(i) Description of the programme;
(ii) Objective and rationale for the programme;
(iii) Consumer segments and estimated level of participation;
(iv) Estimate of baseline;
(v) Assessment of programme in line with Cost Effectiveness Guidelines issued by the Commission;
(vi) Mechanism for recovery of cost and performance incentives;
(vii) Marketing, delivery strategy and Implementation schedule;
(viii) Implementation mechanism e.g. Energy Service Companies, DSM Bidding, DSM Resource Acquisition, etc;
(ix) Monitoring and evaluation plan; and
(x) Plan for Training/ Seminars/ Workshops to increase consumer awareness.
Section 12 • Bihar Electricity Regulatory Commission (Demand Side Management) Regulations, 2014
12. Approval of DSM programme Document.
bihar-electricity-regulatory-commission-demand-side-management-regulations-2014-sec-12.json
•
Section 12
{
"act_title": "Bihar Electricity Regulatory Commission (Demand Side Management) Regulations, 2014",
"act_slug": "bihar-electricity-regulatory-commission-demand-side-management-regulations-2014",
"section_label": "Section",
"section": {
"number": "12",
"title": "12. Approval of DSM programme Document.",
"chapter": null,
"content": "(i) Description of the programme;\n(ii) Objective and rationale for the programme;\n(iii) Consumer segments and estimated level of participation;\n(iv) Estimate of baseline;\n(v) Assessment of programme in line with Cost Effectiveness Guidelines issued by the Commission;\n(vi) Mechanism for recovery of cost and performance incentives;\n(vii) Marketing, delivery strategy and Implementation schedule;\n(viii) Implementation mechanism e.g. Energy Service Companies, DSM Bidding, DSM Resource Acquisition, etc;\n(ix) Monitoring and evaluation plan; and\n(x) Plan for Training/ Seminars/ Workshops to increase consumer awareness.",
"footnote": "",
"is_definition": false,
"sort_order": 11
},
"prev_section": "11",
"next_section": "13"
}