(a) that he has made a careful inspection of the aerial ropeway and appurtenances;
(b) that the moving and fixed dimensions and other conditions prescribed under sub-section (4) of section 9 and sub-section (1) of section 10 have been complied with;
(c) that the aerial ropeway is sufficiently equipped for the traffic for which it is intended;
(d) that the aerial ropeway is, in his opinion, fit for public traffic and can be used without danger either to the persons, animals or goods carried thereon, or to the persons employed thereon, or to the general public.
[14A. Periodical inspection after opening of aerial ropeway.
Construction and Maintenance of Aerial Ropeways for Public Traffic
Construction and Maintenance of Aerial Ropeways for Public Traffic
Section 14 • Bombay Aerial Ropeways Act, 1955
14. Inspection of aerial ropeway before opening.
bombay-aerial-ropeways-act-1955-sec-14.json
•
Section 14
{
"act_title": "Bombay Aerial Ropeways Act, 1955",
"act_slug": "bombay-aerial-ropeways-act-1955",
"section_label": "Section",
"section": {
"number": "14",
"title": "14. Inspection of aerial ropeway before opening.",
"chapter": null,
"content": "(a) that he has made a careful inspection of the aerial ropeway and appurtenances;\n(b) that the moving and fixed dimensions and other conditions prescribed under sub-section (4) of section 9 and sub-section (1) of section 10 have been complied with;\n(c) that the aerial ropeway is sufficiently equipped for the traffic for which it is intended;\n(d) that the aerial ropeway is, in his opinion, fit for public traffic and can be used without danger either to the persons, animals or goods carried thereon, or to the persons employed thereon, or to the general public.\n[14A. Periodical inspection after opening of aerial ropeway.\nConstruction and Maintenance of Aerial Ropeways for Public Traffic\nConstruction and Maintenance of Aerial Ropeways for Public Traffic",
"footnote": "",
"is_definition": false,
"sort_order": 13
},
"prev_section": "13",
"next_section": "15"
}