131R. Transparency, competition, fairness and elimination of arbitrariness in the procurement process.

(i) the text of the bidding document should be self-contained and comprehensive without any ambiguities. All essential information, which a bidder needs for sending responsive bid, should be clearly spelt out in the bidding document in simple language. The bidding document should contain, inter alia ;
(a) the criteria for eligibility and qualifications to be met by the bidders such as minimum level of experience, past performance, technical capability, manufacturing facilities and financial position etc.;
(b) eligibility criteria for goods indicating any legal restrictions or conditions about the origin of goods etc which may require to be met by the successful bidder;
(c) the procedure as well as date, time and place for sending the bids;
(d) date, time and place of opening of the bid;
(e) terms of delivery;
(f) special terms affecting performance, if any.
(ii) Suitable provision should be kept in the bidding document to enable a bidder to question the bidding conditions, bidding process and/or rejection of its bid.
(iii) Suitable provision for settlement of disputes, if any, emanating from the resultant contract, should be kept in the bidding document.
(iv) The bidding document should indicate clearly that the resultant contract will be interpreted under Indian Laws.
(v) The bidders should be given reasonable time to send their bids.
(vi) The bids should be opened in public and authorised representatives of the bidders should be permitted to attend the bid opening.
(vii) The specifications of the required goods should be clearly stated without any ambiguity so that the prospective bidders can send meaningful bids. In order to attract sufficient number of bidders, the specification should be general and broad based to the extent feasible. Efforts should also be made to use standard specifications which are widely known to the industry.
(viii) Pre-bid conference : In case of turn-key contract(s) or contract(s) of special nature for procurement of sophisticated and costly equipment, a suitable provision is to be kept in the bidding documents for a pre-bid conference for clarifying issues and clearing doubts, if any, about the specifications and other allied technical details of the plant, equipment and machinery projected in the bidding document.The date, time and place of pre-bid conference should be indicated in the bidding document.This date should be sufficiently ahead of bid opening date.
Pre-bid conference :
(ix) Criteria for determining responsiveness of bids, criteria as well as factors to be taken into account for evaluating the bids on a common platfrom and the criteria for awarding the contract to the responsive lowest bidder should be clearly indicated in the bidding documents.
(x) Bids received should be evaluated in terms of the conditions already incorporated in the bidding documents; no new condition which was not incorporated in the bidding documents should be brought in for evaluation of the bids. Determination of a bid's responsiveness should be based on the contents of the bid itself without recourse to extrinsic evidence.
(xi) Bidders should not be permitted to alter or modify their bids after expiry of the deadline for receipt of bids.
(xii) Negotiation with bidders after bid opening must be severely discouraged. However, in exceptional circumstances where price negotiation against an ad-hoc procurement is necessary due to some unavoidable circumstances, the same may be resorted to only with the lowest evaluated responsive bidder.
(xiii) In the rate contract system, where a number of firms are brought on rate contract for the same item, negotiation as well as counter offering of rates are permitted with the bidders in view and for this purpose special permission should be given to the State Purchase Organisation.
(xiv) Contract should ordinarily be awarded to the lowest evaluated bidder whose bid has been found to be responsive and who is eligible and qualified to perform the contract satisfactorily as per the terms and conditions incorporated in the corresponding bidding document. However, where the lowest acceptable bidder against ad-hoc requirement is not in a position to supply the full quantity required, the remaining quantity, as far as possible, be ordered from the next higher responsive bidder at the rates offered by the lowest responsive bidder.
(xv) The name of the successful bidder awarded the contract should be mentioned in the Departments Notice Board or Bulletin or website 66.