\nTransmission System\nDistribution System",
"footnote": "",
"is_definition": false,
"sort_order": 41
},
{
"number": "10",
"title": "10. The approved transaction shall be incorporated in day-ahead scheduling in accordance with the provisions of intra-state ABT. < only in case of approval>",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 42
},
{
"number": "11",
"title": "11. Please submit following to SLDC with detials in the manner as specified in procedure: < only in case of approval>",
"chapter": null,
"content": "(a) SLDC Fee Amount Rs. _________ (b) Security Amount Rs. __________\n(a) SLDC Fee Amount Rs. _________ (b) Security Amount Rs. __________\nDue Date: ___________ Due Date: ___________\nDue Date: ___________ Due Date: ___________",
"footnote": "",
"is_definition": false,
"sort_order": 43
},
{
"number": "12",
"title": "12. The approval is subject to provisions of SERC (Terms and conditions for Intra State Open Access) Regulations, 2010 and any other relevant regulation/order/code as amended and applicable from time to time. < only in case of rejection >",
"chapter": null,
"content": "< only in case of rejection >",
"footnote": "",
"is_definition": false,
"sort_order": 44
},
{
"number": "13",
"title": "13. No approvel is being granted on account of < only in case of rejection >",
"chapter": null,
"content": "< SLDC shall convey specific reasons if open access is denied and may also enclore supporting documents the same duly signed on each page >\nPlace Date\nPlace Date\nSignature (with stamp) Name & Designation\nSignature (with stamp) Name & Designation\nEnclosure\n(1) Schedule of payments < only in case of approval >\n(2) If any other\nCopy to along with enclosures\n(1) Customer\n(2) Managing Director of transmission licensee involved in transaction.\n(3) Managing Director of distribution licensee involved in transaction\n(4) officer in charge of transmission substation involved in transaction.\n(5) Officer in charge of distribution substation involved in transaction.\n(6) Any other concerned.\nFormats for short-term\nEnclosure to Format-ST2\nEnclosure to Format-ST2\nSchedule of Payments\nSchedule of Payments\n(to be enclosed for each month by SLDC along with FormatST2)\nNodel SLDC Approval No.\n/(R-0)\nDate\n1\nCustomer Application No\n<as provided by customer on Format-ST1>\nDate\n2\nPeriod of Transaction\n<1 month and less than 1 month/day\n\t\t\t\tahead/same day>\n3\nNature of Customer*\n< Seller/buyer/captive user/trader(on behalf\n\t\t\t\tof seller/buyer/captive user)>\n<* In Term of power transfer>\n4\nCustomer Name\n5\nRegistration Code\nvalid up to\n6\nTentative** Monthly Payment Schedule for\n\t\t\t\tShort-Term Open Access Charges ( Period: date ____ to date\n\t\t\t\t____ )\nMonth\nPayment Chargeable for\nRate (Rs./kWh)\nMWh\nTotal (Rs.)\n(1) Intra-State Network\n(a) Transmission Charges\nconcerned Transmission Licensee\nIntervening intra-State Licensee(if any)\n(b) Wheeling Charges\nconcerned Distribution Licensee\nIntervening intra-State Licensee(if any)\n(c) Surcharge\nconcerned Distribution Licensee\n(d) Additional Surcharge\nconcerned Distribution Licensee\n(e) SLDC Charges\nSLDC\n(2) Inter-State Network\nTransmission Charges\nIntervening inter-State Licensee(if any)\nTotal Monthly Payment Amount (Rs.)\nTotal Monthly Payment Amount (Rs.)\nPlace Date\nPlace Date\nSignature (With Stamp) Name & Designation\nSignature (With Stamp) Name & Designation\n** Tentative on the basis of MWh mentioned in application which may vary on actual operation.\nFormat for short-term\nFormat-ST3\nFormat-ST3\nCongestion Information and Invitation of Bidding\nCongestion Information and Invitation of Bidding\n(to be invited by SLDC)\nSLDC Bidding Invitation No. ___________\nDate ____________________________\n1\nCustomer Application No\n<as provided by customer on Format-ST1>\nDate\n2\nPeriod of Transaction\n<1 month and less than 1 month/day\n\t\t\t\tahead/same day>\n3\nNature of Customer*\n< Seller/buyer/captive user/tradition behalf\n\t\t\t\tof seller/buyer/captive user)>\n<* In Term of power transfer>\n4\nCustomer Name\n5\nRegistration Code\nvalid up to\n6.\nThe anticipated congestion (transformer and\n\t\t\t\telectric line/link) is as follow:\nNetwork Corridor\nCongestion Period\nMargin/Capacity Available\nTotal Capacity Applied by all the Customers\nSub-station with Transformation Capacity\nElectric Line/Link with Capacity\nDate\nHours\nFrom\nTo\nFrom\nTo\nMW\nMW\nIntra-State Transmission System\nIntra-State Distribution System\nInter-State Transmission System\n7.\nIn view of above please submit bid on format [FORMAT-ST4]. \n\t\t\t\tThe details for bidding are hereunder:\n(a) Bid Invitation Date\nTime\n(b) Bid Submission Date\nTime\n(c) Bid Opening Date\nTime\n(d) Bid Invited for\nIntra-State Network Corridor\nCongestion Period\nMargin/Capacity Available for Bidding\nFloor Price\nSub-station\nElectric Line/Link\nDate\nHours\nFrom\nTo\nFrom\nTo\nMW\nRs./kWh\nName of Transmission System\nName of Distribution System\n8.\nIn case of non submission of bid, application shall be \n\t\t\t\tdeemed to have been withdrawn and shall not be processed.\nPlace Date\nPlace Date\nSignature (With Stamp) Name & Designation\nSignature (With Stamp) Name & Designation\nTo: Customers with their references < as provided by customers at sl.no. 1 on Format-ST1 >\nFormat for short-term\nFormat-ST4\nFormat-ST4\nBID Proposal\nBID Proposal\n(to be submitted by the customer to SLDC)\nRef: Nodal Agency Bidding Invitation No. ___________\nDate ____________________________\nDate ____________________________\nTo: Nodal Agency,\n1\nCustomer Application No\n< as provided by customer on Format-ST1>\nDate\n2\nPeriod of Transaction\n<1 month and less than 1 month/day\n\t\t\t\tahead/same day>\n3\nNature of Customer*\n< Seller/buyer/captive user/trader (on behalf\n\t\t\t\tof seller/buyer/captive user)>\n<* In Term of power transfer>\n4\nCustomer Name\n5\nRegistration Code\nvalid up to\n6.\nIn reference to above bidding invitation, \n\t\t\t\tI hereby submit my bid as follows:\nBidding Details as provided by Noday Agency\nBid Price to be Quoted by Bidder\nIntra-State Network Corridor\nCongestion Period\nMargin/Capacity Available for Bidding\nFloor Price\nSub-station\nElectric Line/Link\nDate\nHours\nFrom\nTo\nFrom\nTo\nMW\nPaise/Kwh\nPaise/Kwh**\nName of Transmission System\nName of Distribution System\n< ** Bidder shall quote price (rounded-off to whole number) in denotation of floor price >\n7.\nI do hereby agree that determined bid price(s) shall be \n\t\t\t\ttransmission and/or wheeling charges.\nPlace Date\nPlace Date",
"footnote": "",
"is_definition": false,
"sort_order": 45
}
],
"metadata": {
"Act ID": "Last Updated 15th October, 2019 [guj358]",
"Act Number": "(Regulation of No. 3 of 2011)",
"Enactment Date": "",
"Act Year": "2011",
"Short Title": "Gujarat Electricity Regulatory Commission (Terms and Conditions of Intra-State Open Access) Regulations, 2011",
"Type": "STATE",
"Location": "Gujarat"
},