    "act_title": "The Bihar (Coal Mining) Area Development Authority Act, 1986",
    "act_slug": "the-bihar-coal-mining-area-development-authority-act-1986",
    "section_label": "Section",
    "section": {
        "number": "36",
        "title": "36. Penalty for unauthorised development or for use otherwise than in conformity with the developments.",
        "chapter": null,
        "content": "(a) in contravention of any Development Plan;\n(b) without obtaining a certificate regarding Development change under section 29(1)(a);\n(c) without permission as required under this Act;\n(d) in contravention of any condition subject to which such permission has been granted;\n(e) after the permission for development has been revoked under section 35; or\n(f) in contravention of the permission which has been modified under section 35.",
        "footnote": "",
        "is_definition": false,
        "sort_order": 35
    },
    "prev_section": "35",
    "next_section": "37"
}