    "section": {
        "number": "7",
        "title": "7. Scrutiny fees.",
        "chapter": null,
        "content": "(i)\n(a)\nPlans submitted along with planning permission\n\t\t\t\tapplications per sq.m. of floor area of the building\nRs.2.00\n(b)\nIst revised plan per sq.m. of floor area of the\n\t\t\t\tbuilding\nRs.1.00\n(c)\n2nd revised plan per sq.m. of floor area of the\n\t\t\t\tbuilding\nRs.0.40\n(d)\n3rd revised plan per sq.m. of floor area of the\n\t\t\t\tbuilding\nRs.0.20\n(e)\nSubsequent revised plans\nNil\n(ii)\nLayouts/subdivisions, re-constitutions per sq.m.\n\t\t\t\tof land area\nRs. 1.50\n(iii)\nRe-classifications (lumpsum)\nRs.30,000 (for CMA)\nRs.20,000 (for other areas)",
        "footnote": "",
        "is_definition": false,
        "sort_order": 7
    },
    "prev_section": "6",
    "next_section": "8"
}