    "section": {
        "number": "38",
        "title": "38. Petrochemicals\n\t\t\t\t(Basic & intermediates)",
        "chapter": null,
        "content": "[A. Effluents]\nPH\n6.5-8.5\n[*BOD (3days at\n\t\t\t\t27°C)]\n50\n**Phenol\n5\nSulphide (as S)\n2\nCOD\n250\nCyanide ( as CN)\n0.2\n***Fluoride (as F)\n15\nTotal suspended\n\t\t\t\tsolids\n1000\nHexavalent\n0.1\nChromium (as\n\t\t\t\tCR+6)]\n****Total Chromium\n\t\t\t\t(as CR)\n2.0\nB.\n\t\t\t\tEmission from Chimney/Stack\nB.\n\t\t\t\tEmission from Chimney/Stack\nLimiting\n\t\t\t\tconcentration in mg/Nm3, unless stated\nLimiting\n\t\t\t\tconcentration in mg/Nm3, unless stated\n\"(Furnace,\n\t\t\t\tBoiler, Heater, Vaporiser)\nFuel\n\t\t\t\tType\nFuel\n\t\t\t\tType\nExisting\n\t\t\t\tplants\nExisting\n\t\t\t\tplants\nNew\n\t\t\t\tPlant/Expansion of Existing Plant\nNew\n\t\t\t\tPlant/Expansion of Existing Plant\nSulphur Dioxide\n\t\t\t\t(SO2)\nGas\n50\n50\nLiquid\n1700\n850\nOxides of Nitrogen\n\t\t\t\t(NOx)\nGas\n350\n250\nLiquid\n450\n350\nParticulate Matter\n\t\t\t\t(PM)\nGas\n10\n05\nLiquid\n100\n50\nCarbon Monoxide\n\t\t\t\t(CO)\nGas\n150\n100\nLiquid\n200\n150\nNote,-\nNote,-\n(i)\n\t\t\t\tAll values shall be corrected to 3% Oxygen.\n(ii)\n\t\t\t\tWet scrubber shall necessarily be operated at the time of\n\t\t\t\tdecoking.\n(iii)\n\t\t\t\tNorms for CO shall be monitored only in case of Phthalic\n\t\t\t\tAnhydride (PA), Maleic Anhydride (MA), Terephthalic Acid (PTA)\n\t\t\t\tand Dimethyl Terephalate (DMT) Plants. Norms for CO emissions\n\t\t\t\tshall not be applicable to PA/MA manufacturing standalone\n\t\t\t\texisting piants with an installed capacity of less than 30,000\n\t\t\t\tmetric tonnes per annum, provided that such units have a\n\t\t\t\tchimney/stack of minimum 30 metres height for emitting Carbon\n\t\t\t\tMonoxide.\nProcess\n\t\t\t\tEmission (Specific Pollutant)\nProcess\n\t\t\t\tEmission (Specific Pollutant)\nSource\nSource\nLimiting\n\t\t\t\tconcentration in mg/Nm3\nLimiting\n\t\t\t\tconcentration in mg/Nm3\nExiting\n\t\t\t\tPlants\nExiting\n\t\t\t\tPlants\nNew\n\t\t\t\tPlants\nNew\n\t\t\t\tPlants\nChlorine\nEDC/VCM Plant and\n\t\t\t\tIncinerator\n10\n10\nHydrochloric Acid\n\t\t\t\tMist\nEDC/VCM Plant and\n\t\t\t\tIncinerator\n30\n30\nAmmonia\nWastewater\n\t\t\t\tstripper, acrylonitrile plant, carpolacturm plant\n75\n75\nHydrogen Sulphide\nNaphtha\n\t\t\t\tpre-treatment plant, olefin plant\n05\n05\nPhosgene\n(TDI) and (MDI)\n\t\t\t\tplant\n01\n01\nHydrogen\n\t\t\t\tCyanide(HCN)\nAcrylonitrile\n\t\t\t\tplant\n10\n10\nVOC (HAPs)-TDI and\n\t\t\t\tMDI\nTDI,\n\t\t\t\tMethylenediphenyl Di-isocyante (MDI) Plants\n0.1\n0.1\nVOC (HAPs),\n\t\t\t\tBenzene and Butadiene\nBenzene, Butadiene\n\t\t\t\tPlants\n5.0\n5.0\nVOC\n\t\t\t\t(HAPs), EO, VCM, EDC, ACN and PO\nEO, VCM, EDC, ACN,\n\t\t\t\tPO Plants\n20.0\n10.0\nOrganic\n\t\t\t\tParticulate\nPA, MA and TDI\n\t\t\t\tPlants\n50\n25\nProcess\n\t\t\t\tEmission (General Pollutant)\nProcess\n\t\t\t\tEmission (General Pollutant)\nSource\nSource\nLimiting\n\t\t\t\tconcentration in mg/Nm3\nLimiting\n\t\t\t\tconcentration in mg/Nm3\nVOC (MA, PA and\n\t\t\t\tPhenol)\nMA, PA, Phenol\n\t\t\t\tPlants\n20\nVOC (EB, Styrene,\n\t\t\t\tToluene, Xylene, Aromatics, EG and PG)\nEthyl benzene\n\t\t\t\t(EB), Styrene, Toluene, Xylene, Aromatics, EG, PG Plants\n10\nVOC (Paraffin,\n\t\t\t\tAcetone and Olefins)\nNon-methane, HC\n\t\t\t\t(paraffin), Acetone, Olefins Plants\n150\nNote. - In respect of are furnaces and induction furnaces, provision has to be made for collecting the fumes before discharging the emissions through the stack.\nNote.\nNOTE.\nC. Standards for Fugitive Emission Storage of Volatile Liquids: General Petrochemical/ Petroleum Products.\n(1) Storage tanks with capacity between 4 to 75m 3 and total vapour pressure (TVP) of more than 10 kpa should have fixed roof with pressure value vent. (2) Storage tanks with capacity between 75 to 500 m 3 and total vapour pressure (TVP) of 10 to 76 kpa should have internal floating roof or external floating roof or fixed roof with vapour control or vapour balancing system. (3) Storage tanks with the capacity of more than 500 m 3 and total vapour pressure (TVP) of 10 to 76 kpa should have internal floating roof or external floating roof or fixed roof with vapour control system. (4) The tanks with the capacity of more than 75 m 3 and total vapour pressure (TVP) of more than 76 kpa should have fixed roof with vapour control system. (5) Requirement for seals in Floating Roof Tanks- (i) (a) Internal Floating Roof Tank (IFRT) and External Floating Roof Tank (EFRT) shall be provided double seals with minimum vapour recovery of 96%. (b) Primary seal shall be liquid or shoe mounted for EFRT and vapour mounted for IFRT. Maximum seal gap width will be 4 cm and maximum gap area will be 200 cm 2 /m of tank diameter. (c) Secondary seal shall be rim mounted. Maximum seal gap width will be 1.3 cm and maximum gap area will be 20 cm 2 /m of tank diameter. (d) Material of seal and construction shall ensure high performance and durability. (ii) Fixed roof tanks shall have vapour control efficiency of 95% and vapour balancing efficiency of 90%. (iii) (a) inspection and maintenance of storage tanks shall be carried out under strict control; (b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\nC. Standards for Fugitive Emission\nC. Standards for Fugitive Emission\n(2) Storage tanks with capacity between 75 to 500 m 3 and total vapour pressure (TVP) of 10 to 76 kpa should have internal floating roof or external floating roof or fixed roof with vapour control or vapour balancing system. (3) Storage tanks with the capacity of more than 500 m 3 and total vapour pressure (TVP) of 10 to 76 kpa should have internal floating roof or external floating roof or fixed roof with vapour control system. (4) The tanks with the capacity of more than 75 m 3 and total vapour pressure (TVP) of more than 76 kpa should have fixed roof with vapour control system. (5) Requirement for seals in Floating Roof Tanks- (i) (a) Internal Floating Roof Tank (IFRT) and External Floating Roof Tank (EFRT) shall be provided double seals with minimum vapour recovery of 96%. (b) Primary seal shall be liquid or shoe mounted for EFRT and vapour mounted for IFRT. Maximum seal gap width will be 4 cm and maximum gap area will be 200 cm 2 /m of tank diameter. (c) Secondary seal shall be rim mounted. Maximum seal gap width will be 1.3 cm and maximum gap area will be 20 cm 2 /m of tank diameter. (d) Material of seal and construction shall ensure high performance and durability. (ii) Fixed roof tanks shall have vapour control efficiency of 95% and vapour balancing efficiency of 90%. (iii) (a) inspection and maintenance of storage tanks shall be carried out under strict control; (b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(3) Storage tanks with the capacity of more than 500 m 3 and total vapour pressure (TVP) of 10 to 76 kpa should have internal floating roof or external floating roof or fixed roof with vapour control system. (4) The tanks with the capacity of more than 75 m 3 and total vapour pressure (TVP) of more than 76 kpa should have fixed roof with vapour control system. (5) Requirement for seals in Floating Roof Tanks- (i) (a) Internal Floating Roof Tank (IFRT) and External Floating Roof Tank (EFRT) shall be provided double seals with minimum vapour recovery of 96%. (b) Primary seal shall be liquid or shoe mounted for EFRT and vapour mounted for IFRT. Maximum seal gap width will be 4 cm and maximum gap area will be 200 cm 2 /m of tank diameter. (c) Secondary seal shall be rim mounted. Maximum seal gap width will be 1.3 cm and maximum gap area will be 20 cm 2 /m of tank diameter. (d) Material of seal and construction shall ensure high performance and durability. (ii) Fixed roof tanks shall have vapour control efficiency of 95% and vapour balancing efficiency of 90%. (iii) (a) inspection and maintenance of storage tanks shall be carried out under strict control; (b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(4) The tanks with the capacity of more than 75 m 3 and total vapour pressure (TVP) of more than 76 kpa should have fixed roof with vapour control system. (5) Requirement for seals in Floating Roof Tanks- (i) (a) Internal Floating Roof Tank (IFRT) and External Floating Roof Tank (EFRT) shall be provided double seals with minimum vapour recovery of 96%. (b) Primary seal shall be liquid or shoe mounted for EFRT and vapour mounted for IFRT. Maximum seal gap width will be 4 cm and maximum gap area will be 200 cm 2 /m of tank diameter. (c) Secondary seal shall be rim mounted. Maximum seal gap width will be 1.3 cm and maximum gap area will be 20 cm 2 /m of tank diameter. (d) Material of seal and construction shall ensure high performance and durability. (ii) Fixed roof tanks shall have vapour control efficiency of 95% and vapour balancing efficiency of 90%. (iii) (a) inspection and maintenance of storage tanks shall be carried out under strict control; (b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(5) Requirement for seals in Floating Roof Tanks- (i) (a) Internal Floating Roof Tank (IFRT) and External Floating Roof Tank (EFRT) shall be provided double seals with minimum vapour recovery of 96%. (b) Primary seal shall be liquid or shoe mounted for EFRT and vapour mounted for IFRT. Maximum seal gap width will be 4 cm and maximum gap area will be 200 cm 2 /m of tank diameter. (c) Secondary seal shall be rim mounted. Maximum seal gap width will be 1.3 cm and maximum gap area will be 20 cm 2 /m of tank diameter. (d) Material of seal and construction shall ensure high performance and durability. (ii) Fixed roof tanks shall have vapour control efficiency of 95% and vapour balancing efficiency of 90%. (iii) (a) inspection and maintenance of storage tanks shall be carried out under strict control; (b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(i) (a) Internal Floating Roof Tank (IFRT) and External Floating Roof Tank (EFRT) shall be provided double seals with minimum vapour recovery of 96%. (b) Primary seal shall be liquid or shoe mounted for EFRT and vapour mounted for IFRT. Maximum seal gap width will be 4 cm and maximum gap area will be 200 cm 2 /m of tank diameter. (c) Secondary seal shall be rim mounted. Maximum seal gap width will be 1.3 cm and maximum gap area will be 20 cm 2 /m of tank diameter. (d) Material of seal and construction shall ensure high performance and durability. (ii) Fixed roof tanks shall have vapour control efficiency of 95% and vapour balancing efficiency of 90%. (iii) (a) inspection and maintenance of storage tanks shall be carried out under strict control; (b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(i) (a) Internal Floating Roof Tank (IFRT) and External Floating Roof Tank (EFRT) shall be provided double seals with minimum vapour recovery of 96%. (b) Primary seal shall be liquid or shoe mounted for EFRT and vapour mounted for IFRT. Maximum seal gap width will be 4 cm and maximum gap area will be 200 cm 2 /m of tank diameter. (c) Secondary seal shall be rim mounted. Maximum seal gap width will be 1.3 cm and maximum gap area will be 20 cm 2 /m of tank diameter. (d) Material of seal and construction shall ensure high performance and durability. (ii) Fixed roof tanks shall have vapour control efficiency of 95% and vapour balancing efficiency of 90%. (iii) (a) inspection and maintenance of storage tanks shall be carried out under strict control; (b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(b) Primary seal shall be liquid or shoe mounted for EFRT and vapour mounted for IFRT. Maximum seal gap width will be 4 cm and maximum gap area will be 200 cm 2 /m of tank diameter. (c) Secondary seal shall be rim mounted. Maximum seal gap width will be 1.3 cm and maximum gap area will be 20 cm 2 /m of tank diameter. (d) Material of seal and construction shall ensure high performance and durability. (ii) Fixed roof tanks shall have vapour control efficiency of 95% and vapour balancing efficiency of 90%. (iii) (a) inspection and maintenance of storage tanks shall be carried out under strict control; (b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(b) Primary seal shall be liquid or shoe mounted for EFRT and vapour mounted for IFRT. Maximum seal gap width will be 4 cm and maximum gap area will be 200 cm 2 /m of tank diameter. (c) Secondary seal shall be rim mounted. Maximum seal gap width will be 1.3 cm and maximum gap area will be 20 cm 2 /m of tank diameter. (d) Material of seal and construction shall ensure high performance and durability. (ii) Fixed roof tanks shall have vapour control efficiency of 95% and vapour balancing efficiency of 90%. (iii) (a) inspection and maintenance of storage tanks shall be carried out under strict control; (b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(c) Secondary seal shall be rim mounted. Maximum seal gap width will be 1.3 cm and maximum gap area will be 20 cm 2 /m of tank diameter. (d) Material of seal and construction shall ensure high performance and durability. (ii) Fixed roof tanks shall have vapour control efficiency of 95% and vapour balancing efficiency of 90%. (iii) (a) inspection and maintenance of storage tanks shall be carried out under strict control; (b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(c) Secondary seal shall be rim mounted. Maximum seal gap width will be 1.3 cm and maximum gap area will be 20 cm 2 /m of tank diameter. (d) Material of seal and construction shall ensure high performance and durability. (ii) Fixed roof tanks shall have vapour control efficiency of 95% and vapour balancing efficiency of 90%. (iii) (a) inspection and maintenance of storage tanks shall be carried out under strict control; (b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(d) Material of seal and construction shall ensure high performance and durability. (ii) Fixed roof tanks shall have vapour control efficiency of 95% and vapour balancing efficiency of 90%. (iii) (a) inspection and maintenance of storage tanks shall be carried out under strict control; (b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(d) Material of seal and construction shall ensure high performance and durability. (ii) Fixed roof tanks shall have vapour control efficiency of 95% and vapour balancing efficiency of 90%. (iii) (a) inspection and maintenance of storage tanks shall be carried out under strict control; (b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(ii) Fixed roof tanks shall have vapour control efficiency of 95% and vapour balancing efficiency of 90%. (iii) (a) inspection and maintenance of storage tanks shall be carried out under strict control; (b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(ii) Fixed roof tanks shall have vapour control efficiency of 95% and vapour balancing efficiency of 90%. (iii) (a) inspection and maintenance of storage tanks shall be carried out under strict control; (b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(iii) (a) inspection and maintenance of storage tanks shall be carried out under strict control; (b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(iii) (a) inspection and maintenance of storage tanks shall be carried out under strict control; (b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(b) for the inspection, API RP 575 may be adopted; (c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(c) In-service inspection with regard seal gap should be carried out once in every six months and repair to be implemented in short time; and (d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(d) the possibility of on-stream repair of both shall be examined. (iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(iv) Storage tanks shall be painted with white colour shade, except for derogation of visually sensitive area.D. Storage of Benzene, VCM and ACN D. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\nD. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\nD. Storage of Benzene, VCM and ACN (i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\nD. Storage of Benzene, VCM and ACN\n(i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic compounds (VOC) shall be provided; or (ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with vapour removal efficiency of at least 99% shall be provided; or (iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be provided. (Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading) Loading of\n\t\t\t\tVolatile Products Naphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3 (i) >_\n\t\t\t\t99.5 or (ii) <_ 5 Benzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.99 or (ii) <_ 20 Toluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3 (i) >_\n\t\t\t\t99.98 or (ii) <_ 150 ]\n(Emission control\n\t\t\t\tfor Road tank, truck/Rail tank, wagon loading)\nLoading of\n\t\t\t\tVolatile Products\nNaphtha: (i)\n\t\t\t\tVOC reduction,% or (ii) Emission, gm/m3\n(i) >_\n\t\t\t\t99.5 or (ii) <_ 5\nBenzene and\n\t\t\t\tButadience: (i) VOC reduction,% or (ii) Emission, mg/m3\n(i) >_\n\t\t\t\t99.99 or (ii) <_ 20\nToluene/Xylene: (VOC)\n\t\t\t\treduction,% or (ii) Emission, mg/m3\n(i) >_\n\t\t\t\t99.98 or (ii) <_ 150\n[***]\nSr.No.\nSr.No.\nIndustry\nIndustry\nParameter\nParameter\nStandards\nStandards\n1\n1\n2\n2\n3\n3\n4\n4\n39\nHotel\n\t\t\t\tIndustry\nEffluent\n\t\t\t\tStandards\n(i) Hotel with atleast 20 bedrooms\nlimiting concentration in mg/1, except for pH\nInland Surface Water\nOn land for Irrigation\npH\n5.5-9.0\n5.5-9.0\nBOD 3days, 27 0 C\n30\n100\nTotal Suspended Solids\n50\n100\nOil & Grease\n10\n10\nPhosphate as P\n1\n-\n(ii) Hotel with less than 20 bedrooms or a\n\t\t\t\tBanquet Hall with minimum floor area of 100 m 2 or a Restaurant\n\t\t\t\twith minimum seating capacity of 36\npH\n5.5-9.0\n5.5-9.0\nBOD 3days, 27 0 C\n100\n100\nTotal Suspended Solids\n100\n100\nOil & Grease\n10\n10\nNotes:\ni. Hotels, banquet\n\t\t\t\thalls, restaurants, etc. located in coastal area shall also\n\t\t\t\tcomply with the provisions of the Coastal Regulation Zone, as\n\t\t\t\tapplicable\nii. If, the effluent\n\t\t\t\tis discharged into a municipal sewer leading to a Sewage\n\t\t\t\tTreatment Plant, the hotel or restaurant or banquet hall, as the\n\t\t\t\tcase may be, shall provide a proper Oil and Grease Trap for\n\t\t\t\teffluent arising from its kitchen and laundry and shall have to\n\t\t\t\tcomply with the 'General Standards for Discharge of Environmental\n\t\t\t\tPollutants Part-A: Effluents' notified under Schedule-VI\nOLD LAW  ▼\nOLD LAW  ▼\n\"39. Pharmaceutical Manufacturing and Formulation Industry Effluents 1. pH 5.5-9.0 2. Oil and Grease 10 3. Total Suspended solids 100 4. [BOD (3 days at 27°C)] 30 5. Bio-assay test 90% survival of fish after 96 hrs. in 100% effluent 6. Mercury 0.01 7. Arsenic Chromium 0.20 8. Chromium (Hexavalent) 0.10 9. Lead 0.10 10. Cyanide 0.10 11. Phenolics (as C 6 H 5 OH) 1.00 12. Sulphides (as S) 2.00 13. Phosphates (as P) 5.00\nNote.\nS.No.\nS.No.\nIndustry\nIndustry\nParameter\nParameter\nStandard\nStandard\n(1)\n(1)\n(2)\n(2)\n(3)\n(3)\n(4)\n(4)\nA.\n\t\t\t\tEmission Standards\nA.\n\t\t\t\tEmission Standards\n40\nPesticide Industry\nLimiting\n\t\t\t\tconcentration in mg/Nm3\nHCI\n20\nCl 2\n5\nH 2 S\n5\nP 2 O 5 as H 3 PO 4\n10\nNH 3\n30\nPesticides\n\t\t\t\tcompounds in the form of particulate matter\n20\nCH 3 CI\n20\nHBr\n5\nB.\n\t\t\t\tEffluent Standards\nB.\n\t\t\t\tEffluent Standards\nLimiting\n\t\t\t\tconcentration in mg/l, except for pH and Bioassay test\n(i)\n\t\t\t\tCompulsory Parameters\npH\n6.5-8.5\nBOD, 3 days, 27°C\nFormulation unit\n30\nTechnical graed\n\t\t\t\tunit\n100\nOil\n\t\t\t\tand Grease\n10\nSuspended\n\t\t\t\tSolids\n100\nBioassay\n\t\t\t\tTest\n90\n\t\t\t\tpercent survival of fish after 96 hours in 100% effluent*\n(ii)\n\t\t\t\tAdditional Parameters\nArsenic\n\t\t\t\t(as As)\n0.2\nCopper\n1.0\nManganese\n1.0\nMercury\n0.01\nAntimony\n\t\t\t\t(as Sb)\n0.1\nZinc\n1.0\nNickel, etc.\n\t\t\t\t(heavy metals individually)\nShall not exceed\n\t\t\t\tindividually 5 times the drinking water standards as per Bureau\n\t\t\t\tof Indian Standards\nCyanide\n\t\t\t\t(as CN)\n0.2\nNitrate\n\t\t\t\t(as NO3)\n50\nPhosphate\n\t\t\t\t(as P)\n5.0\nPhenol\n\t\t\t\tand Phenolic Compounds as C6H5OH\n1.0\nSulphur\n0.03\nBenzene\n\t\t\t\tHexachloride (BHC)\n0.01\nCarbonyl\n0.01\nCopper\n\t\t\t\tOxychloride\n9.6\nDDT\n0.01\nDimethoate\n0.45\n24D\n0.4\nEndosulfan\n0.01\nFenitothrion\n0.01\nMalathion\n0.01\nMethyl\n\t\t\t\tparathion\n0.01\nParaquat\n2.3\nPhenathoate\n0.01\nPhorate\n0.01\nProponil\n7.3\nPyrethrums\n0.01\nZiram\n1.0\nOther\n\t\t\t\tPesticide (individually)\n0.10\n*Bioassay Test\n\t\t\t\tshall be carried out as per IS: (6582-1971). Note: 1. The concerned State Pollution Control Board/Pollution Control\n\t\t\t\tCommittee shall prescribe limits of Total Dissolved Solids (TDS),\n\t\t\t\tSulphates and Chlorides depending on the usages of recipient\n\t\t\t\twater body in down stream, in which effluent shall be disposed\n\t\t\t\toff. 2. No limit for chemical Oxygen Demand (COD) is\n\t\t\t\tprescribed but, COD in the treated effluent shall be monitored.\n\t\t\t\tIf COD is persistently reported more than 250 mg/l, the\n\t\t\t\tindustrial units discharging such an effluent shall be required\n\t\t\t\tto identify chemical causing the same. In case, these are found\n\t\t\t\tto be toxic, as defined in Schedule I of the Manufacture, Storage\n\t\t\t\tand Import of Hazardous Chemicals Rules, 1989, the concerned\n\t\t\t\tState Pollution Control Board/Pollution Control Committee in such\n\t\t\t\tcases shall direct the industries to install tertiary treatment\n\t\t\t\tsystem by 31st MArch, 2012. 3. Parameters listed as\n\t\t\t\t\"Additional parameters\" shall be prescribed depending\n\t\t\t\tupon the process and product, on a case basis.\nNote:\nC.\n\t\t\t\tEmission Standards for Incinerator\nC.\n\t\t\t\tEmission Standards for Incinerator\nLimiting\n\t\t\t\tconcentration in mg/Nm3, unless stated\nSampling Duration\n\t\t\t\tin minutes, unless stated\nParticulate\n\t\t\t\tMatter\n50\n30 or more (for\n\t\t\t\tsampling of 300 litres of emission)\nHCI\n50\n30\nSO2\n200\n30\nCO\n100\nDaily\n\t\t\t\taverage\nTotal\n\t\t\t\torganic Carbon\n20\n30\nTotal Dioxins and\n\t\t\t\tFurans*\nExisting\n\t\t\t\tIncinerator\n0.2\n\t\t\t\tng TEQ//Nm3\n8\n\t\t\t\thours\nNew Incinerator\n0.1\n\t\t\t\tng TEQ/NM3\n8\n\t\t\t\thours\nSb+As+Pb+Cr+Co+Cu+Mn+Ni+V\n\t\t\t\tand their compounds\n1.5\n2\n\t\t\t\thours\n*The existing\n\t\t\t\tplant shall comply with norms for Dioxins and Furans as 0.1 ng\n\t\t\t\tTEQ/Nm3 by 18th August, 2013. Note : i. All\n\t\t\t\tmonitored values shall be corrected to 11% oxygen on dry\n\t\t\t\tbasis. ii. The CO2 concentration in tail gas shall not be less\n\t\t\t\tthan 7%. iii. In case, halogenated organic waste is less than 1%\n\t\t\t\tby weight in input waste, all the facilities in single chamber\n\t\t\t\tincinerators shall be designed so as to achieve a minimum\n\t\t\t\ttemperature of 1100°C in the incinerator. For fluidized bed\n\t\t\t\ttechnology based incinerator, temperature shall be maintained at\n\t\t\t\t950°C. iv. In case, halogenated organic waste is less than\n\t\t\t\t1% by weight in input waste, waste shall be incinerated only in\n\t\t\t\ttwin chamber incinerators and all the facilities shall be\n\t\t\t\tdesigned to achieve a minimum temperature of 850±25°C\n\t\t\t\tin primary chamber and 1100°C in secondary combustion chamber\n\t\t\t\twith a gas residence time in secondary combustion chamber not\n\t\t\t\tless than two seconds. v. Scrubber meant for scrubbing\n\t\t\t\temissions shall not be used as quencher. vi. Incineration plants\n\t\t\t\tshall be operated (combustion chambers) with such temperature,\n\t\t\t\tretention time and turbulence, as to achieve Total Organic Carbon\n\t\t\t\t(TOC) content in the incineration ash and residue less than 3%,\n\t\t\t\tand their loss on ignition is less than 5% of the dry weight. In\n\t\t\t\tcase of non-conformity, ash and residue as the case may be, shal\n\t\t\t\tbe re-incinerated. vii. The incinerator shall have a chimney\n\t\t\t\tof atleast thirty metres height.\nNote :\nD.\n\t\t\t\tEffluent from Incinerator\nD.\n\t\t\t\tEffluent from Incinerator\nNote: (i)\n\t\t\t\tStormwater shall not be allowed to mix with scrubber water and/or\n\t\t\t\tfloor washings. (ii) Stormwater shall be channelized through\n\t\t\t\tseparate drains passing through a HDPE lined pit having holding\n\t\t\t\tcapacity of 10 minutes (hourly average) of rainfull.\nNote:\nE.\n\t\t\t\tStormwater\nE.\n\t\t\t\tStormwater\nNote: (i)\n\t\t\t\tStormwater shall not be allowed to mix with scrubber water and/or\n\t\t\t\tfloor washings. (ii) Stormwater shall be channelized through\n\t\t\t\tseparate drains passing through a HDPE lined pit having holding\n\t\t\t\tcapacity of 10 minutes (hourly average) of rainfall.\nNote:\nSubstituted by Notification No. G.S.R. 446(E) dated 13.6.2011 (w.e.f. 19.11.1986) OLD LAW  ▼\nSubstituted by Notification No. G.S.R. 446(E) dated 13.6.2011 (w.e.f. 19.11.1986)\nSubstituted by Notification No. G.S.R. 446(E) dated 13.6.2011 (w.e.f. 19.11.1986)\nOLD LAW  ▼",
        "footnote": "",
        "is_definition": false,
        "sort_order": 35
    },
    "prev_section": "36",
    "next_section": "40"
}