6. Grant or rejection of registration of the project.

6-A Grant of Registration of the Project. - (1) On receipt of the Application, the Authority or, as the case may be, the officer authorized by him shall enter the particulars of the Application in the Register of Applications to be maintained by the Authority in Form - Q and shall give Serial Number to the Application and endorse on every application the date on which it is presented and shall sign the endorsement.
6-A Grant of Registration of the Project.
(2) The Authority shall, within (30) working days from the date of receiving the application for the registration of the Project, scrutinize the Application and register the Project along with the Promoter if it is satisfied that,-
(a) the Project meets the criteria as laid down by the Act and rules made thereunder,
(b) the Project has all the necessary permissions as required under any law for the time being in force and is in consonance with the provisions of the Act and rules made thereunder and the regulations made by the Authority; and
(c) The Promoter has appropriate financial, technical, construction and management capacity to execute and complete the proposed Project.
(3) Upon registration of a project, the Authority shall issue a Certificate of Registration as per Form - C, with Registration Number to the Project along with the name of the Promoter.
(4) The Certificate of Registration shall be issued to the Promoter as well as the concerned authority that has sanctioned the plan for construction of building under any law for the time being in force.
(5) The Authority shall provide access to the Promoter to its Website by issuing a login ID and a Password for further uploading of all information as required by the Act and Rules.
(6) The names of Promoter and the registered Project shall be entered in a register to be maintained by the Authority in such manner as may be determined by it, by regulations.
(7) The Authority may, without prejudice to the generality of sub rules (3) and (4), require any guarantee, indemnity, undertaking or such other security to be furnished by Promoter before granting Certificate of Registration as may be deemed necessary to satisfy itself in respect of the requirements contemplated in sub-rules (3) and (4).
(8) The registration and the Login Id as well as Pass word granted to the promoter shall be valid for a period declared by the Promoter under sub clause (C) of clause (l) of sub-section (2) of section 4 of the Act for completion of the project or phase thereof, as the case may be.
6-B Refusal of Registration of the Project. - (1) If the Authority, on receipt of application for registration of the Project, is of the opinion that the registration shall be refused for non-submission of necessary documents along with the Application or incomplete Application, it shall issue a notice to the Promoter in writing mentioning details of documents which are not submitted along with the Application and give such time as the Authority may deem fit and proper for submission of the documents and completion of Application;
6-B Refusal of Registration of the Project.
(2) If the promoter fails or neglect to submit the necessary documents called by the Authority within period stipulated in the notice, then the Authority shall after giving opportunity of hearing to the promoter refuse to grant registration of the project;
(3) If the Authority, on receipt of application/documents for registration of the Project, is of the opinion that the registration shall be refused on certain reasons, it shall issue a notice to the Promoter in writing mentioning its intention to reject the application and the reasons therefor calling upon promoter to give reasons as to why his registration shall not be refused on the grounds mentioned in the notice within period specified in the notice;
(4) The Promoter shall file his reply to notice within time stipulated in the said notice through himself or through his Authorised Representative or Legal Representative;
(5) Pending consideration of the Application for registration of project by the Authority, the Promoter shall not make any advertisement for sale of Project or create any third party interest in the project;
(6) If the Authority on considering the representations of the Promoter, is of the view that the Promoter has not met the requirements of section 4 of the Act or Rules satisfactorily, it shall reject the application by a assigning reasons as per Form - D and convey its decision to Promoter so also to the concerned Authority who has sanctioned the project under any law for the time being in force.