    "act_title": "Rajasthan Enterprises Single Window Enabling and Clearance Rules, 2011",
    "act_slug": "rajasthan-enterprises-single-window-enabling-and-clearance-rules-2011",
    "section_label": "Section",
    "section": {
        "number": "10",
        "title": "10. Removal of doubt.",
        "chapter": null,
        "content": "[Schedule-I]\n( See rule 3 (1) 6 and 6(A))\nPart - A\nPart - A\nTime Limit for Various Permissions/Clearances\nTime Limit for Various Permissions/Clearances\nS. No.\nS. No.\nDepartments /Organization\nDepartments /Organization\nPermissions/ Clearances\nPermissions/ Clearances\nTime Limit (Within Working Days)\nTime Limit (Within Working Days)\n1.\nFactories and Boilers Inspectorate\n(a)\nFactory building plan approval (under the\n\t\t\t\tFactories Act, 1948)\n(i)\nFactories as defined under section 2m(ii) and\n\t\t\t\tinvolving non hazardous process as defined under rule 2(m)\n10 days\n(ii)\nOther factories\n30 days\n(b)\nFactories license\n(i)\nFactories as defined under section 2m(ii) and\n\t\t\t\tinvolving non hazardous process as defined under rule 2(m)\n7 days\n(ii)\nFactories involving non hazardous process as\n\t\t\t\tdefined under rule 2(m)\n15 days\n(iii)\nFactories involving hazardous process as defined\n\t\t\t\tunder section 2(cb)\n21 days\n(iv)\nFactories involving dangerous operations as\n\t\t\t\tdefined under section 87\n21 days\n(v)\nMAH factories as defined under Rajasthan Control\n\t\t\t\tof Major Accident Hazard Rules, 1991\n60 days\n(c)\nRenewal under Factories license\n(i)\nFactories as defined under section 2m(ii) and\n\t\t\t\tinvolving non hazardous process as defined under rule 2(m)\n7 days\n(ii)\nFactories involving non hazardous process as\n\t\t\t\tdefined under rule 2(m)\n15 days\n(iii)\nFactories involving hazardous process as defined\n\t\t\t\tunder section 2(cb)\n21 days\n(iv)\nFactories involving dangerous operations as\n\t\t\t\tdefined under section 87\n21 days\n(v)\nMAH factories as defined under Rajasthan Control\n\t\t\t\tof Major Accident Hazard Rules, 1991\n60 days\n(d)\nRegistration under Boiler Act\nAfter the receipt of complete application\n(i)\nProvisional order (under the Boilers Act, 1923)\nExempted\n(ii)\nFinal order (under the Boilers Act, 1923)\n30 days\n(e)\nRenewal under 'Registration under Boiler Act'\n(i)\nIn cases in which the Competent Person is\n\t\t\t\tempowered to issue a certificate under section 8 without further\n\t\t\t\treference.\n48 hours\n(ii)\nIn any other case\n15 days\n(f)\nSteam Pipeline Drawing approval (under the\n\t\t\t\tBoilers Act, 1923)\n15 days\n2.\nLabour Department\n(a)\nPermission for engaging contractor for labour\n\t\t\t\tUnder Contract Labour (Regulation and Abolition) Act, 1970\n(i)\nRegistration of Principal Employers\n\t\t\t\tEstablishments\n30 days\n(ii)\nIssuance of Licence to Contractor for employment\n\t\t\t\tof contract labours\n15 days\n(b)\nRegistration of Establishments under Building\n\t\t\t\tand other Construction Workers (Regulation of. Employment and\n\t\t\t\tconditions of Services) Act, 1996\n15 days\n(c)\n'Registration under Shops and Establishments\n\t\t\t\tAct'\n30 days\n(d)\nRenewal under 'Shops and Establishments Act'\n15 days\n3.\nRevenue Department\n(a)\nLand conversion - Conversion of land use under\n\t\t\t\tRajasthan Land Revenue (Conversion of Agricultural Land for Non-\n\t\t\t\tAgricultural Purposes in Rural Areas) Rules, 2007\nSending applications directly to the concerned\n\t\t\t\tDistrict Collectors under intimation to Revenue Department,\n\t\t\t\tJaipur, to save time. Revenue Department would issue on line\n\t\t\t\treceipt and update online status of the application. All\n\t\t\t\tcommunication would be addressed to PS, Revenue for early action.\n(i)\nup to 10 hectares\n60 days from submission of completed application\n\t\t\t\tto District Collector\n(ii)\nabove 10 hectares\n90 days from submission of completed application\n\t\t\t\tto State Government\n4.\nEnergy Department (All Vidhyut Vitran Nigam\n\t\t\t\tLtd.)\n(a)\nRelease Connection (where no extension in\n\t\t\t\tDistribution Mains is required) Electricity connection\n(1)\nRelease of Connection\n\t\t\t\tExplanation:\ni) If LT supply of\n\t\t\t\telectricity can be provided to a premises by existing service\n\t\t\t\tline or by laying service line up to 50 meters, from an existing\n\t\t\t\toverhead line or underground cable where a cable box, junction\n\t\t\t\tbox pillar box etc. has been provided, the distribution mains\n\t\t\t\tshall be deemed to require no extension.\nii) In case of HT supply of electricity to a\n\t\t\t\tpremises, the distribution system shall be deemed to require\n\t\t\t\taugmentation and procedure laid down in Clauses b) & c)\n\t\t\t\thereunder shall be followed.\nWithin one month of the receipt of completed\n\t\t\t\tapplication\n(b)\nSupply where distribution mains require\n\t\t\t\textension\n(1)\nNotice to the applicant to deposit additional\n\t\t\t\texpenses\nWithin one month of the receipt of application\n\t\t\t\t(for a period of one month)\n(2)\nWhere extension of distribution mains is\n\t\t\t\trequired but no additional sum is required to be deposited\nThe Nigam shall complete the extension work\n\t\t\t\twithin 15 days\n(3)\nThe Nigam shall complete the extension of\n\t\t\t\tdistribution mains within the time specified below for different\n\t\t\t\tvoltage levels after deposit of additional sum by the applicant\n(i)\nL.T. line\n15 days\n(ii)\n11 KV line-first 5\n\t\t\t\tKmp\nNext 5 Km each\n30 days\n15 days\n(iii)\n33 KV line-first 5 Km\nNext 5 Km each\n60 days\n30 days\n(iv)\n132 KV line-first 5\n\t\t\t\tKm\nNext 5 Km each\n180 days\n45 days\nNote: After extension work connection\n\t\t\t\twill be released within 15 days after inspection of the\n\t\t\t\tinstallation.\nNote:\n(c)\nSupply where new sub-station or augmentation of\n\t\t\t\ttransformer substation is required\n(1)\nSupply where new substation is to be\n\t\t\t\tcommissioned\nThe Nigam will intimate within two month of\n\t\t\t\treceipt of application, the date of commencement of work, to the\n\t\t\t\tconsumer and complete the work within time limit specified below\n(i)\n11/0.4 KV sub-station\n30 days\n(ii)\n33/11 KV sub-station\n120 days\n(iii)\nExtension of bay at 33/11 KV sub-station\n30 days\n(iv)\n132/33/11 KV sub-station\n12 month\n(v)\nExtension of bay at 132 KV sub-station\n45 days\n(2)\nSupply where augmentation of transformer\n\t\t\t\tsub-station capacity is required\n(i)\n11/0.4 KV sub-station\n15 days\n(ii)\n33/11 KV sub-station\n60 days\n(iii)\n132/33/11 KV sub-station\n6 months\nAfter commencement of work of sub-station\n(i) Intimation to the\n\t\t\t\tconsumer if any additional sum is to be deposited by the\n\t\t\t\tapplicant.\nIntimation -\nTime of deposition -\nRelease of connection -\nWithin 15 days after\n\t\t\t\tcommencement of work.\n1 month or such\n\t\t\t\textended period as the Nigam may allow.\nWithin 15 days of commissioning of substation.\n(d)\nSupply in localities where no provision for\n\t\t\t\tsupply exists\nOnce electrification of such locality is\n\t\t\t\tcompleted supply shall be provided to the applicant in accordance\n\t\t\t\twith the provisions of sub-clauses a) to c) above as may be\n\t\t\t\tapplicable to him.\n(e)\nSupply where electric line/plant is provided by\n\t\t\t\tapplicant\nThe Nigam shall provide supply of electricity\n\t\t\t\twithin 15 days of intimation given by the applicant regarding\n\t\t\t\tcompletion of work.\n5.\nRIICO\n(a)\nAllotment of plots in Industrial Areas\nForm A - 30 days Form A(Preferential) - 90 days\n(b)\nApproval of building plans\n15 Days (After receiving complete\n\t\t\t\tmodification/correction in submitted drawing )\n(c)\nWater Connection\n20 days (After receiving of complete information\n\t\t\t\t)\n6.\nUDH Department (JDA/UITs)\n(a)\n90A of Agriculture Land/ Conversion of land\n\t\t\t\tunder Rajasthan Land Revenue Rules 2012\n60 days\n(b)\nChange of Land use/Conversion of land use from\n\t\t\t\tresidential to commercial\n(i) Matters to be\n\t\t\t\tdecided at Local level committees- 60 days\n(ii) Matters to be decided at State level\n\t\t\t\tcommittees-120 days\n(c)\nIssuance of Lease Deed for institutional plots\n(i) To be issued at\n\t\t\t\tlocal level-30 days\n(ii) When approval of State Govt. is required-\n\t\t\t\t60 days\n(d)\nAllotment of\n\t\t\t\tinstitutional land except the allotment of land through\n\t\t\t\tlottery/auction and of the developed land given as compensation\n\t\t\t\tfor Government/\nSemi-Government departments/ institutions and\n\t\t\t\tacquired land - under instruction of Urban Development and Local\n\t\t\t\tSelf Department dated 4.1.2010\n90 days\n(e)\nBuilding map approval of all kinds of\n\t\t\t\tinstitutional buildings\n60 days\n7.\nLocal Self Government (LSG)\n(a)\nNOC from Fire Department\n30 Days\n(b)\n90A of Agriculture Land/ Conversion of land\n\t\t\t\tunder Rajasthan Land Revenue Rules 2012\n60 Days\n(c)\nChange of Land use/Conversion of land use from\n\t\t\t\tresidential to commercial\n(i) Matters to be\n\t\t\t\tdecided at Local level committees- 60 days\n(ii) Matters to be decided at State level\n\t\t\t\tcommittees - 120 days\n(d)\nBuilding map approval of all kinds of\n\t\t\t\tinstitutional buildings\n60 days\n8.\nPublic Health Engineering Department (PHED)\n(a)\nWater Connection\n07 days as per availability of water and after\n\t\t\t\tdeposition of all fees\n9.\nTourism Department\n(a)\nProject Approval\n45 days from the date of submission of complete\n\t\t\t\tapplication\n10.\nIndustries Department\n(a)\nIncentives under Industrial Policy/Investment\n\t\t\t\tPromotion Scheme\nAs per Schedule I(b)\nPart - B\nPart - B\nTime Limit for Incentives under RIPS-2014\nTime Limit for Incentives under RIPS-2014\nS. No.\nS. No.\nDepartment\nDepartment\nApplication for Benefits under Rajasthan\n\t\t\t\tInvestment Promotion Scheme -2014\nApplication for Benefits under Rajasthan\n\t\t\t\tInvestment Promotion Scheme -2014\nTime Limit for disposal of application\n\t\t\t\t(Decision on eligibility under RIPS-2014)\nTime Limit for disposal of application\n\t\t\t\t(Decision on eligibility under RIPS-2014)\n1.\nIndustries Department\n(a)\nExemption from stamp duty and conversion charge\n07 days from date of submission of complete\n\t\t\t\tapplication\n(b)\nExemption from land tax\n45 days from date of submission of complete\n\t\t\t\tapplication\n(c)\nInvestment subsidy and Employment subsidy\n45 days from date of submission of complete\n\t\t\t\tapplication\n(d)\nExemption from\n(8) Electricity duty\n(9) Entertainment tax\n(10) Luxury tax\n(11) Mandi fee\n(12) Entry\n\t\t\t\ttax\n45 days from date of submission of complete\n\t\t\t\tapplication\n(e)\nInterest subsidy\n45 days from date of submission of complete\n\t\t\t\tapplication\n(f)\nReimbursement of VAT\n45 days from date of submission of complete\n\t\t\t\tapplication\n(g)\nCapital subsidy on ZLD treatment plant\n45 days from date of submission of complete\n\t\t\t\tapplication\nPart - C\nPart - C\nTime Limit for Various Permissions/Clearances\nTime Limit for Various Permissions/Clearances\nS. No.\nS. No.\nOrganisation\nOrganisation\nPermissions/ Clearances\nPermissions/ Clearances\nTime Limit (Within Working Days)\nTime Limit (Within Working Days)\n1.\nRajasthan Pollution Control Board (RPCB)\n(a)\nConsent to Establish (under Water Act & Air\n\t\t\t\tAct)\n120 Days\n(b)\nConsent to Operate (under Water Act & Air\n\t\t\t\tAct)\n120 Days\n(c)\nRenewal of 'Consent to Operate (under Water Act\n\t\t\t\t& Air Act)\n120 Days\n(d)\nAuthorization under Hazardous Waste Rules\n120 Days\nSchedule-II\nSee Rule 6\nSee Rule 6\n[Part - A]\n[Part - A]\nTime Limit for Nodal Agency for State Empowered Committee/District Empowered Committee\nTime Limit for Nodal Agency for State Empowered Committee/District Empowered Committee\nS. No.\nS. No.\nTime Limit For\nTime Limit For\nTime Limit (Within Working Day)\nTime Limit (Within Working Day)\n1\n2\n3\n1\nForwarding the application received in physical\n\t\t\t\tformat from the investor ( As described in sub-rule 1 of rule 3 )\n2 days\n2\nAll Agency to place the application for\n\t\t\t\tpermission\n(i)\nbefore the concerned Empowered Committee for\n\t\t\t\tdecision in cases where the concerned competent authority has\n\t\t\t\tfailed to decide the application within the prescribed time\n\t\t\t\tlimit.\n30 days counted from last date of the time limit\n\t\t\t\tprescribed for the Competent Authority to take the decision in\n\t\t\t\tschedule I (a) & (b)\n(ii)\nbefore the chair person of the concerned\n\t\t\t\tEmpowered Committee in case the\n\t\t\t\tCommittee is unable to meet or otherwise is unable to consider\n\t\t\t\tthe application within 30 days.\n15 days counted from last date of the time limit\n\t\t\t\tprescribed for the Competent Authority to take the decision in\n\t\t\t\tschedule-II, 2 (i)\n3\nComments to be asked from the Competent\n\t\t\t\tAuthority/concerned departments or authority on application/\n\t\t\t\trequest for concessions, exemptions or relaxations or grant of\n\t\t\t\tCustomized Packages.\n7 days from the receipt of the\n\t\t\t\tapplication/request\nPart - B\nPart - B\nTime Limit for State Empowered Committee for submitting recommendations to the Council of Ministers\nTime Limit for State Empowered Committee for submitting recommendations to the Council of Ministers\nS. No.\nS. No.\nTime Limit\nTime Limit\nFor Time Limit (Within Working Day)\nFor Time Limit (Within Working Day)\n1.\nSubmission of recommendations on the\n\t\t\t\tapplication/request for concessions, exemptions or relaxations or\n\t\t\t\tgrant of Customized Packages to the Council of Ministers\n30 days\nPart - C\nPart - C\n[***]\n[Form-1]\n[Form-1]\n[See rule 3 (2)]\n[See rule 3 (2)]\nSelf - Certification\nSelf - Certification",
        "footnote": "",
        "is_definition": false,
        "sort_order": 6
    },
    "prev_section": "8",
    "next_section": "1"
}