    "act_title": "Delhi Electricity Regulatory Commission (State Grid Code) Regulations, 2008",
    "act_slug": "delhi-electricity-regulatory-commission-state-grid-code-regulations-2008",
    "section_label": "Section",
    "section": {
        "number": "31",
        "title": "31. Scheduling and Despatch Procedure.",
        "chapter": null,
        "content": "(a) Network Security and System Operation;\n(b) System Contingencies;\n(c) Demand Estimation and Control;\n(d) Exchange of Information for Scheduling and Rescheduling including scheduling of Inter-Distribution Licensee Transfer of Power, if any;\n(e) Data requirement and verification in respect of ABT metering and accounts;\n(f) Complimentary Commercial Mechanism for ABT;\n(g) Monitoring of Generation and Drawal, keeping in view allocation of power by the Government from time to time;\n(h) Reactive Power Exchange and Pricing, if any;\n(i) Real time Voltage and Frequency Management; and\n(j) Any other relevant procedures considered appropriate by SLDC:\n(i) To switch a generator into or out of service.\n(ii) Details of Spinning Reserve to be maintained.\n(iii) To increase or decrease MVAr generation for maintaining the voltage profile.\n(iv) To begin pre-planned Black Start procedures.\n(v) To hold Generating Units on standby.",
        "footnote": "",
        "is_definition": false,
        "sort_order": 30
    },
    "prev_section": "30",
    "next_section": "32"
}