(ii) The owner shall submit a notice of completion through the registered architect and licenced builder/developer along with prescribed documents and plans to the Sanctioning Authority. The Sanctioning Authority on receipt of such notice of completion shall undertake inspection with regard to the following aspects:
(a) Number of floors
(b) External setbacks
(c) Parking space provision
(d) Abutting road width and shall communicate the approval or refusal of the Occupancy Certificate within 15 days or may issue the same after levying and collecting compounding fee, if any, as follows:
(iii) The sanctioning authority is empowered to compound the offence in relation to setbacks violations (other than the front setback) upto 10%, duly recording thereon the deviations in writing. This provision is made to take care of unintentional and minor violations in setbacks by the individual plot owners. The rate of Compounding fee shall be a minimum rate of Rs.500 per sq mt, and the Government may revise this rate from time to time. Compounding of such violation shall not be considered for buildings constructed without obtaining any sanctioned plan. These fees shall be maintained in a separate escrow account and utilised towards improvement of the roads and public open spaces development in the area.
(iv) For all high rise buildings, the work shall be subject to inspection by the Fire service Department and the Occupancy Certificate shall be issued only after clearance from the Fire Services Department with regard to Fire Safety and Protection requirements.
(v) The functional/line agencies dealing with electric power, water supply, drainage and sewerage shall not give regular connections to the building unless such Occupancy Certificate is produced, or alternatively may charge 3 times the rate till such time Occupation Certificate is produced. This condition shall also be applicable to all unauthorized constructions and buildings constructed without sanctioned building plan. In addition to the above, the local body shall collect every year two times the property tax as penalty from the owner/occupier till such time the Occupation Certificate obtained.
(vi) The Registration Authority shall register only the permitted built up area as per the sanctioned building plan and only upon producing and filing a copy of such sanctioned building plan. On the Registration Document it should be clearly mentioned that the registration is in accordance with the sanctioned building plan in respect of setbacks and number of floors.
(vii) The financial agencies/institutions shall extend loan facilities only to the permitted built up area as per the sanctioned building plan.
Section 22 • Andhra Pradesh Municipalities Development Control Rules, 2008
22. Occupancy Certificate.
andhra-pradesh-municipalities-development-control-rules-2008-sec-22.json
•
Section 22
{
"act_title": "Andhra Pradesh Municipalities Development Control Rules, 2008",
"act_slug": "andhra-pradesh-municipalities-development-control-rules-2008",
"section_label": "Section",
"section": {
"number": "22",
"title": "22. Occupancy Certificate.",
"chapter": null,
"content": "(ii) The owner shall submit a notice of completion through the registered architect and licenced builder/developer along with prescribed documents and plans to the Sanctioning Authority. The Sanctioning Authority on receipt of such notice of completion shall undertake inspection with regard to the following aspects:\n(a) Number of floors\n(b) External setbacks\n(c) Parking space provision\n(d) Abutting road width and shall communicate the approval or refusal of the Occupancy Certificate within 15 days or may issue the same after levying and collecting compounding fee, if any, as follows:\n(iii) The sanctioning authority is empowered to compound the offence in relation to setbacks violations (other than the front setback) upto 10%, duly recording thereon the deviations in writing. This provision is made to take care of unintentional and minor violations in setbacks by the individual plot owners. The rate of Compounding fee shall be a minimum rate of Rs.500 per sq mt, and the Government may revise this rate from time to time. Compounding of such violation shall not be considered for buildings constructed without obtaining any sanctioned plan. These fees shall be maintained in a separate escrow account and utilised towards improvement of the roads and public open spaces development in the area.\n(iv) For all high rise buildings, the work shall be subject to inspection by the Fire service Department and the Occupancy Certificate shall be issued only after clearance from the Fire Services Department with regard to Fire Safety and Protection requirements.\n(v) The functional/line agencies dealing with electric power, water supply, drainage and sewerage shall not give regular connections to the building unless such Occupancy Certificate is produced, or alternatively may charge 3 times the rate till such time Occupation Certificate is produced. This condition shall also be applicable to all unauthorized constructions and buildings constructed without sanctioned building plan. In addition to the above, the local body shall collect every year two times the property tax as penalty from the owner/occupier till such time the Occupation Certificate obtained.\n(vi) The Registration Authority shall register only the permitted built up area as per the sanctioned building plan and only upon producing and filing a copy of such sanctioned building plan. On the Registration Document it should be clearly mentioned that the registration is in accordance with the sanctioned building plan in respect of setbacks and number of floors.\n(vii) The financial agencies/institutions shall extend loan facilities only to the permitted built up area as per the sanctioned building plan.",
"footnote": "",
"is_definition": false,
"sort_order": 20
},
"prev_section": "21",
"next_section": "23"
}