    "act_title": "Kerala Electricity Supply Code, 2005",
    "act_slug": "kerala-electricity-supply-code-2005",
    "section_label": "Section",
    "section": {
        "number": "30",
        "title": "30. Terms and Conditions of supply.",
        "chapter": null,
        "content": "(a) Application form for supply of electricity\n(b) Estimate amount for giving WP /OH service connection\n(c) Estimate amount for giving service connection  HT\n(d) Estimate amount for extension of line  Single Phase/Three Phase. LT\n(e) Estimate amount for extension of line  HT/EHT\n(f) Estimate amount for HT/EHT substation\n(g) Format of agreement for supply of electricity.\n(h) Format of installation completion report\n(i) Format of no-objection certificate\n(j) Initial Security deposit towards charges for power supply for different category of consumers (LT, HT and EHT)\n(k) Security deposit for meter/metering equipment for different category of consumers. (LT, HT and EHT)\n(l) Schedule of miscellaneous charges",
        "footnote": "",
        "is_definition": false,
        "sort_order": 40
    },
    "prev_section": "29",
    "next_section": "31"
}