    "act_title": "The Indian Electricity Act, 1910",
    "act_slug": "indian-electricity-act-1910",
    "section_label": "Section",
    "section": {
        "number": "13",
        "title": "13. Notice of new works",
        "chapter": null,
        "content": "(a) not less than one month before commencing the execution of the works [* * *]\n(b) if the repairing authority intimates to the licensee that it disapproves of such works, section or plan, or approves thereof subject to amendment, the licensee may, within one week of receiving such intimation, appeal to the State Government, whose decision, after considering the reasons given by the repairing authority for its action, shall be final;\n(c) if the repairing authority fails to give notice in writing of its approval or disapproval to the licensee within one month, it shall be deemed to have approved of the works, section and plan, and the licensee, after giving not less than forty-eight hours' notice in writing to the repairing authority, may proceed to carry out the works in accordance with the notice and the section and plan served under clause (a);\n(d) if the owner disapproves of such works, section or plan, or approves thereof subject to amendment, he may, within three weeks after the service of the notice under clause (a), serve a requisition upon the licensee demanding that any question in relation to the works or to compensation, or to the obligations of the owner to others in respect thereof, shall be determined by arbitration, and thereupon the matter shall unless settled by agreement, be determined by arbitration;\n(e) where no requisition has been served by the owner upon the licensee under clause (d), within the time named, the owner shall be deemed to have approved of the works, section and plan, and in that case, or where after a requisition for arbitration the matter has been determined by arbitration, the works may, upon payment or securing of compensation, be executed according to the notice and the section and plan, subject to such modifications as may have been determined by arbitration or agreed upon between the parties.\n(i) any other service-line so attached or intended to be so attached to a distributing main, or\n(ii) works which consist of the repair, renewal or amendment of existing works of which the character or position is not to be altered;]\n(f) where the works to be executed consist of the laying of any underground service-line immediately attached, or intended to be immediately attached, to a distributing main, the licensee shall give to the repairing authority or the owner, as the case may be, not less than forty-eight hours' notice in writing of his intention to execute such works;\n(g) where the works to be executed consist of the repair, renewal or amendment of existing works of which the character or position is not to be altered, the licensee shall, except in cases of emergency, give to the repairing authority, or to the owner, as the case may be, not less than forty-eight hours' notice in writing of his intention to execute such works, and, on the expiry of such notice, such works shall be commenced forthwith and shall be carried on with all reasonable despatch, and, if possible, both by day and by night until completed.",
        "footnote": "",
        "is_definition": false,
        "sort_order": 11
    },
    "prev_section": "12",
    "next_section": "14"
}