← Back to Goa Value Added Tax Rules, 2005

4. Determination of taxable turnover.

(a) turnover of sales of goods on which no tax is leviable under the Act;
(b) turnover of sales of goods which has been exempted from tax;
(c) which have been taken place in the course of inter-state trade within the meaning of section 3 of the Central Sales Tax Act, 1956 (Central Act 74 of 1956) or in the course of import of the goods into or export of the goods out of the Territory of India within the meaning of section 5 of the said Central Sales Tax Act, 1956;
(d) the sale price of the goods returned to the dealer by the purchaser within a period of six months from the date of delivery thereof;
(e) sales made outside the State of goods stock transferred/consigned to other States;
(f) sales through local agents (registered dealer) on behalf of the principal.
Explanation.
[4A. Determination of sale price in respect of Works Contract.
Table
Table
Sr. No.
Classification of works contract
Deduction in Percentage to be allowed for
determining the sale price
(1)
(2)
(3)
1
In respect of road work, including asphalting of road,
construction of culverts, site gutters but excluding bridges.
30% of the gross receipts.
2
In respect of electrical works including building wiring &
fittings, installation of sub-stations, transmission and
distribution lines, control rooms, power grid stations,
installation of high mast electric polls, illumination of
bridges, illumination of urban and rural areas including
installation of under ground cables, installation of generator
sets, transformers and such other electrical works.
35% of the gross receipts.
3
In respect of construction of new buildings and erection of
civil structures (temporary or permanent)
33% of the gross receipts.
4
In respect of renovation and maintenance of buildings
40% of the gross receipts.
5
In respect of painting works (internal and external)
50% of the gross receipts.
6
In respect of water supply and sanitation works, including
providing and laying of conveying main or distribution of water
supply lines and sanitation lines, construction of ground level
reservoirs/overhead reservoirs, pumping stations, control valves
and chambers, main hole chambers, improvement in water supply
systems and sewage system, etc.
30% of the gross receipts.
7
In respect of construction of bridges
35% of the gross receipts.
8
In respect of irrigation and water resources projects,
including construction of tube wells, ground water resources,
projects, construction of dams, bandara, sluice gate, canals,
development of spring, lakes, wells and agricultural bunds, etc.
35% of the gross receipts.
9
In respect of jobworks of processing or altering or adapting,
where the goods consumed in such process cannot be separately
measured.
70% of the gross receipts.
10
Annual maintenance contract (AMC)
80% of the gross receipts.
11
Any other works
30% of the gross receipts]