563. Preparation of estimates for the purpose of Administrative approval.

(b) As a rule, rough plans and estimates only will be prepared in the first instance if the work is likely to cost more than Rs. 5,000 unless there is a likelihood of funds being available in the course of the year and the work is within the power of administrative approval of the Director. A requisition estimate need only be prepared for works costing less than Rs. 1,000 while a detailed plan and estimate will be likely to be available within a reasonable period, otherwise rough plans and estimates only will be prepared.
(c) The Chief Engineer, Public Health Engineering Department and Executive Engineer, a District Engineer or the Electrical Inspector should not prepare rough or detailed plans and estimates for works which appear to him to be of an abnormal nature, or which are not usually allowed. When requests for such works are received, he should obtain the orders of Government through his departmental superiors before taking any further action.
(P. W. D. Resolution no. 7329-A, dated the 31st August, 1937.)