    "act_title": "Rajasthan Minor Mineral Concession Rules, 2017",
    "act_slug": "rajasthan-minor-mineral-concession-rules-2017",
    "section_label": "Section",
    "section": {
        "number": "51",
        "title": "51. Short term permit.",
        "chapter": null,
        "content": "(i) copy of work order or concessionary agreement;\n(ii) copy of G-Schedule or bill of quantities;\n(iii) plan and description of the area from where mineral will be excavated;\n(iv) revenue record of the area; and\n(v) consent of the khatedar in case land does not belong to the applicant.\nS.No.\nS.No.\nQuantity of mineral\nQuantity of mineral\nPermit fee (in Rs.)\nPermit fee (in Rs.)\n1\n1\n2\n2\n3\n3\n1.\nUpto ten tonnes\nTwenty\n2.\nExceeding ten tonnes and upto twenty tonnes\nFifty\n3.\nExceeding twenty tonnes and upto fifty tonnes\nHundred\n4.\nExceeding fifty tonnes and upto hundred tonnes\nOne hundred and twenty five\n5.\nExceeding hundred tonnes\nRupees one hundred and fifty + rupees fifty for\n\t\t\t\tevery additional hundred tonnes or part thereof\n(i) apply for permit along with bill of quantity or G-schedule, permit fees and opting for deduction of royalty and contribution in the District Mineral Foundation Trust fund from running bills by the department concerned. The contractor shall submit the record for the assessment, along with consumption certificate issued by the competent authority and get a no-dues certificate from the Mining Engineer or Assistant Mining Engineer concerned. If any refund has to be claimed, such application shall be submitted within thirty days of completion of the work;\n(ii) apply for permit along with bill of quantity or G-schedule, permit fees, contribution in the District Mineral Foundation Trust and royalty amount. The contractor shall submit the record for the assessment, along with consumption certificate issued by the competent authority and get a no-dues certificate from the Mining Engineer or Assistant Mining Engineer concerned;\n(iii) apply for permit along with bill of quantity or G-schedule and a self-certified undertaking stating that the entire quantity of mineral will be procured or used royalty paid:\n(iv) apply for royalty deduction from running bills to the Mining Engineer or Assistant Mining Engineer concerned along with bill of quantity or G-schedule and a self-certified undertaking stating that the entire quantity of mineral used shall be royalty paid. In such case, no assessment shall be required by the department and the deduction of royalty shall be done from the running bill by the works department concerned in following manner: -\n(a)\nFor construction/widening of roads and building\n\t\t\t\tconstruction\nThree percent of bill amount\n(b)\nFor repairing and other works\nOne and half percent of bill amount",
        "footnote": "",
        "is_definition": false,
        "sort_order": 50
    },
    "prev_section": "50",
    "next_section": "52"
}