The Commissioner may refuse to approve the site on which an applicant proposes to erect or re -
erect any building-
(a) that the erection or re -erection of the proposed building on such site would be in
contravention of a town-planning scheme under section 291 or of any other provision of this Act
or of any other enactment for the time being in force; or
(b ) the site is in a portion within the limits of the City in which the position and direction of the
streets have not been determined, and that the building which it is proposed to erect on such site
126 | P a g e
Madhya Pradesh Municipal Corporation Act, 1956
will, in the opinion of the Commissioner, obstruct or interfere with the construction in future of
suitable streets in such portion or with the drainage, water-supply or ventilation thereof:
Provided that any person to whom permission to erect or re -erect a building on such a site
has been refused may, by written notice to the Chief Executive Officer require that the position
and direction of streets to be laid down in future in th e vicinity of the proposed building should
be forthwith determined, and if such requisition is not complied with within one year from the
date thereof, may, subject to all other provisions of this Act applicable there to, proceed with the
erection of his building; or
(c) that the site has been re -claimed or used as a place for depositing sewage, offensive matter
rubbish or then carcasses of dead animals or is otherwise in sanitary or dangerous to health ; or
(d) that the site is in a portion within the limits of th e City for which a town -planning scheme
has not been sanctioned by the Government and that the building which it is proposed to erect or
re-erect on such site will, in the opinion of the Commissioner, be likely to conflict in a manner,
to be communicated in writing to the applicant, with the provisions of a town-planning scheme:
Provided that any person to whom permission to erect or re -erect a building on such a site
has been refused may, by written notice to the Chief Executive Officer, require that the
preparation of a town -planning scheme for the portion in which the site is situated shall be
proceeded with as early as possible; and if the applicant is not informed in writing within twelve
months of the date of the requisition that the Government have sa nctioned the said town -
planning scheme, he may subject to all the other provisions of this Act applicable there to
proceed with the erection or re -erection of the building in respect of which the application was
made.
Section 296 • The Chhattisgrah Municipal Coproration Act, 1956.
Section 296. Grounds on which site of proposed building may be disapproved.-
chhattisgrah-municipal-coproration-act-1956-sec-296.json
•
Section 296
{
"act_title": "The Chhattisgrah Municipal Coproration Act, 1956.",
"act_slug": "chhattisgrah-municipal-coproration-act-1956",
"section_label": "Section",
"section": {
"number": "296",
"title": "Section 296. Grounds on which site of proposed building may be disapproved.-",
"chapter": null,
"content": "The Commissioner may refuse to approve the site on which an applicant proposes to erect or re - \nerect any building- \n(a) that the erection or re -erection of the proposed building on such site would be in \ncontravention of a town-planning scheme under section 291 or of any other provision of this Act \nor of any other enactment for the time being in force; or \n(b ) the site is in a portion within the limits of the City in which the position and direction of the \nstreets have not been determined, and that the building which it is proposed to erect on such site \n\n126 | P a g e \nMadhya Pradesh Municipal Corporation Act, 1956 \n \n \nwill, in the opinion of the Commissioner, obstruct or interfere with the construction in future of \nsuitable streets in such portion or with the drainage, water-supply or ventilation thereof: \nProvided that any person to whom permission to erect or re -erect a building on such a site \nhas been refused may, by written notice to the Chief Executive Officer require that the position \nand direction of streets to be laid down in future in th e vicinity of the proposed building should \nbe forthwith determined, and if such requisition is not complied with within one year from the \ndate thereof, may, subject to all other provisions of this Act applicable there to, proceed with the \nerection of his building; or \n(c) that the site has been re -claimed or used as a place for depositing sewage, offensive matter \nrubbish or then carcasses of dead animals or is otherwise in sanitary or dangerous to health ; or \n(d) that the site is in a portion within the limits of th e City for which a town -planning scheme \nhas not been sanctioned by the Government and that the building which it is proposed to erect or \nre-erect on such site will, in the opinion of the Commissioner, be likely to conflict in a manner, \nto be communicated in writing to the applicant, with the provisions of a town-planning scheme: \nProvided that any person to whom permission to erect or re -erect a building on such a site \nhas been refused may, by written notice to the Chief Executive Officer, require that the \npreparation of a town -planning scheme for the portion in which the site is situated shall be \nproceeded with as early as possible; and if the applicant is not informed in writing within twelve \nmonths of the date of the requisition that the Government have sa nctioned the said town - \nplanning scheme, he may subject to all the other provisions of this Act applicable there to \nproceed with the erection or re -erection of the building in respect of which the application was \nmade.",
"footnote": "",
"is_definition": false,
"sort_order": 305
},
"prev_section": "295",
"next_section": "297"
}