    "act_title": "Punjab Transparency in Public Procurement Act, 2019",
    "act_slug": "punjab-transparency-in-public-procurement-act-2019",
    "section_label": "Section",
    "section": {
        "number": "8",
        "title": "8. Determination of need for procurement.",
        "chapter": null,
        "content": "(a) the scope or quantity of procurement;\n(b) the method of procurement to be followed with justification thereof;\n(c) need for pre-qualification, if any;\n(d) limitation on participation of bidders in terms of section 13, if any applicable, and justification thereof;\n(e) estimated cost of procurement;\n(f) timeline for procurement; and\n(g) any other matter as may be prescribed.",
        "footnote": "",
        "is_definition": false,
        "sort_order": 7
    },
    "prev_section": "7",
    "next_section": "9"
}