Section 12. Definitions.
Section 23. Guaranteed and Overall standards of performance.
Section 34. Compensation.
Section 45. Information on Standards of Performance.
Section 56. Exemption.
Section 67. Issue of orders and practice directions.
Section 78. Power to remove difficulties.
Section 89. Power to Amend.
Section 910. Repeal and Savings.
Section 10
andhra-pradesh-electricity-regulatory-commission-licensees-standards-of-performance-regulation-2004.json
•
10 Sections
•
Andhra Pradesh
{
"id": 14457,
"slug": "andhra-pradesh-electricity-regulatory-commission-licensees-standards-of-performance-regulation-2004",
"title": "Andhra Pradesh Electricity Regulatory Commission (Licensees' Standards of Performance) Regulation, 2004",
"short_title": "Andhra Pradesh Electricity Regulatory Commission (Licensees' Standards of Performance) Regulation, 2004",
"act_number": "(Regulation No. 7 of 2004)",
"act_year": 2004,
"act_type": "STATE",
"location": "Andhra Pradesh",
"law_status": "unknown",
"enactment_date": null,
"description": "Andhra Pradesh Electricity Regulatory Commission (Licensees' Standards of Performance) Regulation, 2004",
"preamble": "",
"section_label": "Section",
"sections": [
{
"number": "1",
"title": "1. Short title, commencement and interpretation.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": true,
"sort_order": 0
},
{
"number": "2",
"title": "2. Definitions.",
"chapter": null,
"content": "(a) \"Act\" means the Electricity Act, 2003;\n(b) \"area of supply\" means the area within which a Licensee is authorised by his License to supply electricity:\n(c) \"Commission\" means the Andhra Pradesh Electricity Regulatory Commission;\n(d) \"Cities and Towns\" mean the areas covered by all Municipal Corporations and other Municipalities including the areas falling under the various Urban Development Authorities;\n(e) \"Rural areas\" mean the areas covered by Gram Panchayats, including major and minor Panchayats;\n(f) \"Extra High Tension/Extra High Voltage\" means the voltage exceeding 33000 volts under normal conditions;\n(g) \"High Tension/High Voltage\" means the voltage exceeding 440 volts but not exceeding 33000 volts under normal conditions;\n(h) \"Licensee\" means the Distribution Licensee;\n[(i) \"Low Tension/Low Voltage\" means a voltage level which does not exceed 440 volts under normal conditions;]",
"footnote": "",
"is_definition": true,
"sort_order": 1
},
{
"number": "3",
"title": "3. Guaranteed and Overall standards of performance.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 2
},
{
"number": "4",
"title": "4. Compensation.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 3
},
{
"number": "5",
"title": "5. Information on Standards of Performance.",
"chapter": null,
"content": "(a) The levels of performance achieved by the Licensee with reference to the standards specified in Schedule - I to this Regulation:\n(b) The number of cases in which compensation was paid under clause 4 above, and the aggregate amount of the compensation payable and paid by the Licensee, and\n(c) The measures taken by the Licensee to improve performance in the areas covered by Guaranteed Standards and Licensee's assessment of the targets to be imposed for the ensuing year.\n(a) The level of performance achieved with reference to the standards specified in Scheduled I to this Regulation: and,\n(b) The measures taken by the Licensee to improve performance in the areas covered by Overall Standards and Licensee's assessment of the targets to be imposed for the ensuing year.",
"footnote": "",
"is_definition": false,
"sort_order": 4
},
{
"number": "6",
"title": "6. Exemption.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 5
},
{
"number": "7",
"title": "7. Issue of orders and practice directions.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 6
},
{
"number": "8",
"title": "8. Power to remove difficulties.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 7
},
{
"number": "9",
"title": "9. Power to Amend.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 8
},
{
"number": "10",
"title": "10. Repeal and Savings.",
"chapter": null,
"content": "Schedule - I\nGuaranteed Standards of Performance\nGuaranteed Standards of Performance\nI. Restoration of Power Supply.\n1.2 Overhead Line/Cable Breakdowns. - In case of overhead line/cable breakdowns, the Licensee shall ensure restoration of power supply within 6 hours of occurrence of breakdown in towns and cities and within 24 hours of occurrence of breakdown in rural areas.\n1.3 Underground Cable Breakdowns. - In case of breakdown of underground cable, the Licensee shall ensure restoration of power supply within 12 hours of occurrence of breakdown in towns and cities and within 48 hours of occurrence of breakdown in rural areas.\n1.4 Distribution Transformer failure. - The Licensee shall restore supply in the case of distribution transformer failures by replacement of transformer within 24 hours of receiving the complaint in towns and cities and within 48 hours of receiving the complaint in rural areas.\n1.5 Period of scheduled outages. - Interruption in power supply due to scheduled outages, other than the load-shedding, shall be notified by the Licensee at least 24 hours in advance and shall not exceed 12 hours in a day. In each such event, the Licensee shall ensure that the supply is restored by not later than 6.00 p.m.\nII. Quality of Power Supply.\n(i) The Licensee shall maintain the voltages at the point of commencement of supply to a consumer within the limits stipulated hereunder, with reference to declared voltage:\n(a) In the case of Low Voltage, +6% and -6%\n(b) In the case of High Voltage, +6% and -9%: and,\n(c) In the case of Extra High Voltage, + 10% and -12.5%.\n(ii) On receipt of a voltage fluctuation complaint, the Licensee shall verify if the voltage fluctuation is exceeding the limits specified in sub-paragraph (i) above and if confirmed, the Licensee shall\n(a) Ensure that the voltages are brought within the said limits, within 10 days of original complaint if no expansion/enhancement of network is involved:\n(b) Resolve the complaint within 120 days, if up-gradation of distribution system is required:\n2.2 Harmonics. - (i) The Licensee shall maintain the limits of harmonics as per the stages prescribed hereunder:\n2.2 Harmonics.\nState 1. - The cumulative Total Voltage Harmonic Distortion (THDv) at the Point of Commencement of Supply for each consumer connected at 132KV and above shall be limited to 3% (as per Grid Code of Andhra Pradesh).\nState 1.\nStage 2. - The cumulative Total Voltage Harmonic Distortion (THDv) at the Point of Commencement of Supply for each consumer connected at 33KV shall be limited to 8% (as per Grid Code of Andhra Pradesh).\nStage 2.\nStage 3. - The cumulative Total Voltage Harmonic Distortion (THDv) at the Point of Commencement of Supply for each consumer connected at 11KV shall be limited to 8% (as per Grid Code of Andhra Pradesh).\nStage 3.\n(ii) Stage 1 shall be effective on the expiry of one year from the date of publication of this Regulation. The Commission will notify the compensation amounts for default on this standard on commencement of Stage-I.\n(iii) The Commission will specify the effective dates for Stage 2 and Stage 3 after consultation with the Licensees.\n(iv) The assessment method for recording harmonic levels shall be as laid out in the Grid Code of Andhra Pradesh, until the Commission lays down a separate procedure.\nIII. Complaints about meters.\n3.2 The Licensee shall replace at Licensee's own cost the burnt out meters within 7 days of complaint if the burning of meter is due to causes attributable to the Licensee like high voltage, loose contacts, ageing of meter, etc. If the meter is burnt due to causes attributable to the consumer such as tampering, defect in consumer's installation, meter getting wet, connecting unauthorized additional load by the consumer, etc., the Licensee shall serve a notice to the consumer for recovery of cost of the meter within 7 days of detection and shall replace the meter within 7 days of receiving the payment from the consumer and after necessary corrective action is taken to avoid future damage to the meter.\nIV. Applications for New connections/ Additional Load.\n(i) The Licensee shall release supply to an applicant within 30 days of receipt of a complete application accompanied by prescribed fees, charges and security:\n(ii) The Licensee shall keep the fees, charges and security payable by the applicants for new connections notified and also specify the same on the application form.\n4.2 Cases where power supply requires extension of distribution mains\n(i) The Licensee shall acknowledge the receipt of the application within 2 days and shall intimate to the applicant in writing, the amount of security and other charges payable within 7, 15, 30 and 45 days of receipt of application for Low Tension, High Tension! 11KV), High Tension (33KV) and Extra High Tension (above 33 KV) respectively.\n(ii) The supply of electricity in such cases shall be effected by the Licensee within the time limits specified hereunder:\nVoltage of supply\nVoltage of supply\nPeriod from date of payment of required\n\t\t\t\t\tsecurity and other charges, within which supply of electricity\n\t\t\t\t\tshould be provided\nPeriod from date of payment of required\n\t\t\t\t\tsecurity and other charges, within which supply of electricity\n\t\t\t\t\tshould be provided\nLow Tension\n30 days\nHigh Tension -\n\t\t\t\t\t11000 Volts\n60 days\nHigh Tension -\n\t\t\t\t\t33000 Volts\n90 days\nExtra High Tension\n\t\t\t\t\t- Above 330000 Volts\n180 days\n4.3 Erection of substation to extend supply. - In cases of application for new connection, where extension of supply requires erection and commissioning of new 33/11 KV substation, the distribution Licensee shall submit to the Commission within 15 days of receipt of such application, a proposal for erection ofsuch33/11 KV substation together with the time required for erecting and commissioning the substation, and get the same approved by the Commission. The Licensee shall commence power supply to the applicant within the time period so approved by the Commission:\n(a) Title transfer of ownership\n(b) Change of category\n(c) Conversion from Low Tension single phase to Low Tension 3-phase and vice-versa\n(d) Conversion from Low Tension to High Tension and vice-versa\nVI. Complaints about consumer's bills.\n4.4 The Licensee shall not, however, be held responsible for the delay, if any, in extending supply, if the same is on account of problems relating to statutory clearances, right of way, acquisition of land, or the delay in consumer's obligation to obtain approval of Chief Electrical Inspector to Government for his High Tension or Extra High Tension installation, etc. over which Licensee has no reasonable control.\nV. Transfer of ownership and conversion of services.\n- within 7 days of receipt of application, with necessary documents and prescribed fee, if any\n- within 30 days from the date of payment of necessary charges by the consumer\n- within 60 days from the date of payment of necessary charges by the consumer\n(ii) In case the complaint is genuine and revision of bill already issued becomes necessary, the due date for payment of bill shall be reckoned from the date of revised bill for the purpose of disconnection of supply or for levy of additional charges for belated payment.\n6.2 Reconnection of supply following disconnection due to non-payment of bills. - The Licensee shall restore power supply to a consumer, whose supply has been disconnected due to non-payment of electricity bills, within 4 working hours of receipt of production of proof of payment by the consumer in towns and cities, and within 12 working hours of production of proof of payment by the consumer in rural areas.\nSchedule II\nGuaranteed Standards of Performance and Compensation To Consumers In Case of Default\nGuaranteed Standards of Performance and Compensation To Consumers In Case of Default\nCompensation payable\n\t\t\t\tin case of violation of Standard\nCompensation payable\n\t\t\t\tto individual consumer if the event affects a single consumer\nCompensation payable\n\t\t\t\tto individual consumer if the event affects more than one\n\t\t\t\tconsumer\nService Area\nService Area\nStandard\nStandard\nNormal Fuse-off\nNormal Fuse-off\nRs. 50 in each case\n\t\t\t\tof default\nRs. 25 to each\n\t\t\t\tconsumer affected\nCities\n\t\t\t\tand towns\nRural areas\nWithin\n\t\t\t\t4 working hours\nWithin 12 working\n\t\t\t\thours\nOverhead Line/cable breakdowns\nOverhead Line/cable breakdowns\nRs. 50 in each case\n\t\t\t\tof default\nRs. 25 to each\n\t\t\t\tconsumer affected\nCities\n\t\t\t\tand towns\nRural areas\nWithin\n\t\t\t\t6 hours\nWithin 24 hours\nUnderground cable breakdowns\nUnderground cable breakdowns\nRs. 50 in each case\n\t\t\t\tof default\nRs. 25 to each\n\t\t\t\tconsumer affected\nCities\n\t\t\t\tand towns\nRural areas\nWithin\n\t\t\t\t12 hours\nWithin 48 hours\nDistribution Transformer failure\nDistribution Transformer failure\nRs. 100 in each case\n\t\t\t\tof default\nRs. 50 to each\n\t\t\t\tconsumer affected\nCities\n\t\t\t\tand towns\nRural areas\nWithin\n\t\t\t\t24 hours\nWithin 48 hours\nPeriod of Scheduled Outage\nPeriod of Scheduled Outage\nRs. 100 in each case\n\t\t\t\tof default\nRs. 50 to each\n\t\t\t\tconsumer affected\nMaximum\n\t\t\t\tduration in a single stretch\nRestoration of\n\t\t\t\tsupply\nNot\n\t\t\t\tto exceed 12 hours\nBy not later than\n\t\t\t\t6.00 p.m.\nVoltage fluctuations\nVoltage fluctuations\nRs. 50 for each day\n\t\t\t\tof default\nRs. 25 to each\n\t\t\t\tconsumer affected for each day of default\nNo\n\t\t\t\texpansion/enhancement of network involved\nWithin 10 days\nUp-gradation of\n\t\t\t\tdistribution system required\nWithin 120 days\nRs. 100 for each day\n\t\t\t\tof default\nRs. 50 to each\n\t\t\t\tconsumer affected for each day of default\nErection of\n\t\t\t\tSubstation\nWithin the time\n\t\t\t\tperiod as approved by the Commission\nRs. 250 for each day\n\t\t\t\tof default\nRs. 125 to each\n\t\t\t\tconsumer affected for each day of default\nMeter complaints\nMeter complaints\nRs. 50 for each day\n\t\t\t\tof default\nNot Applicable\nInspection and\n\t\t\t\treplacement of slow, fast/creeping, stuck-up meters\nInspection within 7\n\t\t\t\tdays in towns and cities and within 15 days in rural areas and\n\t\t\t\treplacement within 15 days thereafter.\nReplace\n\t\t\t\tburnt meters if cause attributable to Licensee\nReplace burnt meters\n\t\t\t\tif cause attributable to consumer\nWithin\n\t\t\t\t7 days\nWithin 7 days of\n\t\t\t\treceiving payment from consumer\nRs. 50 for each day\n\t\t\t\tof default\nNot\n\t\t\t\tApplicable\nNot Applicable\nApplication of new connection/additional load\n\t\t\t\tConnection feasible from existing network\nApplication of new connection/additional load\n\t\t\t\tConnection feasible from existing network\nRs. 50 for each day\n\t\t\t\tof default\nNot Applicable\nRelease of supply\nWithin 30 days of\n\t\t\t\treceipt of application (along-with prescribed charges)\nNetwork expansion/enhancement required to\n\t\t\t\trelease supply\nNetwork expansion/enhancement required to\n\t\t\t\trelease supply\nRs.\n\t\t\t\t50 for each day of default\nRs.\n\t\t\t\t250 for each day of default\nRs. 500 for each day\n\t\t\t\tof default\nNot Applicable\nRelease\n\t\t\t\tof supply - Low Tension\nRelease\n\t\t\t\tof Supply - High Tension 11KV\nRelease\n\t\t\t\tof Supply - High Tension 33 KV\nRelease\n\t\t\t\tof Supply - Extra High Tension\nErection of\n\t\t\t\tsubstation required for release of supply\nWithin\n\t\t\t\t30 days of receipt of prescribed charges\nWithin\n\t\t\t\t60 days of receipt of prescribed charges\nWithin\n\t\t\t\t90 days of receipt of prescribed charges\nWithin\n\t\t\t\t180 days of receipt of prescribed charges\nWithin the time\n\t\t\t\tperiod approved by the Commission\nTransfer of ownership and conversion of\n\t\t\t\tservices\nTransfer of ownership and conversion of\n\t\t\t\tservices\nRs.\n\t\t\t\t50 for each day of default\nRs. 100 for each day\n\t\t\t\tof default\nNot Applicable\nTitle\n\t\t\t\ttransfer of ownership\nChange\n\t\t\t\tof category\nConversion\n\t\t\t\tfrom LT I-ph to LT 3-ph and vice-versa\nConversion from LT\n\t\t\t\tto HT and vice-versa\nWithin\n\t\t\t\t7 days along-with necessary documents and prescribed fee, if any\nWithin\n\t\t\t\t7 days along-with necessary documents and prescribed fee, if any\nWithin\n\t\t\t\t30 days of payment of charges by the consumer\nWithin 60 days of\n\t\t\t\tpayment of charges by the consumer\nResolution of complaints on consumer's bill\nResolution of complaints on consumer's bill\nRs. 25 for each day\n\t\t\t\tof default\nNot Applicable\nIf\n\t\t\t\tadditional information is required\nIf no additional\n\t\t\t\tinformation is required\nWithin\n\t\t\t\t24 working hours of receipt of complaint\nWithin 7 working\n\t\t\t\tdays of receipt of complaint\nReconnection of supply following\n\t\t\t\tdisconnection due to non-payment of bills\nReconnection of supply following\n\t\t\t\tdisconnection due to non-payment of bills\nRs. 50 in each case\n\t\t\t\tof default\nNot Applicable\nCities\n\t\t\t\tand Towns\nRural Areas\nWithin\n\t\t\t\t4 working hours of production of proof of payment by consumer\nWithin 12 working\n\t\t\t\thours of production of proof of payment by consumer\nManner of payment of compensation amount.\nSchedule III\nOverall Standards of Performance\n1.1 Normal fuse-off calls.\n1.2 Line Breakdowns.\n1.3 Distribution Transformer Failures.\n1.4 Period of scheduled outages.\n1.5 Street Light faults\n1.5.1 The Licensee shall rectify line faults and restore streetlights within 24 hours of detection or receipt of complaint, whichever is earlier, and shall achieve this standard of performance in at least 90% of the cases.\n1.5.2 In case of a fused light or defective unit, the Licensee, wherever responsible for maintenance of street lights, shall replace the light or rectify/replace the unit within 24 hours of detection or receipt of complaint, whichever is earlier, and shall achieve this standards of performance in at least 90% of the cases.\n1.6 Reliability Indices\n(i) The following reliability/outage indices are prescribed by the Institute of Electrical and Electronics Engineers (IEEE) Standard 1366 of 1998. The Licensee shall compute and report the value of these indices from 2002-03 onwards:\n(a) System Average Interruption Frequency Index (SAIFI): The Licensee shall calculate the value as per the formula and methodology specified below.\n(b) System Average Interruption Duration Index (SAIDI): The Licensee shall calculate the value as per the formula and methodology specified below.\n(c) Momentary Average Interruption Frequency Index (MAIFI): The Licensee shall calculate the value as per the formula and methodology specified below.\nMethod to compute Distribution System Reliability Indices.\nAi = Total number of sustained interruptions (each longer than 5 minutes) on ith feeder for the month\nNi = Connected load of ith feeder affected due to each interruption\nNt = Total connected load at 11KV in the Distribution Licensee's supply area\nn = number of 11 KV feeders in the licensed area of supply (excluding those serving predominantly agricultural loads)\nNote. - The feeders must be segregated into rural and urban and the value of the indices must be reported separately for each month.\nNote.\n(i) The Licensee shall compute the value of these indices separately for feeders serving predominantly agricultural loads. The methodology for computation of indices shall remain the same as in the case of other feeders.\n(ii) Based on the information provided by the Licensees, the Commission would notify the target levels for these indices annually.\n1.7 Frequency variations.\n1.8 Voltage Unbalance.\n1.9 Billing mistakes.\n1.10 Faulty meters.\n1.11 The Summary of Overall performance standards is as follows:\nService area\nService area\nOverall Standard of Performance\nOverall Standard of Performance\nNormal fuse-off\n\t\t\t\tcalls\nAt least 99% calls\n\t\t\t\treceived should be rectified within prescribed time limits in\n\t\t\t\tboth Cities and Towns and in Rural areas\nLine Breakdowns\nAt least 95% of\n\t\t\t\tcases resolved within time limit in both Cities and Towns and in\n\t\t\t\tRural areas\nDistribution\n\t\t\t\tTransformer failure\nAt least 95% of DTRs\n\t\t\t\tto be replaced within prescribed time limits in both Cities and\n\t\t\t\tTowns and in Rural areas\nPeriod of scheduled\n\t\t\t\toutage\nMaximum duration in\n\t\t\t\ta single stretch\nAt least 95% of\n\t\t\t\tcases resolved within time limit\nRestoration of\n\t\t\t\tsupply by 6.00 p.m.\nStreet Light Faults\nRectification of\n\t\t\t\tline faults\nAt least 90% cases\n\t\t\t\tshould be complied within prescribed time limits\nReplacement of\n\t\t\t\tfused/defective unit\nContinuity indices\nSAIFI\nSAIDI\nTo be laid down\n\t\t\t\tlater by the Commission\nMAIFI\nFrequency variations\nTo maintain supply\n\t\t\t\tfrequency within 49-50.5 Hz as per IEGC.\nVoltage Unbalance\nMaximum of 3% at\n\t\t\t\tpoint of commencement of supply\n% billing mistakes\nNot exceeding 0.1%\n% faulty meters\nNot exceeding 3%",
"footnote": "",
"is_definition": false,
"sort_order": 9
}
],
"metadata": {
"Act ID": "Last Updated 26th October, 2019 [ap345]",
"Act Number": "(Regulation No. 7 of 2004)",
"Enactment Date": "",
"Act Year": "2004",
"Short Title": "Andhra Pradesh Electricity Regulatory Commission (Licensees' Standards of Performance) Regulation, 2004",
"Type": "STATE",
"Location": "Andhra Pradesh"
},
"updated_at": "2026-09-29 21:55:18"
}