        "title": "15. How to ensure that inflated demand for ports is not made by a TSP?",
        "chapter": null,
        "content": "(a) View-1: Augmentation should be based on current capacity utilization of more than 70% during network busy hour (NBH) consistently for last one week. The quantum of augmentation should be reasonable increase which should bring utilization in between the range of 50 to 70%.\n(b) View-2: Some interconnection seekers tend to project inflated demands due to their ambitious traffic projections. Catering to such inflated demands would be a costly affair, and might also lead to the creation of superfluous capacities at the port, radio and switch level as well as other wasteful investments. Therefore, it should be the responsibility of the interconnection seeker to justify the demand from a technical and commercial standpoint for the ports and it should be up to the provider to agree to the calculations given by the interconnection seeker.\n(c) View-3: To ensure that inflated demand for ports is not made by the requesting TSP, the Port Charges should be abolished. In case even after three months, average busy hour utilization of initial POI is below 10% continuously for a month, the Port Charges, as prescribed by TRAI, should be applicable on the interconnection seeker for a period of six months. In case, even after expiry of six months' period from the last POI augmentation, the average busy hour utilisation of POI remains below 30% for a month, then the TSP may withdraw such augmented port capacity.\na. Request for initial provisioning of ports: After entering into an interconnection agreement, the service provider, who made request for entering into interconnection agreement, may request the other service provider to provide such number of ports at POIs which shall meet the requirement of its outgoing and incoming traffic at the POIs for a period of three months from the date of initial interconnection.\nb. Request for augmentation of POIs: A service provider may request the other service provider for additional ports at a POI, if the projected capacity utilization of the ports at such POI, at the end of thirty days from the date of placing the request, is likely to be more than 70% of the ports at the POI and such projected capacity utilization of the ports at the POI shall be determined on the basis of the daily traffic for the preceding thirty days at the POI during busy hour: Provided that the service provider shall request for such number of additional ports which is likely to bring the capacity utilization of the ports at the POI at the end of thirty days from the date of making request, to less than 60%.",
        "footnote": "",
        "is_definition": false,
        "sort_order": 28
    },
    "prev_section": "14",
    "next_section": "16"
}