(a) administrative approval has been accorded by the competent authority; and
(b) the report prefacing the estimates and the principal plans attached thereto have been countersigned by the Director-
Rs.
(1)
Superintending Engineer
..
..
10,000 for each work
(2)
Electric Inspector, Bihar
..
..
20,000 for each work
(3)
All Executive Engineers
..
..
5,000 for each work
Note. - (1) The above limits exclude departmental charges.
(2) These powers apply to deposit works also.
(P.W.D. Resolution no. 7329-A., dated the 31st August 1937. The Compendium of Financial Delegation, 1953.)
Section 561 • Bihar Education Code, 1961
561. Technical Sanction.
bihar-education-code-1961-sec-561.json
•
Section 561
{
"act_title": "Bihar Education Code, 1961",
"act_slug": "bihar-education-code-1961",
"section_label": "Section",
"section": {
"number": "561",
"title": "561. Technical Sanction.",
"chapter": null,
"content": "(a) administrative approval has been accorded by the competent authority; and\n(b) the report prefacing the estimates and the principal plans attached thereto have been countersigned by the Director-\nRs.\n(1)\nSuperintending Engineer\n..\n..\n10,000 for each work\n(2)\nElectric Inspector, Bihar\n..\n..\n20,000 for each work\n(3)\nAll Executive Engineers\n..\n..\n5,000 for each work\nNote. - (1) The above limits exclude departmental charges.\n(2) These powers apply to deposit works also.\n(P.W.D. Resolution no. 7329-A., dated the 31st August 1937. The Compendium of Financial Delegation, 1953.)",
"footnote": "",
"is_definition": false,
"sort_order": 600
},
"prev_section": "560",
"next_section": "562"
}