    "act_title": "Andhra Pradesh Revised Building Rules, 2008",
    "act_slug": "andhra-pradesh-revised-building-rules-2008",
    "section_label": "Section",
    "section": {
        "number": "20",
        "title": "20. Compliance by Owner for Ensuring Construction is as per Sanctioned Plan.",
        "chapter": null,
        "content": "(b) Before the release of the building sanction by the sanctioning authority, the owner of the plot/site is not only required to produce the original Sale Deed, registered under the provisions of the Indian Registration Act, 1908 for the perusal of the sanctioning authority and cross verification with the attested copy submitted with the building application, but also shall be required to demarcate the setbacks and open spaces at the site.\n(c) The owner is required to hand over the ground floor area for first floor or the second floor area, as the case may be, or 10% of the total built-up area, whichever is less, to the sanctioning authority by way of a Notarized Affidavit. The Notarized Affidavit shall be got entered by the sanctioning authority in the Prohibitory Property Watch Register of the Registration Department. Then only the Building sanction will be released and the owner shall be allowed to commence the construction.\nHowever in respect of group housing schemes like row houses/ independent houses/cluster housing/residential enclaves, 5% of the units shall be handed over to the urban development authority/ sanctioning authority by way of a Notarized Affidavit.\nIndividual buildings in plots up to 3000sq.mts. with height upto 6mts, And Industrial buildings are exempted from the above conditions.",
        "footnote": "",
        "is_definition": false,
        "sort_order": 19
    },
    "prev_section": "19",
    "next_section": "21"
}