        "title": "44. Restriction on establishment of new generating stations or major additions or replacement of plant in generating stations",
        "chapter": null,
        "content": "(a) for consent to the establishment or acquisition of a new generating station, the Board-\n(i) gives to the applicant being a licensee an undertaking that it is competent to, and will, within twenty-four months from the said date, afford to him a supply of electricity sufficient for his requirements pursuant to his application; or\n(ii) shows to the applicant that the electricity required by him pursuant to his application could be more economically obtained within a reasonable time from another appropriate source;\n(b) for consent to the extension of any major unit of plant or works as aforesaid, the Board-\n(i) gives to the applicant being a licensee an undertaking that within twenty-four months from the said date either the station to which the application pertains will become a controlled station in terms of section 34, or the Board will make a declaration to the applicant in terms of section 35 offering him a supply of electricity sufficient for his requirements pursuant to his application, or the Board will make a declaration to him in terms of section 36; or\n(ii) shows to the applicant that the electricity required by him pursuant to his application could be more economically obtained within a reasonable time from another appropriate source or by other appropriate means;\n(c) for consent to the replacement of any major unit of plant or works, the Board-\n(i) gives to the applicant being a licensee an undertaking that within eighteen months from the said date either the station to which the application pertains will become a controlled station in terms of section 34 or the Board will make a declaration to him in terms of section 36; or\n(ii) shows to the applicant that the electricity required by him pursuant to his application could be more economically obtained within a reasonable time from another appropriate source or by other appropriate means.",
        "footnote": "",
        "is_definition": false,
        "sort_order": 43
    },
    "prev_section": "43",
    "next_section": "45"
}