Bihar Electricity Regulatory Commission (Standards of Performance of Distribution Licensee) Regulations, 2006
Bihar Electricity Regulatory Commission (Standards of Performance of Distribution Licensee) Regulations, 2006
Sections
1. Short Title, Extent, Applicability, and Commencement.
Section 12. Definitions.
Section 23. Interpretation.
Section 34. Other Statutes.
Section 45. Legal Provision.
Section 56. Information to the consumers.
Section 67. Co-operation from Consumers.
Section 78. Maintenance of Records.
Section 89. Stand Alone Systems, Non-conventional Energy Systems and Local Distribution Systems in Rural Areas.
Section 911. Handling of Consumer's Complaints.
Section 1112. Power Quality Standards.
Section 1213. System Reliability.
Section 1314. Interruptions and Restoration of Supply to Essential Services.
Section 1415. New Service Connection.
Section 1516. Temporary Supply/Connection.
Section 1617. Enhancement of Load of Existing Consumer.
Section 1718. Shifting of Service Wire, Line and Equipment.
Section 1819. Reduction of Load of Existing Consumer.
Section 1920. Change of Tariff.
Section 2021. Change of name of Service Connection.
Section 2122. Defective Meters.
Section 2223. Erroneous Bills.
Section 2326. Guaranteed Standards of Performance.
Section 2627. Compensation for Under Performance.
Section 2728. Exemption.
Section 2829. Manner of Payment of Compensation.
Section 2930. Reporting to the Commission.
Section 3031. Repeal.
Section 3132. Savings.
Section 3233. Power to Remove Difficulties.
Section 3334. Power to Amend.
Section 341. No. of instances of planned interruptions in power supply in
Section 12. Total duration in hours of planned interruptions in power supply in
Section 2
bihar-electricity-regulatory-commission-standards-of-performance-of-distribution-licensee-regulations-2006.json
•
33 Sections
•
Bihar
{
"id": 15284,
"slug": "bihar-electricity-regulatory-commission-standards-of-performance-of-distribution-licensee-regulations-2006",
"title": "Bihar Electricity Regulatory Commission (Standards of Performance of Distribution Licensee) Regulations, 2006",
"short_title": "Bihar Electricity Regulatory Commission (Standards of Performance of Distribution Licensee) Regulations, 2006",
"act_number": "Published vide Notification No. BERC/Regl-9/2006, ",
"act_year": 2006,
"act_type": "STATE",
"location": "Bihar",
"law_status": "unknown",
"enactment_date": null,
"description": "Bihar Electricity Regulatory Commission (Standards of Performance of Distribution Licensee) Regulations, 2006",
"preamble": "",
"section_label": "Section",
"sections": [
{
"number": "1",
"title": "1. Short Title, Extent, Applicability, and Commencement.",
"chapter": null,
"content": "three months",
"footnote": "",
"is_definition": false,
"sort_order": 0
},
{
"number": "2",
"title": "2. Definitions.",
"chapter": null,
"content": "(a) \"Act\" means the Electricity Act, 2003 (36 of 2003).\n(b) \"Area of Supply\" means the area within which a licensee is authorised by his licence to distribute and supply electricity.\n(c) \"Commission\" means the Bihar Electricity Regulatory Commission.\n(d) \"Consumer\" means any person who is supplied with electricity for his own use by a licensee or the Government or by any other person engaged in the business of supplying electricity to the public under the Act, or any other law for the time being in force and includes any person whose premises are for the time being connected for the purpose of receiving electricity.\n(e) \"Danger\" means danger to the health or life or any part of the body from shock burn or other injury to person or to property originating from the electricity distribution or utilization system and includes danger from electricity originated fire or explosion in distribution and utilization systems.\n(f) \"Emergency Periods\" means the periods declared such by the Government due to war, mutiny, strikes, natural calamities, severe drought, heavy floods and similar abnormal periods.\n(g) \"Extra High Tension/Extra High Voltage\" means the voltage exceeding 33000 volts under normal conditions.\n(h) \"High Tension or High Voltage\" means the voltage exceeding 440 volts but not exceeding 33,000 volts under normal conditions.\n(i) \"Licensee\" means the Distribution Licensee who has been granted licence by the Commission under Section 14 of the Act, including a deemed Licensee.\n(j) \"Low Tension or Low Voltage\" means the voltage that does not exceed 230/440 volts (phase to neutral and phase to phase respectively) under normal conditions.\n(k) \"Period of Load Shedding\" means a period during which the power has to be Switched off to certain feeders to match the demand and supply as per the instructions of the respective load despatch centres.\n(l) \"Period of Scheduled Outage\" means a period wherein certain equipment and lines are under pre-arranged shut-down for maintenance during which it may or may not be possible to make alternative arrangements for maintaining supply to consumers.\n(m) \"Period of Forced Outage\" means a period wherein certain equipment or a line breaks down during which alternative arrangements by using standby equipment for maintaining supply to consumers may or may not be possible.\n(n) \"Rural Areas\" means areas covered by Gram Panchayats .\n(o) \"Urban Areas\" means cities, towns, cantonments, industrial estates, and areas covered by municipalities, municipal corporations, urban development authorities, and cantonment authorities.",
"footnote": "",
"is_definition": true,
"sort_order": 1
},
{
"number": "3",
"title": "3. Interpretation.",
"chapter": null,
"content": "(i) words in the singular or plural term, as the case may be, shall also be deemed to include the plural or the singular terms.\n(ii) references herein to these Regulations shall be construed as references to these Regulations as amended or modified by the Commission from time to time in accordance with the applicable Act, and Rules made thereunder.\n(iii) the headings inserted in these Regulations are for convenience only.\n(iv) reference to the statutes, Regulations or guidelines shall be construed as including all provisions consolidated, amended or replaced by such other statutes, Regulations or guidelines as the case may be from time to time.",
"footnote": "",
"is_definition": true,
"sort_order": 2
},
{
"number": "4",
"title": "4. Other Statutes.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 3
},
{
"number": "5",
"title": "5. Legal Provision.",
"chapter": null,
"content": "(ii) The sub-section (1) of Section 57 of the Act, stipulates that the Commission after consultation with Licensees and persons likely to be affected shall specify standards of performance of a Licensee or a class of Licensees.\n(iii) The sub-section (2) of Section 57 of the Act, provides that if a Licensee fails to meet the standards specified under sub-section (1), without prejudice to any penalty, which may be imposed, or prosecution be initiated, he shall be liable to pay such compensation to a person affected as may be determined by the Appropriate Commission;\n(iv) Under the provisions of Section 86 (1) (i) of the Act, the Commission is required to specify and enforce standards with respect to quality continuity and reliability of service by the Licensees.\n(v) In terms of stipulations made in Section 59 of the Act, provision has been made in Regulation 30(1) for furnishing information with respect to level of performance and quarterly report on performance standards and publication of Annual Report.\n(vi) The penal provision for imposition of penalty on the licensee for any shortfall or deviation from overall standards prescribed under Chapter 7 & 8 of the Regulation and non payment of compensation to aggrieved consumer has been made in terms of provisions of Section 142 of the Act.",
"footnote": "",
"is_definition": false,
"sort_order": 4
},
{
"number": "6",
"title": "6. Information to the consumers.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 5
},
{
"number": "7",
"title": "7. Co-operation from Consumers.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 6
},
{
"number": "8",
"title": "8. Maintenance of Records.",
"chapter": null,
"content": "(a) Separate register of application for new service connection, enhancement of load, temporary supply, reduction of load, change of name, etc.\n(b) Service connection register\n(c) Security Deposit register\n(d) Connection charges collection register\n(e) Fuse call register\n(f) Interruption in power supply register\n(g) Disconnection and Reconnection of service connection register\n(h) Meter replacement register\n(i) Distribution transformer register with load details\n(j) Estimates register\n(k) Work order register",
"footnote": "",
"is_definition": false,
"sort_order": 7
},
{
"number": "9",
"title": "9. Stand Alone Systems, Non-conventional Energy Systems and Local Distribution Systems in Rural Areas.",
"chapter": null,
"content": "(b) The organization owning or managing such rural distribution systems shall prepare their own standards and obtain approval of the Commission.\n(c) Such organizations shall gradually improve their operating standards and move towards the standards of performance prescribed in these Regulations. After a period of five years from the date of coming into being, these standards shall also be applicable to such rural distribution systems.\nChapter 2\nSafety\n10. (1) Safety Standards to be complied with, by the Licensee.\n(ii) The grounding provided for the equipment and lines and earthing grid for sub-stations shall be in accordance with latest version of IS : 3043-Code of Practice for Earthing.\n(iii) The Licensee shall erect and maintain earthing systems by following best standards and connect all those points of the system which are required to be connected to earth.\n(iv) The earthing connections shall be maintained in a sound and healthy state at all times. The licensee shall take all necessary steps for testing the same and maintain the record of each test in accordance with the provisions under relevant Rules of IER 1956.\n(v) The Licensee shall follow provisions of IER 1956 and would ensure that no live parts of any overhead line or distribution transformer are so exposed as to cause danger. The Licensee shall also adhere with the provisions under relevant Rules of IER 1956 regarding clearances in the construction of overhead lines, erection of transformers, sub-stations and other equipment and guarding must be provided for the lines where necessary.\n(vi) The licensee shall adopt prescribed mechanical factor for safety of components of overhead lines and must provide guys and stays where necessary. The structures and overhead lines must be capable to withstand the storms, wind and rain that occur every year in his area.\n(vii) At places of high density population and wherever heavy traffic exists the Licensee shall maintain higher degree of safety by insulating live parts and by providing adequate guarding although the clearances may be adequate.\n(viii) Leakage current means the difference between phase current and return path. The Licensee shall take necessary steps to measure leakage current at various points in the system.\n(ix) The earth wires and earth electrodes provided in the Distribution System shall be maintained in good condition to ensure instantaneous operation of the protective equipment, either a fuse or a circuit breaker as the case may be, in case of accidental snapping of a conductor. In case of failure in the operation of the protective system during any accidental snapping of conductors, the circuit shall be de-energised manually, immediately after it comes to the notice of the concerned employee of the Distribution Licensee. A detailed investigation shall be done to determine cause for non-operation of the protective systems and remedial measures should be taken promptly by the Licensee.\n(x) The Licensee must install lightning arresters at appropriate points of the system to protect the system from lightning.\n(xi) The Licensee shall fix danger warning boards and display voltage level at appropriate points of the system.\n(xii) The safety precautions to be followed in respect of the Licensee's installations in the consumer's premises at the point of supply and for the system part downstream and adjacent to the point of supply i.e. in the consumer's system shall be conveyed by the Licensee to the consumer both in writing and verbally at the time of release of supply to a new service connection.\n(xiii) The Licensee shall take alt necessary action to spread awareness among the consumers for safe usage of the electricity.\n(xiv) The Licensee shall educate the public through press notifications regarding precautions to be taken and methods to protect themselves when an overhead line conductor snaps or when a pole falls or when a structure collapses and other similar events occur.\n(xv) The Licensee may disconnect supply to such consumer, in the event of consumer's non compliance even after due notice, or any specific condition or direction if such non compliance can reasonably be expected to affect system operations and safety. In cases of emergency, disconnection may be effected immediately in the interest of system operation and safety. The connection should be immediately restored as soon as the cause(s) leading to the disconnection are removed or rectified.\n(2) Electrocution Accidents.\n(ii) The records of all the fatal electrocution accidents shall be maintained along with the investigation report of the CEI. A copy of the action taken on report of CEI alongwith safety measures taken for avoiding recurrence of such accidents shall be submitted to the Commission every six months i.e. by 31st October and 30th April of each financial year.\nChapter 3\nHandling of Complaints",
"footnote": "",
"is_definition": false,
"sort_order": 8
},
{
"number": "11",
"title": "11. Handling of Consumer's Complaints.",
"chapter": null,
"content": "Chapter 4\nQuality of Power and System Reliability",
"footnote": "",
"is_definition": false,
"sort_order": 9
},
{
"number": "12",
"title": "12. Power Quality Standards.",
"chapter": null,
"content": "(i)\nLow tension/Low Voltage\n+ 6% and -6%\n(ii)\nHigh tension/High Voltage\n+ 6% and -9%, and\n(iii)\nExtra High tension/Extra High Voltage\n+ 10% and -12.5%\n(b) Frequency variation. - The frequency variation shall be governed by the Indian Electricity Grid Code (IEGC)/State Grid Code. IEGC stipulates operating frequency range between 49.0 Hz and 50.5 Hz.The transmission utility, transmission Licensee and the State load despatch centre shall jointly maintain the operating frequency between 49.0 and 50.5 Hz. The distribution Licensee shall co-operate with the State load despatch centre and the transmission utility/transmission Licensee by reducing load whenever requisitioned.\n[(c) Harmonics: - (i) Harmonics generated by one consumer may affect the normal operation of another consumer. Therefore on receipt of a complaint from a consumer who cannot carry out normal operations due to large harmonics, the licensee shall investigate the cause and eliminate or reduce the harmonics. This may involve identification of harmonic generating consumers and serving notices on them to instalfilters. Harmonics may cause temporary over voltages and ferro-resonance. These harmonics may cause large neutral current.\n(ii) The Licensee shall monitor the voltage harmonics and current harmonics in terms of \"Total Harmonic Distortion\" (THD), a measure of distortion of the voltage or current wave form (which shall ideally be sinusoidal) and is the square root of the sum of squares of all voltage or current harmonics expressed as a percentage of the magnitude of the fundamental.\n(iii) In any installations the voltage and current Harmonic Distortion (THD) shall not exceed the limit as specified in the Central Electricity Authority (Technical Standards for connectivity to the Grid) Regulations, 2007, as amended from time to time, applicable to the Distribution Systems. The Consumer will take appropriate measures to restrict the THD to the stipulated limit.\n(iv) The total harmonic distortion for voltage at the connection point shall not exceed 5% with no individual harmonic higher than 3% and the total harmonic distortion for current drawn from the transmission/sub-transmission system at the connection point shall not exceed 8%.\n(v) The Licensee shall submit a quarterly report on THD of voltage and current harmonic to the Commission of following type of loads:\n(a) Salient Pole synchronous generators\n(b) Power Transformers of more than 15 years old\n(c) Rolling Mills\n(d) Induction Furnaces\n(e) Welding Equipment\n(f) Static Power Loads\n(g) Inverters / power rectifiers\n(h) Railway Traction Load\n(vi) All the users operating the power generating plant in parallel with the grid shall comply with the terms and conditions of the agreement for such connectivity laid down by the Distribution Licensee. Such units shall also promptly comply with any direction that may be issued by the SLDC or the Distribution Licensee in the interest of orderly operation of the grid.\n(vii) The Consumer shall not keep connected to the Distribution Licensees supply system any apparatus including phase splitters which in the Distribution Licensees opinion may interfere with or effect injuriously the Distribution Licensees supply to other Consumers and may disturb the supply system in short or long term.]",
"footnote": "",
"is_definition": false,
"sort_order": 10
},
{
"number": "13",
"title": "13. System Reliability.",
"chapter": null,
"content": "(a) System Average Interruption Frequency Index (SAIFI). It is the average number of interruptions (longer than 5 minutes) that a customer would experience and is calculated as:\n(a) System Average Interruption Frequency Index (SAIFI).\n(b) System Average Interruption Duration Index (SAIDI). - It is the average outage duration for each customer served and is calculated as:\n(b) System Average Interruption Duration Index (SAIDI).\n(c) Momentary Average Interruption Frequency Index (MAIFI). - It is the average number of interruptions (less than 5 minutes) that a customer would experience and is calculated as:\n(c) Momentary Average Interruption Frequency Index (MAIFI).",
"footnote": "",
"is_definition": false,
"sort_order": 11
},
{
"number": "14",
"title": "14. Interruptions and Restoration of Supply to Essential Services.",
"chapter": null,
"content": "Chapter 5\nNew Service Connection/Additional Load and Other Service Connection Related Matters",
"footnote": "",
"is_definition": false,
"sort_order": 12
},
{
"number": "15",
"title": "15. New Service Connection.",
"chapter": null,
"content": "(A) L.T. Connection :\n(A) L.T. Connection :\n(a)\nIntimation regarding acceptance of application from the date\n\t\t\t\tof receipt of application\n- 5 days\n(b)\nIntimation of estimated charges and amount of security\n\t\t\t\tdeposit from date of acceptance of application involving\n\t\t\t\textension of dist., network and addition/enhancement of\n\t\t\t\tdistribution transformers\n- 30 days\n(c)\nFor providing service connection after payment of charges\n\t\t\t\tinvolving extension of dist, network and addition/enhancement of\n\t\t\t\tdistribution transformers\n- 30 days\n(B) H.T. Connection:\n(B) H.T. Connection:\n(a)\nIssue of feasibility certificate from the date or receipt of\n\t\t\t\tapplication\n- 10 days\n(b)\nIntimation of estimated charges and amount of security\n\t\t\t\tdeposits payable by the applicant for providing new connection\n- Involving erection of new 33 KV sub-station (S/S), lines\n\t\t\t\tetc. up to Contract Demand of 7500 KVA\n- 45 days\n- Involving erection of EHT S/S, lines etc. for Contract\n\t\t\t\tDemand above 7500 KVA\n- 60 days\n(c)\nCompletion of works from payment of Service Line/Development\n\t\t\t\tCharges, security deposit and execution of agreement\n- Involving erection of new 11 KV line\n- 45 days\n- Involving erection of new 33 KV line\n- 75 days\n- Involving erection of new EHT line\n- 150 days\n- Involving augmentation or addition of transformers (33/11 or\n\t\t\t\t132/33 KV)\n- 30 days additional\n(d)\nRelease of supply from the date of furnishing of Chief\n\t\t\t\tElectrical Inspector's approval\n- 11 KV & 33 KV loads\n- 15 days\n- 132 KV loads\n- 30 days\n(e) The Licensee may approach Commission for extension of time specified above in cases where the magnitude of work requires more time with furnishing details and justification in support of such request for extension. Such request shall be made within 5 days from the preparation of the estimate.\n(f) The Licensee shall however, not be held responsible for delay in providing connection, if the same is on account of special circumstance such as right of way, acquisition of land, delay in permission for road cutting, over which Licensee has no reasonable control provided that the reason for expected delay are communicated to the applicant within the period specified for. Additional period required on account of special circumstances mentioned above shall be added to the normal period as specified under Regulation 15(4) i.e. the period within which the Licensee has to release new service connection.\n(g) The time limit shall be extended by the period which the consumer delays in fulfilling the following tasks beyond the due date intimated by the Licensee:-\n(i) Payment of service connection charges and security deposit.\n(ii) Certificate that the internal wiring/consumer's electrical system including machinery, equipment and appliances are in goods condition, comply with the standards including safety standards and the insulation resistance of the system.\n(iii) Signing of Agreement between the Licensee and the consumer.\n(iv) Filling ownership certificate of the premises.\n(v) Settlement of dues if the applicant had availed supply of electricity earlier.\n(vi) Providing of space for installation of transformer or metering equipment, if required.",
"footnote": "",
"is_definition": false,
"sort_order": 13
},
{
"number": "16",
"title": "16. Temporary Supply/Connection.",
"chapter": null,
"content": "(b) The Licensee shall collect the cost for effecting temporary service connection and the cost towards expected energy consumption as per tariff order in force.\n(c) The Licensee shall release supply on the date required by the consumer in case where distribution lines are laid down.\n(d) Where extension of distribution main is required, the time schedule as mentioned in Regulation 15(4) shall apply.\n(e) The Licensee shall refund the balance deposit, if any within one month from the date of dismantling the temporary service connection, after adjustment of the dues payable by the consumer",
"footnote": "",
"is_definition": false,
"sort_order": 14
},
{
"number": "17",
"title": "17. Enhancement of Load of Existing Consumer.",
"chapter": null,
"content": "(b) If extension and alteration of distribution network is required, the time schedule under Regulation 15(4) shall apply for allowing load enhancement.\nOther Service Connection Related Matters\nOther Service Connection Related Matters",
"footnote": "",
"is_definition": false,
"sort_order": 15
},
{
"number": "18",
"title": "18. Shifting of Service Wire, Line and Equipment.",
"chapter": null,
"content": "(i) Shifting of Meter or service line\n7 days\n(ii) Shifting of LT line\n15 days\n(iii) Shifting of 11 KV line\n30 days\n(iv) Shifting of 33 KV line\n45 days\n(v) Shifting of U.G. cable\n45 days\n(vi) Shifting of Distribution Transformer\n30 days\n(a) Shifting of meter/service wire\n15 days\n(b) Shifting of pole, LT or HT Line\n60 days\n(c) Shifting of underground Cable\n45 days\n(d) Shifting of Distribution Transformer alongwith the\n\t\t\t\tstructure\n90 days",
"footnote": "",
"is_definition": false,
"sort_order": 16
},
{
"number": "19",
"title": "19. Reduction of Load of Existing Consumer.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 17
},
{
"number": "20",
"title": "20. Change of Tariff.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 18
},
{
"number": "21",
"title": "21. Change of name of Service Connection.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 19
},
{
"number": "22",
"title": "22. Defective Meters.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 20
},
{
"number": "23",
"title": "23. Erroneous Bills.",
"chapter": null,
"content": "24. (a) Reconnection of Service.\n(2) If service connection is disconnected for malpractice like pilferage, the service connection shall be restored after the case is settled and consumer pays the entire assessment amount. In such cases the Licensee shall not pay any compensation for delay in reconnection.\n(b) Permanent disconnection on request of consumer - If a consumer desires to get his service connection disconnected permanently, he shall given prior notice as specified in the Electricity Supply Code (ESC) or as otherwise provided in the Tariff Order which is in force. The Licensee shall serve final bill along with disconnection charges and after payment of the final bill the service connection shall be disconnected and the agreement shall be terminated.\n(b) Permanent disconnection on request of consumer\nChapter 6\nOverall Standard of Performance and Level of Performance\n25.\n(a) Normal Fuse of Calls - The Licensee shall ensure rectification of fuse-off calls within the time limits as specified in Schedule in Chapter 7. The Licensee shall achieve this standard of performance in atleast 95% of the cases.\n(a) Normal Fuse of Calls\n(b) Line Breakdowns - In case of line breakdowns, the Licensee shall ensure restoration of power supply within the time period as specified in Schedule in Chapter 7. The Licensee shall achieve such standard of performance in atleast 95% of the cases.\n(b) Line Breakdowns\n(c) Distribution Transformer Failure - The Licensee shall maintain the percentage of distribution transformers replacement within the time period as specified in Schedule in Chapter 7 in atleast 95% of the cases.\n(c) Distribution Transformer Failure\n(d) Period of Scheduled Outages - Interruptions in power supply due to scheduled outages have to be notified in advance and shall not exceed such number of hours in a day as specified in Schedule in Chapter 7 and the licensee shall ensure that the supply is restored by such time as specified in the Schedule. The Licensee shall achieve both of these standards of performance in atleast 95% of the cases.\n(d) Period of Scheduled Outages\n(e) Street Lights - The Licensee shall as soon as possible attend to complaints relating to non working of street lights or not operating property, to the extent the matter lies within the purview of the Licensee, atleast 90% of the cases be attended and resolved within the time limit as specified in Schedule in chapter 7.\n(e) Street Lights\n(f) Billing Mistakes - Billing mistakes shall not exceed 1% of the total bills prepared, 99% of the cases related to billing mistakes should be resolved within the time period as specified in Schedule in Chapter 7.\n(f) Billing Mistakes\n(g) Faulty Meters - The licensee shall maintain the percentage of faulty Meters not greater than 3% of the total number of meters in service 99% of the cases in urban areas and 33% of the cases in rural areas shall be resolved within the time period as specified in Schedule in Chapter 7.\n(g) Faulty Meters\n(h) Voltage Unbalance - The licensee shall ensure that the voltage unbalance does not exceed 3% at the point of commencement of supply.\n(h) Voltage Unbalance\nAtleast 98% of the cases related to voltage unbalance shall be resolved within the time period as specified in Schedule in Chapter 7.\n(i) Release of new connections/ Additional Load/Temporary Connection - All cases (100%) of release of new connection, additional load and temporary connection on application by the applicant/consumer should be resolved within specified time limits.\n(i) Release of new connections/ Additional Load/Temporary Connection\n(k) Transfer of Ownership and Conversion of Service - At least 98% of the cases related to transfer of ownership and conversion of service should be resolved within specified time limits.\n(k) Transfer of Ownership and Conversion of Service\nService area\nOverall standard of performance\na\nNormal fuse-off calls\nAt least 95% calls received should be rectified within\n\t\t\t\tprescribed time limits\nb\nLine Breakdowns\nAt least 95% of cases should be resolved within prescribed\n\t\t\t\ttime limits.\nc\nDistribution Transformer (DTR) failure\nAt least 95% of DTRs to be replaced within prescribed time\n\t\t\t\tlimits.\nd\nPeriod of scheduled outage\nMaximum duration in a single stretch\nAt least 95% of cases resolved within time limit\nRestoration of supply by 6.00 PM\ne\nStreet Light Faults\nRectification of line faults\nAt least 90% of cases resolved within time limits\nReplacement of fused/defective unit\nf\nBilling mistakes\nNot exceeding 1%\ng\nFaulty meters\nNot exceeding 3%\nh\nVoltage unbalance\nMaximum of 3% at the point of commencement of supply.\ni\nRelease of new connection/additional load/Temporary connection\n100% cases within specified time limits\nk\nTransfer of Ownership and Conversion of Service\nAt least 98% of cases within specified time limits.\nChapter 7\nGuaranteed Standards of Performance and Compensation for under performance",
"footnote": "",
"is_definition": false,
"sort_order": 21
},
{
"number": "26",
"title": "26. Guaranteed Standards of Performance.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 22
},
{
"number": "27",
"title": "27. Compensation for Under Performance.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 23
},
{
"number": "28",
"title": "28. Exemption.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 24
},
{
"number": "29",
"title": "29. Manner of Payment of Compensation.",
"chapter": null,
"content": "Schedule (½)\nGuaranteed Standards of Performance and Compensation to Affected Consumers in case of Default\nGuaranteed Standards of Performance and Compensation to Affected Consumers in case of Default\nSl. No.\nService Area\nStandard\nCompensation payable in case of violation of\n\t\t\t\tStandard\nCompensation payable to Individual Consumer if the\n\t\t\t\tevent affects a single Consumer\nCompensation payable in individual Consumer if the\n\t\t\t\tevent affects more that one Consumer\nNormal Fuse-off\nNormal Fuse-off\n1\nCities and Towns\nWithin 4 hours\nRs. 25 for each day of default\nRs. 25 to each Consumer affected for each day of default\nRural Areas\nWithin 24 hours\nOverhead Line/Cable breakdowns\nOverhead Line/Cable breakdowns\n2\nCities and Towns\nWithin 6 Hours\nRs. 25 for each day of default\nRs. 25 to each Consumer affected for each day of default\nRural Areas\nWithin 36 Hours\nUnderground Cable breakdowns\nUnderground Cable breakdowns\n3\nCities and Towns\nWithin 24 Hours\nRs. 25 for each day of default\nRs. 25 to each Consumer affected for each day of default\nRural Areas\nWithin 48 Hours\nDistribution Transformer failure\nDistribution Transformer failure\n4\nCities and Towns\nWithin 24 Hours\nRs. 50 for each day of default\nRs. 25 to each Consumer affected for each day of default\nRural Areas\nWithin 72 Hours\nPeriod of Scheduled outage\nPeriod of Scheduled outage\n5\nmaximum-duration a single stretch\nNot to exceed 12 hours\nRs. 50 for each day of default\nRs. 25 to each Consumer affected for each day of default\nRestoration of Supply\nBy not later than 6.00 P.M.\nVoltage Fluctuations\nVoltage Fluctuations\n6\nNo expansion/enhancement of network involved\nWithin 10 days\nRs. 50 for each day of default\nRs. 25 to each Consumer affected for each day of default\nUp-gradation of distribution system required\nWithin 120 days\nRs. 50 for each day of default\nRs. 25 to each Consumer affected for each day of default\nErection of Sub-Station\nWithin the time period as approved by the Commission\nRs. 250 for each day of default\nRs. 25 to each Consumer affected for each day of default\nMeter Complaints\nMeter Complaints\n7\nInspection and replacement of slow, fast/creeping, stuck-up\n\t\t\t\tMeters\nInspection within 7 days in towns and cities and within 15\n\t\t\t\tdays in rural areas and replacement within 15 days thereafter\nRs. 50 for each day of default\nNot Applicable\nReplacement of burnt meters if cause attributable to Licensee\nWithin 7 days\nRs. 50 for each days of default\nNot Applicable\nReplacement of burnt meter if cause attributable to Consumer\nWithin 14 days of receiving payment/ meter from Consumer\nNot Applicable\nReconnection of supply following disconnection due to\n\t\t\t\tnon-payment of bills\nReconnection of supply following disconnection due to\n\t\t\t\tnon-payment of bills\n8\nCities and Towns\nSame day on which payment was accepted\nRs. 25 for each day of default\nNot Applicable\nRural areas\nUpto next day of payment\nSchedule (2/2)\nSl. No.\nService Area\nStandard\nCompensation payable in case of violation of\n\t\t\t\tStandard\nCompensation payable to Individual Consumer if the\n\t\t\t\tevent affects a single Consumer\nCompensation payable in individual Consumer if the\n\t\t\t\tevent affects more that one Consumer\n9\nNew Service connection/enhancement of\n\t\t\t\tload/Temporary Connection\nNew Service connection/enhancement of\n\t\t\t\tload/Temporary Connection\nConnection feasible from existing network\nRelease of Supply\nWithin 30 days of receipt of application (along\n\t\t\t\twith prescribed charges) and for temporary connections as per\n\t\t\t\tRegulation 16(c)\nRs. 50 for each day of default\nNot Applicable\n10\nNetwork expansion/enhancement required to\n\t\t\t\trelease supply\nNetwork expansion/enhancement required to\n\t\t\t\trelease supply\nRelease of supply-Low Tension\nWithin 30 days of receipt of prescribed charges\nRs. 50 for each day of default\nRelease of supply-High Tension 11 KV\nWithin 60 days of receipt of prescribed charges\nRs. 250 for each day of default\nNot Applicable\nRelease of supply High Tension 33 KV\nWithin 90 days of receipt of prescribed charges\nRelease of supply-Extra High Tension\nWithin 180 days of receipt of prescribed charges\nErection of sub-station required for release of\n\t\t\t\tsupply\nWithin the time period approved by the Commission\nRs. 500 for each day of default\n11\nTransfer of Ownership and Conversion of Service\nTransfer of Ownership and Conversion of Service\nTitle transfer of ownership\nWithin 7 days along with necessary documents and\n\t\t\t\tprescribed fee, if any\nRs. 50 for each day of default\nNot Applicable\nChange of Category\nWithin 7 days along with necessary documents and\n\t\t\t\tprescribed fee, if any\nReduction of load\nWithin the notice period after awaiting compulsory\n\t\t\t\tperiod of supply.\nRs. 25 for each day of default\nNot Applicable\n12\nShifting of meter, lines and transformer\nShifting of meter, lines and transformer\n(a) Meter/service wire\nWithin 15 days of payment of charges\nRs. 50 for each day of default\nNot Applicable\n(b) Pole, line\nWithin 60 days of payment of charges\n(c) UG cable\nWithin 45 days of payment of charges\n(d) Transformer\nWithin 90 days of payment of charges\n13\nResolution of Complaints on Consumers, bill\nResolution of Complaints on Consumers, bill\nIf no additional information is required\nWithin 24 working hours of receipt of complaint\nRs. 25 for each day of default\nNot Applicable\nIf additional information is required\nWithin 7 working days of receipt of Complaint\nChapter 8\nMiscellaneous",
"footnote": "",
"is_definition": false,
"sort_order": 25
},
{
"number": "30",
"title": "30. Reporting to the Commission.",
"chapter": null,
"content": "(a) The levels of overall performance standards achieved by the Licensee with reference to the standards specified in Regulation (25) of these Regulations in the format given at Appendix C to these Regulations.\n(b) The number of consumer complaints, redressed and cases in which compensation was paid and the aggregate amount of the compensation payable and amount paid by the Licensee in the format given at Appendix D to these Regulations.\n(c) The number of claims made by the consumers against the Licensee for failure to meet the guaranteed standards of performance and the action taken by the Licensee including the reasons for delay in payment, and non-payment of compensation for such claims, and\n(d) The measures taken by the Licensee to improve performance in the areas covered by guaranteed standards and Licensee's to improve performance in the areas covered by guaranteed standards and Licensee's assessment of the targets to be fixed for the ensuing year.",
"footnote": "",
"is_definition": false,
"sort_order": 26
},
{
"number": "31",
"title": "31. Repeal.",
"chapter": null,
"content": "(ii) Notwithstanding such repeal, the action taken under the earlier Regulations, orders and directions shall remain valid.",
"footnote": "",
"is_definition": false,
"sort_order": 27
},
{
"number": "32",
"title": "32. Savings.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 28
},
{
"number": "33",
"title": "33. Power to Remove Difficulties.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 29
},
{
"number": "34",
"title": "34. Power to Amend.",
"chapter": null,
"content": "Appendix-A\nAppendix-A\nRegister of Complaints at Complaint Centres and Offices of Junior Engineer/ Assistant Engineer\n[See Regulation 11(1)]\nName of Office.............................\nSl. No.\nTime & Date\nName, Address, & Consumer No. of the\n\t\t\t\tcomplainant\nUnique no. of complaint\nComplaints classification\nnature of complaint\nComplaint Classification & its no.\n1\n2\n3\n4\n5\n6\nTime & Date of redressal of grievance\nTotal time taken (in Hrs/mts)\nNo. of consumers affected\nTotal duration of interruption (8x9) = 10 (in\n\t\t\t\thrs/mts)\nWhether redressed within stipulated time as per\n\t\t\t\tstandards of performance (Yes/No.)\n7\n8\n9\n10\n11\nInstructions :\n(i) Separate register shall be maintained for complaints of Type-A & other than Type-A\n(ii) Compilation will be made every month. Unattended complaints may be brought forward after each interval, so that a true picture of the pendency is reflected.\nClassification of Complaints :\n(A) Interruption in power supply\n(A) Interruption in power supply\n(i) Loose connections from pole\n(ii) Interruption due to line breakdown\n(iii) Interruption due to failure of transformer\n(B) Quality of power supply\n(B) Quality of power supply\n(i) Ordinary case, which requires no augmentation\n(ii) Where augmentation is required\n(C) Meters\n(C) Meters\n(i) Stopped/Defective Meters\n(ii) Billing on average basis for more than two bills\n(D) Overhead lines\n(D) Overhead lines\n(i) Loose Wires\n(ii) Inadequate ground clearance\n(E) Bills\n(E) Bills\n(i) For current bills where no additional information is required\n(ii) Where additional information is relating to correctness of reading etc. is required\n(F) Service connections (Domestic & Non Domestic)\n(F) Service connections (Domestic & Non Domestic)\n(i) Where extension of mains is not required\n(ii) Where extension of mains is required\n(iii) Modification in connected load\n(iv) Name of change/reconnection\n(G) Refund of amount due in regard to temporary connection\n(G) Refund of amount due in regard to temporary connection\n(H) Others\n(H) Others\nAppendix-B\nAppendix-B\nRegister for Compiling the Complaints Classification-Wise\nRegister for Compiling the Complaints Classification-Wise\n[See Regulation 11(5)]\nClassification\nPending complaints of previous month\nComplaints received during the month\nTotal Complaints\nNo. of Complaints redressed during the month\nBalance Complaints to be redressed (4)-(9)\nin stipulated time\nBeyond stipulated time\nTotal (5) to (8)\nWithin 50% of stipulated time\nWithin stipulate of time\nUp to double the stipulated time\nMore than double the stipulated time\n1\n2\n3\n4\n5\n6\n7\n8\n9\n10\nA (i)\nA (ii)\nA (iii)\nB (i)\nB (ii)\nC (i)\nC (ii)\nD (i)\nD (ii)\nE (i)\nE (ii)\nF (i)\nF (ii)\nF (iii)\nF (iv)\nG\nH\nAppendix-C\nAppendix-C\nReport on Overall Level of Performance Standards\nReport on Overall Level of Performance Standards\n[See Regulation 30(1)(a)]\n(2) Financial Year.\nSl. No.\nService area\nNo. of complaints received\nNo. of complaints attended\nOverall standard of performance\nVariance (%)\nAchievement (%)\nTarget (%)\n1\nNormal Fuse-off calls\n2\nLine Breakdowns\n3\nDistribution Transformer failure\n4\nPeriod of Scheduled outage\nMaximum duration in a single stretch\nRestoration of supply by 6.00 Pm\n5\nStreet Light Faults\nRectification of line faults\nReplacement of fused/ defective unit\n6\nBilling Mistakes\n7\nFaulty Meters\n8\nVoltage unbalance\n9\nNew connection/additional load/temporary connection\n10\nTransfer of ownership and conversion of service\n11\nOthers\nAppendix-D (½)\nAppendix-D (½)\nReport on Consumer Complaint\n[See Regulation 30 1(b)]\n(2) Financial Year..................\nSl. No.\nType of complaints\nPending complaints of previous quarter\nComplaints received during the current quarter\nTotal complaints cumulative\nNo. of complaints redressed during the quarter\nBalance complaints to be redressed\nWithin stipulated time\nBeyond stipulated time\nTotal\n1\nNew connections where distribution mains already exist\n2\nNew connections where extension of distribution mains was\n\t\t\t\trequired\n3\nNew connections where commissioning of a new sub-station was\n\t\t\t\trequired\n4\nModification of load\n5\nTransfer of ownership and conversion of service\n6\nComplaints on consumer's bill\n7\n8\nunplanned interruptions Voltage related complaints\n9\nMeter related complaints\n10\nOthers\nTotal",
"footnote": "",
"is_definition": false,
"sort_order": 30
},
{
"number": "1",
"title": "1. No. of instances of planned interruptions in power supply in",
"chapter": null,
"content": "LT Network- HT Network-",
"footnote": "",
"is_definition": false,
"sort_order": 31
},
{
"number": "2",
"title": "2. Total duration in hours of planned interruptions in power supply in",
"chapter": null,
"content": "LT Network- HT Network-\nAppendix-D (2/2)\nAppendix-D (2/2)\nSl. No.\nType of complaints\nPending No. of complaints of previous quarter\nNo. of complaints received during the quarter\nNo. of complaints redressed during the quarter\nNo. of cases where compensation was payable\nNo. of cases where compensation was paid during\n\t\t\t\tthe quarter\nTotal amount (in Rs.) of compensation paid\n1\n2\n3\n4\n5\n6\n7\n8\n1\nNew connections where distribution mains already existed\n2\nNew connections where extension of distribution mains was\n\t\t\t\trequired\n3\nNew connections where commissioning of a new sub-station was\n\t\t\t\trequired\n4\nModification of load\n5\nTransfer of ownership and conversion of service\n6\nComplaints on consumer's bill\n7\nUnplanned interruptions\n8\nVoltage related complaints\n9\nMeter related complaints\n10\nOthers\nTotal",
"footnote": "",
"is_definition": false,
"sort_order": 32
}
],
"metadata": {
"Act ID": "bh210",
"Act Number": "Published vide Notification No. BERC/Regl-9/2006, dated 18th January, 2007",
"Enactment Date": "",
"Act Year": "2006",
"Short Title": "Bihar Electricity Regulatory Commission (Standards of Performance of Distribution Licensee) Regulations, 2006",
"Type": "STATE",
"Location": "Bihar"
},
"updated_at": "2026-09-29 21:55:19"
}