(a) Wherever top soil exists and is to be excavated for quarrying operation, it shall be removed separately;
(b) The top soil so removed shall be stored for future use;
(c) The dumps shall be properly secured to prevent escape of material therefrom and cause land degradation or damage to agricultural fields, pollution of surface water bodies or cause floods;
(d) The site of dumps shall be selected, as far as possible, on impervious and barren ground within the leased area; and
(e) The top soil dumps shall be suitably terraced and established through vegetation or otherwise.
(a) Every holder of an Quarry Lease/Quarry Permit shall take steps so that the over burden, waste rock, rejects and fines generated during quarrying or during sizing shall be stored in separate dumps;
(b) The dumps shall be properly secured and shall be suitably terraced and stabilised through vegetation or otherwise;
(c) Wherever possible, the waste rock, over burden etc. shall be back-filled into the mined out area excavations with a view to restoring the land to its original use as far as possible.
Section 63 • Chhattisgarh Minor Mineral Rules, 2015
63. Protection of environment.
chhattisgarh-minor-mineral-rules-2015-sec-63.json
•
Section 63
{
"act_title": "Chhattisgarh Minor Mineral Rules, 2015",
"act_slug": "chhattisgarh-minor-mineral-rules-2015",
"section_label": "Section",
"section": {
"number": "63",
"title": "63. Protection of environment.",
"chapter": null,
"content": "(a) Wherever top soil exists and is to be excavated for quarrying operation, it shall be removed separately;\n(b) The top soil so removed shall be stored for future use;\n(c) The dumps shall be properly secured to prevent escape of material therefrom and cause land degradation or damage to agricultural fields, pollution of surface water bodies or cause floods;\n(d) The site of dumps shall be selected, as far as possible, on impervious and barren ground within the leased area; and\n(e) The top soil dumps shall be suitably terraced and established through vegetation or otherwise.\n(a) Every holder of an Quarry Lease/Quarry Permit shall take steps so that the over burden, waste rock, rejects and fines generated during quarrying or during sizing shall be stored in separate dumps;\n(b) The dumps shall be properly secured and shall be suitably terraced and stabilised through vegetation or otherwise;\n(c) Wherever possible, the waste rock, over burden etc. shall be back-filled into the mined out area excavations with a view to restoring the land to its original use as far as possible.",
"footnote": "",
"is_definition": false,
"sort_order": 62
},
"prev_section": "62",
"next_section": "64"
}